MOS-008 For Water Leaking Test

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

RWTP

•· Air Selangor RASAU WATER TREATMENT PLANT


�GAMUDA
PENGURUSAN AIR SELANGOR
SON BHD
METHOD STATEMENT

1.0 SCOPE OF WORKS

1.1 General Description

This method of statement is prepared to outline the procedure and resources used for the
work commencement for water leaking test used in Rasau Water Treatment Plant. It
comprises the sequence of work and technical compliance throughout the entire usage of form
tie. The form tie system prevents breakage in the formwork, thus keeping concrete structures
in good shape without discolouration. Thus, this water leaking test main concern for form tie
performance in water tank construction.

1.2 Reference

The scope of work is carried out in accordance to following:

No Description Document Ref. No.

1. Job Safety Analysis RWTP-SPM-HSE-JSA-08

2. Shop Drawings RWTP- GB-H-WTP-CWT-CNS-TAN-CRS-000016

3. Quality Assurance/ Quality Control Plan RWTP-SPM-MOS-ITP-008-00

5. Environmental Impact & Aspect RWTP-SPM-HSE-EIA-08

1.3 Materials

Item Materials Usage

1. Water Pressure Gun Water leaking test purposes

2. Form tie Connect opposite faces of wall formwork to restrain the applied
concrete pressures

3. Corkjoint Swellable Waterstop


Superswell @47B

20x15mm

4. SIKA 215 Grout Repairs to concrete structures and grouting works

REF. NO: RWTP-SPM-MOS-008-00 Page 3


RWTP
.. · Air Selangor RASAU WATER TREATMENT PLANT
�GAMUDA
PENGURUSAN AIR SELANGOR
SON BHD
METHOD STATEMENT

1.4 Manpower

Item Designation Responsibilities

1. Construction manager - Responsible for monitoring the overall construction


activities, safety, and environmental issues
- Provide all necessary resources, safety and quality
measures to implement the earthwork activities

2. Site Engineer Planning, coordinating, supervising site activities

3. sss Conduct site toolbox meeting and ensure all the site
staffs obey the safety and health regulations

4. General Worker Helper

1.5 Work Procedure

1.5.1 Water Leaking Test

1) Prefabricated of 6" MS pipe with the following components (refer to figure 2)


• flange at one end with 6 to 8 nos. of 16mm dia. fasteners and end cap at the
other end
• pressure gauge and release valve
• Adaptor for pressure pump
• rubber gasket
2) The 6" dia. pipe with flange will be fixed to the pre-selected form-tie (refer to figure 1)
position with 6 to 8nos of 16mm dia. bolts fastener at 50mm to 65mm length tighten
into the wall and with a layer of rubber gasket to prevent loss of pressure.
3) Once installed, the pipe will be filled with water until completely filled up and air
bubble released.
4) Then pipe will be connected to compressor and pressure will be slowly increased to
require reading at 0.8 bar as per specification 2.14.18.
5) The test will be hold for 7 days to determine the said functionality of the swellable
water stop.

REF. NO: RWTP-SPM-MOS-008-00 Page 4

You might also like