Document Title: Inspection and Test Plan for concrete repair PP-YECS-ITP - 001 Rev. 00
Item No. Work Phase Project Specifications & Acceptance Criteria Inspection/Test Frequency Record ITR
Standards S/C MC C
A Review of relevant Documentation
Review of Material All required documents such as material
A.1 submital, method submital/method statement/ITP are approved by Initial Approved Document R R R
statement Engineer
B Material Delivery, Storage, Inspection and Testing
B.1 Material inspection Approved MAR For each material delivery MIR,Delivery notes H H R
C Execution
Surface preparation –
setting out, markings
C.1 chipping concrete to as mentioned in MS Approved material submital/method Each completed area WIR H S R
required depth and statement/ITP/RA
cleaning.
Document Title: Inspection and Test Plan for concrete repair PP-YECS-ITP - 001 Rev. 00
Item No. Work Phase Project Specifications & Acceptance Criteria Inspection/Test Frequency Record ITR
Standards S/C MC C
D Post conctruction activities
Resolve deviation / NCR Corrective actions /
D.1 NCR Reports Corrective actions Each NCR Compliance H S R
issues