Professional Documents
Culture Documents
Payment Procedures Under FIDIC 2017 Conditions of Contract 1708427163
Payment Procedures Under FIDIC 2017 Conditions of Contract 1708427163
Payment Procedures Under FIDIC 2017 Conditions of Contract 1708427163
FIDIC 2017 Redbook’s provisions for advance payment are outlined in Clause 14,
emphasizing the necessity for a clear agreement on the amount, terms, and
security. The contractual requirement of an Advance Payment Guarantee adds a
layer of financial security for the Employer. However, the Contractor must be
diligent in adhering to the repayment schedule to avoid incurring interest
charges as per the contract terms, promoting a fair and secure mechanism for
project initiation
2.0 PROGRESS PAYMENTS
Progress payments play a pivotal role in sustaining contractor operations. The
process involves several steps, and adherence to these procedures is crucial for
both parties
2.1. CONTRACTOR SUBMITS STATEMENT (C14.3)
The Engineer ensures that specific prerequisites are met before certifying
interim payments. These include the owner's approval of the performance bond
and the appointment of the Contractor's representative, subject to the
Engineer's approval
2.3. FAIR DETERMINATION BY ENGINEER (C14.6)
The Engineer verifies that the net amount due to the contractor, after
deductions, meets the minimum specified in the contract. If the amount falls
below the minimum, the contractor is not entitled to an interim payment
certificate, and the Engineer notifies the contractor
2.5. INTERIM PAYMENT CERTIFICATE ISSUANCE (C14.6)
The employer must make the payment to the contractor within 56 days of the
contractor's submittal of the statement and supporting documents. Failure to
comply entitles the contractor to take actions, including suspension of work and
termination, after specified notice periods. Additionally, the contractor is
entitled to financial charges on late payments without prior notice or
certification
3.0 FINAL PAYMENT
Final payment marks a significant milestone in project closeout, signifying
agreement on all aspects. The final payment procedure involves the following
steps
3.1. CONTRACTOR RECEIVES PERFORMANCE CERTIFICATE
If the contractor does not apply for final payment, the Engineer requests the
draft statement within 28 days. If an agreement is reached, the contractor
submits the final statement. If not, the Engineer makes a fair determination and
issues the Final Payment Certificate.
3.4. FINAL STATEMENT SUBMISSION (C14.11)
AND WRITTEN DISCHARGE (C14.12)
After reaching an agreement on the draft statement, the contractor submits the
final statement along with a written discharge
3.5. FINAL PAYMENT CERTIFICATE ISSUANCE (C14.13)
The Engineer is required to issue the Final Payment Certificate within 28 days of
receiving the final statement and written discharge. Failure to certify on time
entitles the contractor to financial charges on late certification.
3.6. EMPLOYER'S PAYMENT DEADLINE (C14.7)
The employer must make the payment (certified amount) to the contractor
within 56 days of receiving the Final Payment Certificate. Failure to comply
results in financial charges or interest on late payments