SF - FDA - 407-01 FD&FA Contract Checklist
Requirement Returned
Form Associated by Date Done
Ref Paperwork Activity New Mod Takeover Technician or N/A Initial
SF_407 Contract Checklist Contract file made up and Contract Checklist inserted Y Y Y
ENQUIRY
Copy client enquiry drawings in file P P P
Copy client enquiry specification in file P P P
Copy client enquiry documents (other) in file P P P
SALES
Surveyors pack produced as below Y Y Y
SF_420 Survey & Design Report FD&FA Design Checklist Y Y N
SF_471 MSRA Complete H&S MSRA Y Y Y
SF_459 Drawing Register Drawing register completed Y Y Y
SF_401 Specification Template Specification submitted (reviewed by sales) Y P P
Estimate Sheet Fire Estimate Sheet Y Y Y
SF_406 Design battery calculation in file Y Y Y
Signed acceptance / order / letter (reviewed by sales) Y Y Y
SF_474 Customer Order Acceptance Order acceptance sent to customer Y Y Y
COMMUNICATIONS
SF_464 Keyholders forms sent to client P P P
Keyholders forms sent to ARC P P P
URN application made to Fire & Rescue Service P P P
URN No received P P P
System connected to ARC P P P
ARC connection confirmation received P P P
INSTALLATION
Date agreed for works and recorded in diary Y Y Y
Prepare technicians job pack as below Y Y Y
SF_471 MSRA Copy of sales completed MSRA Y Y Y
SF_424 Commissioning Checklist (to be signed by engineer) Y Y Y
SF_421 Schedule of Test Results (to be completed by Engineer) N N Y
SF_422 Standby Power Supply Capacity (to be completed by Engineer) N N Y
SF_478 Battery Labels Y Y Y
Log Book (to be left with customer) Y Y Y
SF_406 From Sales Design battery calculation for tech reference Y Y N
Construction Drawings As fitted drawings returned Y Y P
SF_401 Fire Specification As fitted specification returned Y Y P
Zone Diagram Fitted Confirm zone diagram fitted Y P P
CERTIFICATION
SF_408 BS 5839-1 Design Certificate Certificate issued and sent to customer P P P
SF_409 BS 5839-1 Installation Certificate Certificate issued and sent to customer P P P
SF_410 BS 5839-1 Commissioning Certificate Certificate issued and sent to customer Y P P
SF_411 BS 5839-1 Acceptance Certificate Certificate issued and sent to and signed customer Y P P
SF_412 BS 5839-1 Verification Certificate Certificate issued and sent to customer P N P
SF_414 BS 5839-1 Modification Certificate Certificate issued and sent to customer N Y P
SF_490 BS 5839-1 Schedule of Variations Accepted by Client Y Y Y
As Fitted Drawings Copy as fitted drawings sent to customer Y Y P
SF_401 As Fitted Specification Copy as fitted specification sent to customer Y Y P
BAFE Modification Certificate Certificate issued and sent to customer N Y P
BAFE Modular Certificate Issued Certificate issued and sent to customer P N N
BAFE Certificate of Compliance Issued Certificate issued and sent to customer P N P
CLOSE OUT
Date invoice sent Y Y Y
Preventative Maintenance Logged in Database:
Two / Four Visits per Year P N Y
Notes