PROJECT: ARENCO DIP - 939, STRUCTURAL REPAIRS AND SOIL IMPROVEMENT WORKS, Plot No.

598-939, Dubai Investment


Park, Dubai.

Document Title: Inspection and Test Plan for concrete repair PP-YECS-ITP - 001 Rev. 00

Item No. Work Phase Project Specifications & Acceptance Criteria Inspection/Test Frequency Record ITR
Standards S/C MC C
A Review of relevant Documentation
Review of Material All required documents such as material
A.1 submital, method submital/method statement/ITP are approved by Initial Approved Document R R R
statement Engineer
B Material Delivery, Storage, Inspection and Testing
B.1 Material inspection Approved MAR For each material delivery MIR,Delivery notes H H R
C Execution

Surface preparation –
setting out, markings
C.1 chipping concrete to as mentioned in MS Approved material submital/method Each completed area WIR H S R
required depth and statement/ITP/RA
cleaning.

Coating of corrosion Approved material submital/method


C.2 inhibitor and placing of as mentioned in MS Each completed area WIR H S R
statement/ITP/RA
new steel reinforcement
where ever necessary.

Application of approved Approved material submital/method


C.3 repair mortar in the as mentioned in MS statement/ITP/RA Each completed area WIR H S R
prepared area.
PROJECT: ARENCO DIP - 939, STRUCTURAL REPAIRS AND SOIL IMPROVEMENT WORKS, Plot No. 598-939, Dubai Investment
Park, Dubai.

Document Title: Inspection and Test Plan for concrete repair PP-YECS-ITP - 001 Rev. 00

Item No. Work Phase Project Specifications & Acceptance Criteria Inspection/Test Frequency Record ITR
Standards S/C MC C
D Post conctruction activities
Resolve deviation / NCR Corrective actions /
D.1 NCR Reports Corrective actions Each NCR Compliance H S R
issues

Involvements Inspection Codes


W – Witness: Notification required (IR) Presence not mandatory
H – Hold Point: Notification required (IR) Presence mandatory
SC: Subcontractor
MC: Main Contractor R – Review, Inspect and Approve, T- Test
C: Consultant S -- Surveillance check