Equipment Erection
Equipment Erection
Equipment Erection
Job specific PPE Required (check ✓ if provided, mention NA if not applicable) (Other than mandatory PPE i.e. Safety Shoes, Helmet &
Safety Goggle, Gloves)
Acid-Alkali
Hand cotton Full Body SCBA proof Hand High Voltage Electrical Hand Gloves
Gloves Harness Gloves
(FBH)
Chemical
High temperature Online Chemical Splash Cut Resistance Hand Gloves
hand gloves Respirator Suit Goggles
Online Mention Job Specific PPE (By execution
Cartridge mask Dust Mask air Mask Face Shield team)
Applicable
Sr. No. Sub activity (✓)(NA) Hazards Control Measures to be taken
Personnel Trained & experienced person to be deployed
Toolbox talk conducted
Cut Resistance gloves to be used.
Cut Injury Check the route for suitable width and turning
radius Drains should have minimum 1 meter
distance so that wheel should not plunge inside
it.
Inspect the area immediately around the load and
the route for clearance and tripping hazards.
Ensure route is clear and without any obstruction.
Inspect Farana and ensure required documents
available as per our checklist. Form no.10
available
.Puc ,Rc, Physical Work Condition Sli
Trips & Fall Of Vehicle Clear movable objects from the route
Check for uneven terrain. Clean up spills that could
1 affect foot traction
Check the Ensure hydra, farana & crane used for lifting of
intended route material only (Shifting activity strictly prohibited)
and point of Crane load chart should be available in permit or JSA
placement
flagman with road clearance
Rigging Plan should be made in the prescribed
format with due approvals as per the procedures.
Lacerations, Examine object for snags, burrs, splinters, sharp
edges, nails. Remove objects prior to lift and/or
wear cut resistant gloves for hand protection
Slip of load from hands Check object for greasy/slippery surfaces. Remove
grease prior to lifting. Wear gloves to improve grip.
Size up the load before you lift. If load is too big
Crush Injury or awkward ,Divide load up, Ask for help
Use mechanical assist device such as a hand
truck or trolley
If load will block your vision, get help of signal
man.
Misjudgment due to blocked
Ensure valid TPI certificate for all lifting
vision.
equipment’s and tools and tackles.
Non Compliance of rules
Crane checklist should be available with
. permit .Crane inspection validity and checking
frequency should be available in checklist
Use of certified lifting tools. Form no 10 for
farna/man/crane required.
4 Lowering the
Load Certified persons slinging and operating crane
Load Filing on workers and Lift area suitably barricaded. Suitable capacity
/or public due to crane crane for the job.
overturning All rigging will be inspected prior to use. The unit
will be picked according to manufacturer's
Electric Shock recommendations.
Avoid sudden raising and lowering of the boom
as it makes the crane prone to tipping over.
Ensure no parts from crane enter the electrical
danger zone
Pinch point.
Toppling of
crane/Hydra/Farana
6 Housekeeping Remove the Unwanted Materials from workplace
at
workplace Fall of person or material Barricade the area properly
Ensure that workplace is dry & non slippery, free from
spillage / leakage / obstacle
Material or person may fall Ensure environmental condition is good - no rainfall
due to wet, slippery or oily or direct expose of gas or steam vent.
surface.
Additional Precaution to be taken:
Legends (*): Mandatory (hand written) to write at least 1 job specific and work condition hazard and their control measures. In case of no
job specific hazard, please write "No Job specific hazard identified". (**): In case, new sub activity found on job site, write it's job
specific and work condition hazard and their control measures. Else write NA.
Declaration: I/We hereby declare that, I/we have identified & understood all the possible hazards while performing the job (including job / site specific) and adequate
control measures have been mentioned (including job specific). Same have been explained to execution team members.
Review By
Approved by
JSA prepare
Accepted By
Follow By
Other By