Professional Documents
Culture Documents
CAF-03 CMA CRESCENT MOCK Solution
CAF-03 CMA CRESCENT MOCK Solution
Answer-1
a.
Rs. Rs.
Material costs
Component 1 – circuit board 4.10
Delivery cost (Rs. 2,400 / 4,000 batches) 0.60 4.70
Component 2 - Wiring 0.13
(Rs. 0.50 per meter 25/100 meter 100/98)
Other materials 8.10
12.93
Labour costs 7.00
(Rs. 12.60/hours 30/60 hours 100/90)
Production overheads
Variable overheads (Rs. 20/hour (W-1) 30/60 hours) 10.00
Fixed overheads (Rs. 12/hour 30/60 hours) 6.00 16.00
Target cost 35.93
Less: Desired cost (Rs. 44 0.80) 35.20
Cost gap 0.73
WORKINGS
W-1 Production overhead cost (using high low method)
Extra overhead cost between month 1 and 2 (700,000 – 620,000) 80,000
Extra assembly hours (23,000 – 19,000) 4,000
Variable cost per hour (80,000/4,000) Rs. 20/hour
Monthly fixed production overhead (Rs. 700,000 − (23,000 Rs. 20/hour)) Rs. 240,000
Annual fixed production overhead (Rs. 240,000 12) Rs. 2,880,000
Absorption rate of fixed overheads (Rs. 2,880,000/24,000 hours) Rs. 12/hour
b.
Page 1
CMA Mock: Suggested solution CAF-03
Answer-2
Operating statement
Rs. Rs. Rs.
Budgeted profit 112,000
Sales volume profit variance (W-1) (22,400)
Standard profit on actual sales 89,600
Sales price variance (W-2) 16,000
105,600
Cost Variances Favorable Adverse
Material price (W-3) 24,000
Material usage (W-4) 32,000
Labour rate (W-5) 16,000
Labour efficiency (W-6) 12,800
Variable overhead efficiency (W-7) 6,400
Variable overhead expenditure (W-8) 4,000
8Fixed overhead expenditure (W-9) 60,000
Fixed overhead efficiency (W-10) 25,600
Fixed overhead capacity (W-11) 0
Total cost variances 112,000 68,800 43,200
Actual Profit 148,800
WORKINGS
(W-1) Sales volume profit variance = (Actual sales quantity - Budgeted sales quantity) x Std. Profit/Unit
= (3,200 units – 4,000 units) x Rs. 28
= Rs. 22,400 (A)
(W-2) Sales price variance = (Actual selling price per unit - Standard selling price per unit) x Actual qty.
= (Rs 225 – Rs. 220) x 3,200 units
= Rs. 16,000 (F)
(W-3) Material Price Variance = (Standard Price - Actual Price) x Actual Quantity
= (Rs. 3.2 – Rs. 3.5) x 80.000 kg
= Rs. 24,000 (A)
(W-4) Material Usage Variance = (Standard quantity for actual production - Actual quantity) x Std price
= [(3,600 x 25 kg) – 80,000 kg) x Rs. 3.2
= Rs. 32,000 (F)
(W-5) Labour rate variance = (Standard wages rate/hour - Actual wages rate/hour) x Actual labour hours
= (Rs.8 – Rs.7) x 16,000 hours
= Rs. 16,000 (F)
(W-6) Labour efficiency variance = (SLH for act. production – ALH worked) x Std. wage rate/hour
= [(4 hrs x 3,600 units) – 16,000 hrs] x Rs. 8
= Rs. 12,800 (A)
(W-7) Variable OH efficiency variance = (Std. hrs for act. production – Act. hrs) x Std. VFOH rate/hour
= [(4 hrs x 3,600 units – 16,000 hrs) x Rs. 4]
= Rs. 6,400 (A)
Page 2
CMA Mock: Suggested solution CAF-03
(W-8) Variable OH exp. variance = (Std. VFOH rate – Act. VFOH rate) x Act. hrs worked
= [(Rs.4 x 16,000 hrs) – Rs. 60,000]
= Rs. 4,000 (F)
(W-9) Fixed FOH exp. variance = Budgeted fixed overhead - Actual expenditure on fixed overhead
= [(4,000 units x Rs. 64) – Rs. 196,000]
= (Rs. 256,000 – Rs. 196,000)
= Rs. 60,000 (F)
(W10) FFOH eff. variance = (Std hrs for act. production – Act. hrs worked) x Fixed FOH absorption rate
= [(4 hrs x 3,600 units) - 16,000 hrs)] x Rs. 16
= Rs. 25,600 (A)
(W11)Fixed overhead capacity variance = (Budgeted hours – Actual hours) x Fixed overhead absorption rate.
= [(4 hrs x 4,000 units) – 16,000 hrs] x Rs. 16
= Rs. 0
Answer-3
Since there is an additional profit of Rs. 6.5 million, it is financially worthwile to use imported diamonds
and increase production to 1,500 units
Page 3
CMA Mock: Suggested solution CAF-03
Answer-4
a. Optimal Production Plan
Rs.
Material R2 (3 x 5.67) 17.01
Material R3 (1.6 x 2) 3.20
Labour (4 x 1.5) 6.00
Variable overhead 1.10
27.31
Selling price 27.30
Hence Contribution 00.00
Further supplies of Material R2 will be used to produce additional units of project HT4 since we
already produced the required quantities for the maximum demand of AR2 and GL3. The ruling
market price for R2 is Rs. 2.50 and the contribution per kg of material R2 for Product HT4 is Rs.
Page 4
CMA Mock: Suggested solution CAF-03
3.17. In order to cover, the costs the product should recover an amount equal to the additional
costs incurred.
Hence if Denver Limited pays 3.17 + 2.50 = Rs. 5.67 per kg for Material R2, the additional units
of product HT4 produce will make a zero contribution towards fixed costs. Rs. 5.67 is therefore
the maximum price.
This is because we increased the cost of material R2, to an extent that resulted in the total cost of
the produced HT4 being equal to its selling price.
The total cost when material R2 is purchased at Rs. 5.67 per kg.
The company would need to manufacture more than 12,500 units per year of Product XY5, or 1,042 units
per month, in order for the offered substitute to be financially acceptable. If it needed less than 12,500
units of Product XY5 per year, it would be cheaper to manufacture the product in house.
Answer-5
a.
Amount Amount
Page 5
CMA Mock: Suggested solution CAF-03
b.
As 1/3rd of under absorbed overheads were due to defective production planning, this being abnormal,
hence should be debited to profit and loss account.
Amount to be debited to profit and loss account = 234,000 x 1/3 = Rs. 78,000
Balance of under absorbed production overheads should be distributed over finished goods and cost of
sales.
c.
Answer-6
Page 6
CMA Mock: Suggested solution CAF-03
Lighting charges:
It is given in the question that lighting charges for 8 months are Rs. 110 per month and during winter
season of 4 months, it is Rs. 30 per month. Further, it is also given that peak season is 6 months and off
season is 6 months.
It should be noted that being Hill station, winter season is to be considered as part of off season. Hence,
non-winter season of 8 months include peak season of 6 months and off season of 2 months.
Season & non-winter – 80% occupancy 200 rooms x 80% x 6 months x Rs. 110 per month = Rs.
105,600
Off season & non winter – 40% 200 rooms x 40% x 2 months x Rs. 110 per month = Rs.
occupancy 17,600
Off season & winter – 40% occupancy 200 rooms x 40% x 4 months x Rs. 30 per month = Rs. 9,600
Particulars Amount
Staff salary 800,000
Repairs to building 300,000
Laundry 140,000
Interior 250,000
Miscellaneous expenses 200,200
Depreciation on building (300,000,000 x 80% x 5%) 12,000,000
Depreciation on furniture and equipment (300,000,000 x 20% x 15%) 9,000,000
Room attendant’s wages (Rs. 15 per room day for 43,200 room days) 648,000
Lighting charges 132,800
Total cost 23,471,000
Add: Profit margin (20% of room rent) 5,867,750
Total rent to be charged 29,338,750
Room rent per day = Total rent / Equivalent full room days = 29,338,750 / 36,000 = Rs. 814.97
Room rent during off season = Rs. 814.97 x 50% = Rs. 407.49
Page 7
CMA Mock: Suggested solution CAF-03
Answer-7
a.
2 x 480,000 x 248.44
=√ 1.06
Page 8
CMA Mock: Suggested solution CAF-03
2 x 300,000 x 267
=√ 0.10
Page 9