Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

Project Feasibility Study for Engineers

Contents:
1. Feasibility Study Overview
2. Financial Indicators
3. Financial Support Studies
4. Financial Feasibility Studies
5. Economical Study
6. Project Risk Study
7. Cost-Benefit Analysis
8. Schedule Study
9. Technical Study
10. Market Study
11. Case Studies
12. Test Exam
Feasibility Studies - – 2
Example #5
A manager is trying to decide between two projects (A or B):
Item Project (A) Project (B)

Construction investment $ 400,000 $ 400,000

Running cost $ 120,000 / year $ 150,000 / year

Revenue $ 300,000 / year $ 350,000 / year

Life Four years Four years

Salvage value $ 100,000 $ 100,000

Minimum Attractive Rate of Return (MARR) 25%

Based on this information, discuss & select the best alternative.


Feasibility Studies - – 2021 65

Project (A): 100 100


300 180

0 0

120
400 400
Year 0 1 2 3 4
Net Cash Flow (1000) -400 180 180 180 280

Project (B): 100 100


350 200

0 0

150
400 400

Year 0 1 2 3 4
Net Cash Flow (1000) -400 200 200 200 3030
Feasibility Studies - – 2021 66
Project (A):
Year 0 1 2 3 4
Net Cash Flow (1000) -400 180 180 180 280
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 2.22
IRR % 33.4
Project (B):
Year 0 1 2 3 4
Net Cash Flow (1000) -400 200 200 200 300
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 2.0
IRR % 39.49
Project (B) is the best alternative
Feasibility Studies - – 2021 67

Example #6
A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)

Construction period One year One year

Construction investment $ 400,000 $ 400,000

Running cost after construction $ 120,000 / year $ 150,000 / year

Revenue after construction $ 300,000 / year $ 350,000 / year

Life after construction Four years Four years

Salvage value $ 100,000 $ 100,000

Minimum Attractive Rate of Return (MARR) 25%

Based on this information, discuss & select the best alternative.

Feasibility Studies - – 2021 68


Project (A): 100 100
300 180

0 1 0 1

120
400 400
Year 0 1 2 3 4 5
Net Cash Flow (1000) -400 0 180 180 180 280

Project (B): 100 100


350 200

0 1 0 1

150
400 400

Year 0 1 2 3 4 5
Net Cash Flow (1000) -400 0 200 200 200 300
Feasibility Studies - – 2021 69

Project (A):
Year 0 1 2 3 4 5
Net Cash Flow (1000) -400 0 180 180 180 280

Indicators Base
Payback Period 3.22
IRR % 22.44

Project (B):
Year 0 1 2 3 4 5
Net Cash Flow (1000) -400 0 200 200 200 300

Indicators Base
Payback Period 3.0
IRR % 25.98

Project (B) is the best alternative


Feasibility Studies - – 2021 70
Example #7
A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)


Construction Period One year One year

Construction $ 300,000 Down payment (t=0) $ 200,000 Down payment (t=0)


investment $ 100,000 Final payment $ 200,000 Final payment

Running cost after $ 120,000 / year $ 150,000 / year


construction

Revenue after $ 300,000 / year $ 350,000 / year


construction

Life after construction Four years Four years

Salvage value $ 100,000 $ 100,000

Minimum Attractive Rate of Return (MARR) 25%

Based on this information, discuss & select the best alternative.


Feasibility Studies - – 2021 71

Project (A): 100 100


300 180

0 1 0 1

100 120 100


300 300
Year 0 1 2 3 4 5
Net Cash Flow (1000) -300 -100 180 180 180 280

Project (B): 100 100


350 200

0 1 0 1

150
200 200 200 200

Year 0 1 2 3 4 5
Net Cash Flow (1000) -200 -200 200 200 200 300
Feasibility Studies - – 2021 72
Project (A):
Year 0 1 2 3 4 5
Net Cash Flow (1000) -300 -100 180 180 180 280
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 3.2 2.9 3.7
IRR % 24.25% 30% 18%
Project (B):
Year 0 1 2 3 4 5
Net Cash Flow (1000) -200 -200 200 200 200 300
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 3.0 2.7 3.4
IRR % 309.8% 38% 23%
Project (B) is the best alternative
Feasibility Studies - – 2021 73

Example #8
A manager is trying to decide between two projects (A or B):
Item Project (A) Project (B)
Construction Period One year Two years
Construction $ 100,000 Down payment (t=0) $ 100,000 Down payment (t=0)
investment $ 300,000 Final payment 200,000 after one year
100,000 after two years
Running cost after $ 100,000 / year 50,000 first year
construction 100,000 second year
150,000 third year
200,000 forth year
Revenue after $ 250,000 / year 150,000 first year
construction 300,000 second year
500,000 third year
400,000 forth year
Life after construction Four years Four years
Salvage value $ 100,000 $ 100,000
Minimum Attractive Rate of Return (MARR) 25%

Based on this information, discuss & select the best alternative.


Feasibility Studies - – 2021 74
Cash Flow:
100
Item Project (A) 250
Construction One year
Period 0 1
Construction $ 100,000 Down payment (t=0)
investment $ 300,000 Final payment 100 100

Running cost $ 100,000 / year 300


after
construction
Net Cash Flow:
100
Revenue after $ 250,000 / year
150
construction
0 1

Life after Four years


construction 100
Salvage value $ 100,000 300
Minimum Attractive Rate of Return (MARR) 25%
IRR = 21.7 < 25%
(Rejected)
Feasibility Studies - – 2021 75

Net Cash Flow:


Item Project (B) 350
300
Construction Two years 200
Period 100
Construction $ 100,000 Down payment (t=0)
investment 200,000 after one year 0
100,000 after two years
Running cost 50,000 first year 100
100
after 100,000 second year
construction 150,000 third year 200
200,000 forth year
Revenue after 150,000 first year
construction 300,000 second year
500,000 third year
400,000 forth year
Life after Four years
construction IRR = 25.25% > 25%
Salvage value $ 100,000 (Accepted)

Feasibility Studies - – 2021 76


Example #9
A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)


Construction Period One year One year
Construction $ 300,000 Down payment (t=0) $ 100,000 Down payment (t=0)
investment $ 100,000 Final payment 300,000 after one year
Running cost after 200,000 first year 50,000 first year
construction 150,000 second year 100,000 second year
100,000 third year 150,000 third year
50,000 forth year 200,000 forth year
Revenue after 400,000 first year 150,000 first year
construction 500,000 second year 300,000 second year
300,000 third year 500,000 third year
150,000 forth year 400,000 forth year
Life after construction Four years Four years
Salvage value $ 100,000 $ 100,000
Minimum Attractive Rate of Return (MARR) 25%
Based on this information, discuss & select the best alternative.
IRR  A = 32.8% B = 33.0%
Feasibility Studies - – 2021 77

Example #10
A manager is trying to decide between two projects (A or B):
Item Project (A) Project (B)
Construction Period Two years Two years
Construction 10 Down payment (t=0) 50 Down payment (t=0)
investment; M$ 40 after one year 40 after one year
50 after two years 10 after two years
Running cost after 15 first year 15 first year
construction; M$ 20 second year 20 second year
30 third year 30 third year
10 forth year 10 forth year
Revenue after 35 first year 35 first year
construction; M$ 55 second year 55 second year
75 third year 75 third year
50 forth year 50 forth year
Life after construction Four years Four years
Salvage value ; M$ 10 10
Minimum Attractive Rate of Return (MARR) 25%

Based on this information, discuss & select the best alternative.

Feasibility Studies - – 2021 78


Risk Analysis: Tool #1 - Sensitivity analysis
Example #11
A manager is trying to decide between two projects (A or B):
Item Project (A) Project (B)
Construction Period One year One year
Initial Investment; M$ 4 5
Annual Running Cost; M$/year 1 2
Annual Revenue; M$/year 3 5
Salvage Value; M$ 1 1
Life after construction; years 4 4

Loan 15% MARR = 20% Project (A)


PBP = 3 years
Based on this information, discuss the following: NPV(15%) = 1.46
1. Cash Flow Diagram IRR = 25.98%
2. Payback Period
3. Net Present Value (NPV) Project (B)
4. Internal Rate of Return (IRR) PBP = 3 years
5. Which offer should you accept and why? NPV(15%) = 2.94
6. Sensitivity analysis for market price change (±10%) IRR = 32.1%
Feasibility Studies - – 2021 79

Risk Analysis: Tool #1 - Sensitivity analysis


Example #12
A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)


Construction Period - One year
Construction investment $ 400,000 $ 100,000 Down payment
$ 300,000 Final payment
Running cost after construction $ 80,000 / year $ 100,000 / year
Revenue after construction $ 200,000 / year $ 250,000 / year
Life after construction Four years Four years
Salvage value $ 100,000 $ 100,000
Loan 15% MARR = 20%

Based on this information, discuss the following:


1. Cash Flow Diagram
2. Payback Period, Net Present Value (NPV) and Internal Rate of Return (IRR)
3. Which offer should you accept and why?
4. Sensitivity analysis for market price change (±10%)
Feasibility Studies - – 2021 80
Project (A): 100 Construction Period -

Cash Flow (1000) 200 Construction investment $ 400,000


Running cost after construction $ 80,000 / year
0 1 2 3 4 Revenue after construction $ 200,000 / year
Life after construction Four years
80 Salvage value $ 100,000

400

Year 0 1 2 3 4
Net Cash Flow (1000) - 400 120 120 120 220

100
Project (B): Construction Period One year

250 Construction investment $ 100,000 Down payment


Cash Flow (1000) $ 300,000 Final payment

0 1 2 3 4 5 Running cost after construction $ 100,000 / year


Revenue after construction $ 250,000 / year
Life after construction Four years
100 100
Salvage value $ 100,000
300
Year 0 1 2 3 4 5
Net Cash Flow (1000) - 100 - 300 150 150 150 250
Feasibility Studies - – 2021 81

Project (A):
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 3y+2m 2 y + 10 m 3y+6m
IRR % 14.97 % 21.28 % 8.47 %
Probability; % 50% 25% 25%
E (IRR) = 21.28 * 0.25 + 14.97 * 0.50 + 8.47 * 0.25 = 14.92 %
Project (B):
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 3y+8m 3 y + 3.4 m 4 y + 1.3 m
IRR % 21.7 % 28.16 % 14.91 %
Probability; % 50% 25% 25%
E (IRR) = 28.16 * 0.25 + 21.7 * 0.50 + 14.91 * 0.25 = 21.6 %

Project (B) is the best alternative but IRR 21.6 < MARR 25%
Feasibility Studies - – 2021 82
Risk Analysis: Tool #1 - Sensitivity analysis
Example #13
A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)


Construction Period One year One year

Construction investment $ 350,000 $ 300,000 Down payment


$ 200,000 Final payment
Running cost after construction $ 100,000 / year $ 120,000 / year
+ 10% Annually + 15% Annually
Revenue after construction $ 250,000 / year $ 280,000 / year
+ 15% Annually + 20% Annually
Life after construction Four years Four years

Salvage value $ 100,000 $ 100,000

Loan Interest Rate 15% MARR = 25%


Based on this information, discuss the following:
a) Cash Flow Diagram
b) Payback Period & Internal Rate of Return (IRR)
c) Sensitivity analysis for revenue change (±10%)
e) Which offer should you accept and why?
Feasibility Studies - – 2021 83

Project (A):
100,000
Cash Flow: 330,625 380,219
287,500
250,000

0 1 2 3 4 5

100,000 110,000
350,000 121,000 133,100

209,625 347,119
Net Cash Flow: 177,500
150,000

0 1 2 3 4 5

350,000
• Payback Period = 4 (3.11) years
• IRR = 28.55 % > MARR 25%
Feasibility Studies - – 2021 84
Project (B):
100,000
Cash Flow: 403,200 483,840
336,500
280,000

0 1 2 3 4 5

200,000 120,000 138,000


300,000 158,700 182,505

244,500 401,335
Net Cash Flow: 198,500
160,000

0 1 2 3 4 5

200,000
300,000
• Payback Period = 4 (3.58) years
• IRR = 22.91 % < 25%
Feasibility Studies - – 2021 85

Project (A):
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 4 (3.11) 3 (2.87) 4 (3.43)
IRR % 28.55% 33.73% 22.95%

Project (B):
Sensitivity Analysis
Indicators Base
Market Price (+10%) Market Price (-10%)
Payback Period 4 (3.58) 4 (3.28) 4 (3.99)
IRR % 22.91% 28.52% 16.86%

Project (A) is the best alternative, IRR 28.55 > MARR 25%

Feasibility Studies - – 2021 86


Example #14
A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)


Construction Period One year One year

Construction investment $ 350,000 $ 300,000 Down payment


$ 200,000 Final payment
Running cost after construction $ 100,000 / year $ 120,000 / year
+ 10% Annually + 15% Annually
Revenue after construction $ 250,000 / year $ 280,000 / year
+ 15% Annually + 20% Annually
Life after construction Four years Four years

Salvage value $ 100,000 $ 100,000

MARR = 25% Assume; $=16 LE


Loan Description: Loan 5,000,000 LE, over 3 years, interest rate = 15% annually
Based on this information, discuss the following:
a) Cash Flow Diagram b) Payback Period & Internal Rate of Return (IRR)
c) Sensitivity analysis for revenue change (±10%)
d) Which offer should you accept and why?
Feasibility Studies - – 2021 87

Loan Analysis
Loan 5,000,000 LE ($ 312,500), over 3 years, interest rate = 15%

A A A

1 2 3

- 312,500 P = { F / (1 + i)n }

A = Annual Payment = PMT? NPV =0

0 = - 312,500 + A / (1.15)1 + A / (1.15)2 + A / (1.15)3

A = PMT( i , n , P ) = 136,868 $/year


Feasibility Studies - – 2021 88
Project (A): 100,000
330,625 380,219
287,500
Cash Flow: 250,000
0 1 2 3 4 5

100,000 110,000
350,000 121,000 133,100
Net Cash Flow 209,625 347,119
177,500
Without Loan: 150,000
0 1 2 3 4 5

350,000
312,500
136,868 Annual
Loan
Net Cash Flow 209,625 347,119
40,632
With Loan: 13,132
0 1 2 3 4 5
37,500 136,867 Payback = 4 years IRR = 41.55 %
Feasibility Studies - – 2021 89

Project (B): 100,000


403,200 483,840
336,500
Cash Flow: 280,000
0 1 2 3 4 5

200,000 120,000 138,000


300,000 158,700 182,505

Net Cash Flow 244,500 401,335


198,500
Without Loan: 160,000
0 1 2 3 4 5

300,000 200,000
312,500
136,868 Annual
Loan
Net Cash Flow 244,500 401,335
61,132
With Loan: 23,132
12,500 1 2 3 4 5
0
336,868 Payback = 4 years IRR = 28.08 %
Feasibility Studies - – 2021 90
Example #14
A manager is trying to decide between two projects (A or B):
Item Project (A) Project (B)
Construction Period One year One year
Construction investment $ 350,000 $ 300,000 Down payment
$ 200,000 Final payment
Running cost after construction $ 100,000 / year $ 120,000 / year
+ 10% Annually + 15% Annually
Revenue after construction $ 250,000 / year $ 280,000 / year
+ 15% Annually + 20% Annually
Life after construction Four years Four years
Salvage value $ 100,000 $ 100,000

MARR: 25% Currency Rate: 16 LE/$


Loan Description: Loan 5,000,000 LE, over 3 years, interest rate = 15% annually,
and the first payment at the end of year #2.
Based on this information, discuss the following:
a) Cash Flow Diagram b) Payback Period & Internal Rate of Return (IRR)
c) Sensitivity analysis for revenue change (±10%)
d) Which offer should you accept and why?
Feasibility Studies - – 2021 91

Example #15 A manager is trying to decide between two projects (A or B):

Item Location (A) Location (B)


Construction Period One year One year
Initial Investment; M$ 10 12
Annual Running Cost; M$/year 2 3
Annual Revenue; M$/year 8 10
Salvage Value; M$ 1 1
Life After Construction; years 3 3
Loan Interest Rate % 15%
Loan Value; M$ 6
Loan Life; years 3
First Payment of Loan End of year #1
Based on this information, discuss the following:
1. Cash Flow Diagram & Net Cash Flow
2. Payback Period & Internal Rate of Return (IRR)
3. Sensitivity analysis for (market price increase10% annually) &
(running cost increase 12% annually).
4. Which offer should you accept and why?
Feasibility Studies - – 2021 92
Loan Analysis: P = { F / (1 + i)n }
6 = { A / (1.15)1 } + { A / (1.15)2 } + { A / (1.15)3 }
Annual Payment = A = 2.627862
Project (A): 7
1 6
8 3.372138
0 1 2 3 4
+ 0 1 2 3
= 0 1 2 3 4

2 2.627861 2.627862
10 4
Payback Period = 3 years IRR = 29.68%

Project (B): 8
1 6
10 4.372138
0 1 2 3 4
+ 0 1 2 3
= 0 1 2 3 4

3 2.627861 2.627862
12 6
Payback Period = 3 years IRR = 26.16%
Feasibility Studies - – 2021 93

Project (A):
Year 0 1 2 3 4
Net Cash Flow -4 -2.627862 3.372138 3.372138 7
Sensitivity Analysis
Indicators Base
Market Price (+10%) Running Cost (+12%)
Payback Period 3
IRR % 29.68
Project (B):
Year 0 1 2 3 4
Net Cash Flow -6 -2.627862 4.372138 4.372138 8
Sensitivity Analysis
Indicators Base
Market Price (+10%) Running Cost (+12%)
Payback Period 3
IRR % 26.16
Project (A) is the best alternative
Feasibility Studies - – 2021 94
Example #15 A manager is trying to decide between two projects (A or B):

Item Location (A) Location (B)


Construction Period One year One year
Initial Investment; M$ 10 12
Annual Running Cost; M$/year 2 3
Annual Revenue; M$/year 8 10
Salvage Value; M$ 1 1
Life After Construction; years 3 3
Loan Interest Rate % 15%
Loan Value; M$ 6
Loan Life; years 3
First Payment of Loan End of year #2
Based on this information, discuss the following:
1. Cash Flow Diagram & Net Cash Flow
2. Payback Period & Internal Rate of Return (IRR)
3. Sensitivity analysis for (market price increase10% annually) &
(running cost increase 12% annually).
4. Which offer should you accept and why?
Feasibility Studies - – 2021 95

Example #16 A manager is trying to decide between two projects (A or B):

Item Project (A) Project (B)


Construction Period One year One year
Initial Investment; M$ 6 8
Annual Running Cost; M$/year 1 2
Annual Revenue; M$/year 3 5
Salvage Value; M$ 1 1
Life After Construction; years 6 8
Loan Interest Rate % 12% 14%
Loan Value; M$ 3 4
Loan Life; years 3 4
First Payment of Loan End of year #1 End of year #1
Based on this information, discuss the following:
1. Cash Flow Diagram & Net Cash Flow
2. Payback Period & Internal Rate of Return (IRR)
3. Sensitivity analysis for (market price increase10% annually) &
(running cost increase 8% annually).
4. Which offer should you accept and why?
Feasibility Studies - – 2021 96
Risk Analysis: Tool #2 - Scenario analysis
Example #17

Scenario Analysis
Item
Worst Base Best
Probability; % (by default) 25% 50% 25%
Initial Investment; M$ 5.1 5 4
Annual Running Cost; M$/year 4.1 4 3
Annual Revenue; M$/year 4.9 5 6
Salvage Value; M$ 1.9 2 3
Project Life; years 4 4 4

Based on this information, discuss the following:


1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
Feasibility Studies - – 2021 97

Risk Analysis
Scenario Analysis
Item
Worst Base Best
Probability; % 25% 50% 25%
Initial Investment; M$ 5.1 5 4
Annual Running Cost; M$/year 4.1 4 3
Annual Revenue; M$/year 4.9 5 6
Salvage Value; M$ 1.9 2 3
Project Life; years 4 4 4

Payback Period (years) 4 4 1.33


Internal Rate of Return (IRR) 0 6.4 72.7

Estimation:
E (Payback Period) = 4 * 0.25 + 4 * 0.50 + 1.33 * 0.25= 3.33 years

E (IRR) = 0 * 0.25 + 6.4 * 0.50 + 72.7 * 0.25 = 21.4 %

Feasibility Studies - – 2021 98


Risk Analysis: Tool #2 - Scenario analysis
Example #18
Scenario Analysis
Item
Worst Base Best
Probability; % (by default) 25% 50% 25%
Initial Investment; M$ 6 5 4
Annual Running Cost; M$/year 5 4 3
Annual Revenue; M$/year 4 5 6
Salvage Value; M$ 1 2 3
Project Life; years 4 4 4

Based on this information, discuss the following:


1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
Feasibility Studies - – 2021 99

Risk Analysis
Scenario Analysis
Item
Worst Base Best
Probability; % 25% 50% 25%
Initial Investment; M$ 6 5 4
Annual Running Cost; M$/year 5 4 3
Annual Revenue; M$/year 4 5 6
Salvage Value; M$ 1 2 3
Project Life; years 4 4 4

Payback Period (years) N/A 4 2


Internal Rate of Return (IRR) N/A 6.4 72.7
Infeasible
Estimation:
E (Payback Period) =

E (IRR) =

Feasibility Studies - – 2021 100


Risk Analysis: Tool #3- Breakeven analysis

Breakeven Analysis “Sensitivity Analysis of Quantity”

Total costs = fixed costs + variable costs


Total Fixed Costs
QBE =
Price  Var. Cost per unit
Profit =0
Revenue = Total Cost

Feasibility Studies - – 2021 101

Risk Analysis: Tool #3- Breakeven analysis


Example #19
A manager is trying to decide between two machines (A or B):
A B
Initial cost, $ 10,000 15,000
Life, years 5 5
Salvage value, $ 1,000 2,000
Annual maintenance, $ 1,000 1,200
Variable cost; $/unit 1 0.80
Annual Sales Quantity, unit 8,000 8,000
Unit Price, $/unit 1.5 1.5
Based on this information, select the best machine.

Payback Period IRR Breakeven Quantity


Machine A 3.6 years 17.22 % 28,000
Machine B 3.4 years 16.97 % 27,143
Best Machine B A B
Feasibility Studies - – 2021 102
Risk Analysis: Tool #3- Breakeven analysis
Example #20

A manager is trying to decide between two machines (A or B):

Alternative A has an initial cost of $10,000 and a salvage value of


$1000 after 5 years. Alternative A also has a variable cost of $1/unit
of product produced and an annual maintenance of $1000.

Alternative B has an initial cost of $15,000 and a salvage value of


$2,000 after 7 years. Alternative B also has a variable cost of
$0.80/unit of product produced and an annual maintenance cost of
$1200.

Based on this information, select the best machine.

Feasibility Studies - 2021 103

Risk Analysis: Tool #3- Breakeven analysis

A manager is trying to decide between two machines (A or B):

A B
Initial cost, $ 10,000 15,000
Life, years 5 7
Salvage value, $ 1,000 2,000
Annual maintenance, $ 1,000 1,200
Variable cost; $/unit 1 0.80

Based on this information, select the best machine.

Feasibility Studies - – 2021 104


• Alt. 1: Machine A:
– Capital Cost =10,000 –1,000= 9,000 A
B
– Maintenance Cost =1,000*5 = 5,000
– Total Fixed Cost = 14,000
– Total Variable cost = 1 * Q BEP
– Total Cost = 14,000 + 1 * Q

• Alt. 2: Machine B:
– Capital Cost =15,000 –2,000= 13,000
– Maintenance Cost =1,200*7 = 8,400
– Total Fixed Cost = 21,400
– Total Variable cost = 0.8 * Q Q
– Total Cost = 21,400 + 0.8 * Q

At BEQ: <Q Q >Q


TC(A) = TC(B) A A,B B
F(A) + Q . v(A) = F(B) + Q . v(B)

Q = units
Feasibility Studies - – 2021 105

• Alt. 1: Machine A:
– Capital Cost =10,000 –1,000= 9,000 A
B
– Maintenance Cost =1,000*5 = 5,000
– Total Fixed Cost = 14,000
– Total Variable cost = 1 * Q BEP
– Total Cost = 14,000 + 1 * Q

• Alt. 2: Machine B:
– Capital Cost =15,000 –2,000= 13,000
– Maintenance Cost =1,200*7 = 8,400
– Total Fixed Cost = 21,400
– Total Variable cost = 0.8 * Q 37000
– Total Cost = 21,400 + 0.8 * Q

At BEQ: <37000 37000 >37000


TC(A) = TC(B) A A,B B
14,000 + 1 * Q = 21,400 + 0.8 * Q
0.2 Q = 7,400
Q = 37,000 units
Feasibility Studies - – 2021 106
Example #23
A manager is trying to decide between two machines (A or B):

A B
Initial cost, $ 10,000 15,000
Life, years 5 5
Salvage value, $ 1,000 2,000
Annual maintenance, $ 1,000 1,200
Variable cost; $/unit 1 0.80

Based on this information, select the best machine.


A B
NPV(12%)

Feasibility Studies - – 2021 107

You might also like