9 - WMS - Turpentine Building - Pedestal (Above Plinth) Reinforcement, Shuttering & RCC Works
9 - WMS - Turpentine Building - Pedestal (Above Plinth) Reinforcement, Shuttering & RCC Works
INDEX
1. Introduction
2. Location of Works
3. Equipment and Tools (as required)
4. PPE’S to be used
5. Supervision (PERSONS INVOLVED)
6. Site preparation & Work Precaution
7. Method Statement/ Safe Work Procedure
8. Safety documents to be produced before commencing the work
9. Emergency Procedures
10. Rolls and Responsibility
11. Environmental
12. Approval and review
1. Introduction:
This document covers for pedestal (Above Plinth) Reinforcement, Shuttering &
RCC works for Turpentine Building construction works.
2. Location of Works:
Turpentine Storage Yard
Page 1 of 8
AMAR/LTTS/SIBIPL/WMS/044/R-0/23-24
Die (As per making Dia of Bar)
Bar Cutting Machine (If required)
Binding Wire
Hook
Line Dori
Chalk
Measuring Tape
Hammer
Plumb
Surveying Machine
Hydra/ Farana
Scaffolding
Tie Rod
Transit Mixture- 02 Nos
Spade- 03 Nos
Shovel- 02 Nos
Trowel- 02 Nos
Vibrator (Electric) with Needle- 01 Nos
Vibrator (Diesel) Needle- 01 Nos
Gamela- 10 Nos
Panja- 02 Nos
Fanti- 02 Nos
Randa- 02 Nos
Tarpaulin- 01 Nos
Concrete bucket - 01 Nos
Boom Placer – 01 Nos
Wheel barrow
Wooden cutter
Fire Blanket
Non-combustible sheet
Reinforcement
By using green tagged scaffolding, prefabricated steel shall be placed in position
as per approved drawings of the related structural member i.e. column
Marked Ring spacing on all Corner bars & bind proper alignment.
Put stirrups from top and bind with binding wire via binding hook manually as
per drawing.
All reinforcement must be cleared to ensure that it is free from all oil, dust, and
deleterious materials.
Page 3 of 8
AMAR/LTTS/SIBIPL/WMS/044/R-0/23-24
Cover block binding as per required distance.
After the completion of steel reinforcement take approval of inspection engineer.
Shuttering
For shuttering, the box size to be checked by inspection engineer
Shuttering oil use on boards for smooth finishing.
Manually lift of board from store to work place.
Shuttering will manually fix with tie rod or external support of props or battens etc
We provide support to all four directions with appropriate material.
Proper check diagonal and provide cover block.
Prior to placing, check the TMT bar all are as per approved BBS/ as per drawing.
Checklist to be filled for inspection
RCC Work
The Site Engineer shall initiate the concrete pour record & inspection request.
Upon the arrival of the transit mix truck at the site the delivery note will be
checked for the actual details like quantity, mixing type, approved mix design, and
slump checked regularly to the satisfaction of the engineer.
Pump car or bucket and chute or Farana (if required) or manually pouring will be
used as placing equipment as appropriate.
The concrete is placing to the column by concrete pump/ boom placer/ concrete
bucket or manually as per situation.
The Cube sample to be taken when concrete pouring is going on, the no’s of cubes
are taken as per IS specification. and will test in 7 days and 28 days.
The slump test shall be continued as per standards.
Concrete shall be consolidated by mechanical vibrators. The vibrators shall be
adequate in number of units.
In Consolidating each layer of concrete, the vibrator shall be operated in a near-
vertical position, Vibrator shall be allowed to remain inside the concrete for
sufficient time to obtain proper consolidation of concrete.
Concrete finishes shall be as required in the specification and shall be free from
voids, honeycomb or any other concrete defects.
After concrete placing, the site engineer/ supervisor shall record relevant details
on format ‘Concrete pour record’ in the presence of the engineer.
After setting of concrete work (setting time of concrete as per IS), all the
formwork will remove and properly stacked at nearby barricaded area.
Curing shall start as soon as free water has disappeared from the concrete surface
after placing and finishing.
Concrete shall be cured for a minimum of 7 days. The curing compound, if used,
shall be approved by the engineer.
Scaffolding Works
All scaffolds should be approved and inspected from LTTS
The approved Toe guard should be used for height work
Ladder should be clamp over the scaffolding pipe at top and bottom rail
The scaffolding should be checked before use the man movement or access for
works.
Yellow tagging to be fix for making the scaffolding, green tagging will be fix after
checked and okay for uses and approved by LTTS.
Page 4 of 8
AMAR/LTTS/SIBIPL/WMS/044/R-0/23-24
Method for Placing of concrete
1. Placing of concrete-by-concrete bucket
The TM is stand at one place.
Concrete bucket is hung to the Farana and move with Farana with the help of
signal man and bucket handler.
The bucket is filled by concrete and transfer the concrete to the Column.
The man is stand on green tagged scaffolding and handle the vibrator for
concreting.
Page 5 of 8
AMAR/LTTS/SIBIPL/WMS/044/R-0/23-24
9. Emergency Procedures
Site Supervisor has to report any incident to Site Manager immediately .as per
Emergency Procedure, if any person gets injured during working time
immediately sent to nearest Plant first Aid Centre and handover to medical if get
more injured.
Supervisor has to take off control over the danger and rescue over the incident.
Site manager has to inform to the first aider.
Site manager to call Plant ambulance (in P&G scope) (if required)
Site manager alerts to doctor and asked for treatment (In P&G scope) (if required)
Site manager to inform Project Manager, client and concern government
authorities if required
11. Environmental:
This section will need to reflect environmental issues associated with the work
Noise will be within permissible limits
Reduction of dust
Date
Page 7 of 8
AMAR/LTTS/SIBIPL/WMS/044/R-0/23-24
Signature
Date
Page 8 of 8
AMAR/LTTS/SIBIPL/WMS/044/R-0/23-24