2 WEEKS LOOK-AHEAD PLAN

25th Mar-Apr 8th


Original Planned Start Planned Finish
Activity ID Activity Name
Duration date date
REPLACING THE EXISTING ROOF SLAB WATERPROOFING SYSTEM
ZONE A
A1380 Application of Aluminium flashing and sealant in vertical faces 4 26-Mar-24 29-Mar-24
A1390 Installation of 50mm thk thermal insulation boards 4 22-Mar-24 25-Mar-24
A1400 Installation of geo textile 4 26-Mar-24 29-Mar-24
A1410 Reinstate same type of roof tiles as pe existing design 3 30-Mar-24 01-Apr-24
ZONE B
A1470 Application of Aluminium flashing and sealant in vertical faces 4 26-Mar-24 29-Mar-24
A1480 Installation of 50mm thk thermal insulation boards 4 22-Mar-24 25-Mar-24
A1490 Installation of geo textile 4 26-Mar-24 29-Mar-24
A1500 Reinstate same type of roof tiles as pe existing design 3 30-Mar-24 01-Apr-24
ZONE C
Removal of existing finishes(Concrete Tiles,geotextile,Aggregates,
A1510 10 18-Mar-24 27-Mar-24
insulation board,waterproofing membrane)
A1520 Carryingout necessary concrete repairs 8 28-Mar-24 04-Apr-24
A1530 Installation of Two layers of 4mm thick SBS Membrane 5 05-Apr-24 09-Apr-24
A1540 Application of verticalsurface/Skirting 3 10-Apr-24 12-Apr-24
ZONE D
Removal of existing finishes(Concrete Tiles,geotextile,Aggregates,
A1600 10 18-Mar-24 27-Mar-24
insulation board,waterproofing membrane)
A1610 Carryingout necessary concrete repairs 8 28-Mar-24 04-Apr-24
A1620 Installation of Two layers of 4mm thick SBS Membrane 5 05-Apr-24 09-Apr-24
A1630 Application of verticalsurface/Skirting 3 10-Apr-24 12-Apr-24
2 WEEKS LOOK-AHEAD PLAN
25th Mar-Apr 8th
Original Planned Start Planned Finish
Activity ID Activity Name
Duration date date
GROUND IMPROVEMENT BY LATERAL COMPACTION OF SOIL
INTERNAL AREAS AREAS
A1740 Lancer Placing and Injection 20 18-Mar-24 06-Apr-24
A1820 DCPT after soil stabilizing NA 28-Mar-24 09-Apr-24
BOUNDARY WALL REPAIR
A1230 Boundry Wall Repairing and plastering 20 18-Mar-24 06-Apr-24
REPLACEMENT OF THE WATERPROOFING SYSTEM ON THE UNDERGROUND TANK
A1770 Removing existing WP membrane and cleaning 10 14-Mar-24 23-Mar-24
A1780 Carrying out neccessary repairing works 6 24-Mar-24 29-Mar-24
A1800 Applying primer new hybrid polyurea coating 5 30-Mar-24 03-Apr-24
VERIFICATION OF PUMP ROOM AND UNDER GROUND SERVICES
A1050 Carryout Necessary rectification 10 16-Mar-24 25-Mar-24
REMOVING AND REINSTATEMENT OF ROOF EXPANSION JOINT 20
A1690 Removing and reinstatement of roof expansion joint 10 20-Mar-24 29-Mar-24
EXTERNAL WALL REPAIR 20
A1230 External wall Reparing 20 29-Feb-24 19-Mar-24
A1231 Primer application 6 21-Mar-24 26-Mar-24