Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

JSA NO. Department /


Job Title: Routine/ Non Routine New/ Revised
Activity/ No…

Reference work Permit


JOB SAFETY no:- Supervisor: Prepared By:
ANALYSIS

Plant Location: -Unit-01,


Department: Project Reviewed By:
Niacinamide

Job Description: - Reactor Erection Work By 100-ton crane & farana used for reactor
trailing and Use of Boom lift for platform. Approved By:

SEQUENCE OF TASK POTENTIAL HAZARDS PREVENTIVE MEASURES

 Horseplay  Site safety induction should be provided to all new


 Unskilled workers, employees.
 Mobilization of  Person injury  Deploy experienced trained skilled workers for specific
Manpower  Property damage jobs.
 Untrained worker ,unauthorized  Job-specific training should be given
entry  TBT to be taken on daily basis prior to starting the job
Mandatory
 PPE’s should be provided viz. safety helmet, safety shoes,
reflective jacket etc.
 Safety Awareness/motivational programs shall be conducted
to workmen for more awareness of safety.
 Medical fitness is must for all workers.
 Gate pass compliance (As per JIL HR Dept.) shall be
complied.

 Mobilization of  Involvement of unskilled  Trained & skilled staff to be authorized for job
equipment & personnel  Obtain relevant permit before vehicle/equipment entry in the
Materials  Unauthorised/ uninspected area
equipment/tools at site  Ensure use of appropriate PPE’s on site
 Personnel/Structures hit by  JSA Briefing to all of workforce involved
Equipment/Heavy Vehicle
 Deliver tool box talk to all of vehicles drivers & operators
 Damaging to drains/culverts
 Banks man should be available at site
beside roads
 Be careful about nearby drains/culverts while vehicle
 Striking of vehicles with movement on roads
structure/overhead live lines
 Keep away all unauthorized people during movement of
 Personnel injury / property
heavy vehicle/equipment
damage
 Do not left un attendant any of equipment/tool in the area
 Ensure Close HSE monitoring /supervision
 Flame arrestor to be installed in vehicles

Page 1 of 3
Format No.:- EHS-006/F06-00 Effective Date:-16/08/18
 Barricading of work  Use of required PPEs as per company rules safety norms-
area.  Personal injury safety shoes, safety helmet, safety goggle, reflective jacket.
 No any unauthorized material to be kept inside barricading
area.
 Required area should be barricaded.

 Working at Height  Fall of person or material from  Obtain valid work permit.
 Use of boom lifter height.  TBT must be taken before starting the work.
 Failure of lifting tools & tackles.  Trained and experience person should be allowed to do
 Burns work.
 Physical injury  Continue supervision to be provided.
 Boom struck with adjacent  All the documents available with Boom lift
structures,
 Inspect all tools & equipment’s prior to use at workplace.
 Electrical shock
 Ensure all tools are in safe working conditions.
 Ensure valid documents of the operator.
 SWL of the Boom lift must be checked before Obtain valid
work permit.
 Always look in the direction of travel of bucket when
operating lift.
 Never move the lift when the boom is elevated in a working
position with worker in the bucket.
 Ensure be must Anchorage double lanyard with Anchorage
point due to elevated work.
 Never run boom or bucket into conductors, cables, poles,
trees etc.

 Used of farana for  Fall of material  Equipment trailing area should be barricaded properly.
trailing  Topple of vehicle  Unauthorized entry will be strictly prohibited.
 Property damage  Used lifting equipment must be certified by competent
 Collision with other vehicle person & before starting work physical inspection should be
 Traffic blockage done by concerning supervisor or authorized personal on
 Personal injury regular.
 Failure of load  The structure integrity of crane should be maintained, check
 Mechanical failure for any sign of corrosion.
 Proper tag/guy rope to be used.
 Monthly inspection of colour code shall provide for lifting
tools tackles.
 Lifting tackles, slings, wire rope, eyebolts and shackles
should be tested/examined daily.
 Ensure qualified signal man to be engaged with visible vest,
flag.
 Only one man gives signal to operator.
 All the lifting gears to be third party certified, form-10.
 Work permit must be obtain before starting the work.
 Ground survey shall be done before trailing work.
 Ensure that all safe distance maintain from farana.
 10 km/h speed allowed when shifting of material.
 Vehicle inspection shall carry out prior to deploy at site.

Page 2 of 3
Format No.:- EHS-006/F06-00 Effective Date:-16/08/18
 Reactor Erection Work  Fall of equipment/reactor.  Ensure all lifting tools tackles tested should be done.
By- Crane:- 100  Over load.  Proper supervision by site supervisor.
Ton.  Collapse of crane.  Operator with HMV license deployed.
 Reactor weight-  Uneven ground condition.  Capacity of the vehicle should be related to the load to be
9.6 ton.  Overhead power power line. carried
 Uncontrolled movement of load.  Trained riggers are deployed.
 Pinch point hazard.  Ensure proper communication between rigger/signal man &
 People under suspended load, operator.
 Unbalancing of load while  Conducted On job site specific training.
holding it  Operator shall check soil condition working location.
 Ensure as per JIL format lifting plan.
 Ensure use of inspected & colour coded hand tools &
rigging accessories
 Area should be properly barricaded during lifting operations
 Use tag line to control the load
 Ensure equipment weight according to crane capacity.
 Ensure all Crane document & check list.
 Ensure Crane as per job.
 Lifting tools and tackles have valid form-10.
 Lifting equipment within SWL of crane
 Required area should be barricaded.
 Multiple activity not should be start in the same location.

 Housekeeping  Slip, trip hazards  Ensure entire area shall be cleaned after job is completed.
Remove unwanted material from site after close the job.
 Erection material should be proper stacking.

 In Case of  Confusion  Emergency assembly point, emergency access should be


Emergency defined & always free from any obstructions.
 Emergency contact details to be displayed at prominent
locations of the site.
 Emergency vehicles must be available at work locations
during all working hours.
 All workers shall be aware / trained about site emergency
procedure.
 Fire team- 4666
 OHC- 4777

Day-1 Day-2 Day-3

Permit issuer

Permit acceptor

Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/
Safety officer

Approved By HO

Page 3 of 3
Format No.:- EHS-006/F06-00 Effective Date:-16/08/18