Professional Documents
Culture Documents
1001-1 - Att1-1 Scope of Indirect Work - R2 - Initialed
1001-1 - Att1-1 Scope of Indirect Work - R2 - Initialed
MSP-ICS-1001-1
Revision 2
Exhibit A, Attachment 1-1
Scope of Indirect Work
Page 1 of 11
Exhibit A
Scope of Work
Attachment 1-1
Scope of Indirect Work
Document No. MSP-ICS-1001-1
Revision 2
Exhibit A, Attachment 1-1
Scope of Indirect Work
Page 2 of 11
Table of Contents
1. Introduction ................................................................................................ 3
2. Transportation ............................................................................................ 3
7. Utility ........................................................................................................... 9
7.1. Electricity ............................................................................................... 9
7.2. Telecommunications ............................................................................ 10
7.3. Water ................................................................................................... 10
7.4. Sanitary Waste .................................................................................... 10
7.5. Fuel ......................................................................................................11
7.6. Steam, Air, Nitrogen for Pre-commissioning .........................................11
1. Introduction
The following explanatory notes are to be used in conjunction with
Attachment 1-1 Scope of indirect work_table, which utilizes the same
item descriptions as detailed herein.
2. Transportation
The Subcontractor shall transport all indirect materials and Construction
Equipment.
4. Temporary Facilities
4.1. Jobsite Temporary Facilities
The temporary facilities for common use will be provided for in-plant area
ONLY. For areas other than the in-plant area, the Subcontractor shall
provide the temporary facilities, such as toilets, rest shelters, etc
Workers shelters
Equipment & vehicles maintenance shop
First AID Facility
Toilets
Ablutions
The Subcontractor shall provide its own Jobsite offices complete with
typical office furniture and shall reticulate with power, telephone and data
connections. The Subcontractor shall be responsible for provision of
computers, printers, copiers, scanners, conference phones, office
equipment and the like as well as general office supplies/consumables.
5.2.2. Medicals
Subcontractor shall provide the initial emergency paramedic level
treatment at the Jobsite while Chiyoda shall provide emergency transport
by ambulance from the jobsite to a local hospital.
5.2.3. Safety
The Subcontractor shall provide all safety equipment (such as fire
extinguisher, safety instrument etc.) for both Temporary facilities and
Jobsite.
5.2.4. Security
Chiyoda will carry out security screening at the Jobsite main gate and
overall project area. Chiyoda will provide primary security services
including issuance of ID badges. The ID will be provided to
subcontractor’s personnel without charging to Subcontractor. But any
second ID to be issued to Subcontractor’s personnel due to the damage
or loss of the original copy will be back charged to Subcontractor.
5.2.5. Environment
The Subcontractor shall comply with the environmental requirements of
Document No. MSP-ICS-1001-1
Revision 2
Exhibit A, Attachment 1-1
Scope of Indirect Work
Page 8 of 11
Any environmental issues arising from the use and operation of the
Temporary facilities located outside of the Jobsite shall be under
Subcontractor’s responsibility.
5.2.7. Others
Chiyoda will provide common rest shelters, toilets and ablutions. The
operational cost shall be borne by Chiyoda. But if any damage or misuse
occurred by subcontractor’s personnel the remedy cost shall be charged
to Subcontractor.
6.2. Scaffolding
Chiyoda will provide Common Scaffolding in particular areas of the
Project Site for use by Subcontractor. Tag list, Tag map and Guideline for
Common Scaffolding are attached to Exhibit C. Additional scaffolding
other than Common Scaffolding shall be provided and managed by
Subcontractor, refer to Attachment 1-3 of Exhibit A.
7. Utility
7.1. Electricity
The Subcontractor shall provide all electricity required for the Work.
The Subcontractor shall reticulate this from the distribution boards to the
Document No. MSP-ICS-1001-1
Revision 2
Exhibit A, Attachment 1-1
Scope of Indirect Work
Page 10 of 11
7.2. Telecommunications
7.3. Water
7.3.1. Drinking Water
The Subcontractor shall be responsible for providing drinking water.
7.5. Fuel
The Subcontractor shall provide all fuels required for the Work.
The fuel supply shall be arranged by tank lorry; fueling station on jobsite
will not be allowed.