CLIENT: KENYA WILDLIFE SERVICE CASH FLOW FORECAST

CONTRACTOR: TELLO COMPANY LTD

MONTHS EXPENDITURE WORK GRAPHIC MONTH 1 MONTH 2 MONTH 3 MONTH 4 MONTH 5 MONTH 6
WEEKS WEEK CUMULATIVE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
0 0 OUTLAY
34,000,000

32,000,000
SITE ESTABLISHMENT 4,141,200 4
Mobilisiation
Services and utilities
Hoarding / Site security 30,000,000
Setting up office and stores

SUBSTRUCTURES 11,440,500 8 28,000,000


Site clearance /Ssetting out
Excavation
Foundation Concrete
26,000,000
Foundation Walling
Filling
Reinforced Concrete Slab
WALLING 15,140,784 12 24,000,000
Masonry works
Concrete works
EPS 22,000,000
Painting
ROOF 18,159,057 13
Wall Plate 20,000,000
Roof structure
Rainwater Goods
Eaves, Filling and Fascia
WINDOWS 18,904,438 14 18,000,000
Casement Frames
Window Cills
Glazing 16,000,000
DOORS 20,360,157 15
Frames
Doors 14,000,000
Ironmongery
EXTERNAL WORKS 21,252,742 15
Plaster and Pointing
12,000,000
Slabs
INTERNAL FINISHES 25,864,995 16
Wall Finishes
Floor Finishes 10,000,000
Ceiling Finishes
FIXTURES AND FITTINGS 26,297,907 17
Wardrobes 8,000,000
Cabinets and Cupboards
Pelmet boxes
PLUMBING AND DRAINAGE 31,226,979 19
6,000,000
Tanks and plumbing
Fittings and accessories
Waste water system
Testing 4,000,000
ELECTRICAL WORKS 31,527,825 20
Cabling and wiring
Electrical fittings 2,000,000
Earthing
Mainline connection
0
0 4 8 12 13 14 15 15 16 17 19 20