Material List Template
Material List Template
Project Name:
Project Location:
Item Mobilization Materials Qty. Unit Rate Cost Cost w/ 10% margin
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
SUBTOTAL - -
Item Materials for Civil Works Qty. Unit Rate Cost Cost w/ 10% margin
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
SUBTOTAL - -
Item Materials for Civil Works Qty. Unit Rate Cost Cost w/ 10% margin
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
SUBTOTAL - -
Item Materials for ducting Qty. Unit Rate Cost Cost w/ 10% margin
- -
-
-
-
-
-
-
-
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
SUBTOTAL - -
Total Budget
- AED
- AED w/ 10% margin
Site Engineer
Procurement Specialist
MATERIAL LIST
Item Mobilization Materials Qty. Unit Rate Cost Cost w/ 10% margin
1 Temporary Fencing 20 rolls 65.00 1,300.00 1,430.00
2 Personal protective equipment (PPE) 5 pcs 102.85 514.25 565.68
3 First Aid Kit 1 pc 23.00 23.00 25.30
4 Caution Tape 4 rolls 10.00 40.00 44.00
5 Safety Cones 8 pcs 20.00 160.00 176.00
6 Taslleeh Signage 1 pc 4,000.00 4,000.00 4,400.00
7 Vertical Storage Cabinet (HDPE) 2 pcs 2,900.00 5,800.00 6,380.00
SUBTOTAL 11,837.25 13,020.98
Total Budget
17,645.75 AED
19,410.33 AED w/ 10% margin
Site Engineer
Procurement Specialist