JOB SAFETY ANALYSIS

JSA NO. Department / Activity/


Job Title: Routine/ Non Routine New/ Revised
No…
Reference work Permit no:

Supervisor:
JOB SAFETY ANALYSIS Prepared By:

Plant Location:(UNIT-1)
Department: Project
Niacinamide Expansion Reviewed By:

Job Description: Gas cutting work.


Approved By:

SEQUENCE OF TASK POTENIAL HAZARDS PREVENTIVE MEASURES

 Burns  Deploy trained fire watcher at hot working area.


 Damaged or leaking  Inspect the cylinder & hoses before starting the work.
 Gas Cutting work cylinders or hoses  Ensure inspection tag must be displayed on the cutting set.
 Fire & Explosion due to  Ensure competent/ designated person will perform this activity.
mishandling of Gas  Follow gas cutting safety procedures & handling of compressed gas
cutting Set cylinders.
 Fire hazard due to bad  Wear mandatory PPEs like cutting goggles, safety shoes, apron, helmet
housekeeping such as etc.
paper, wooden material,  FBA & NRV should be fixed for gas cutting set.
chemical material  All cylinder should be secured with trolley.
available near about hot  Ensure compressed gas leakage system is provided
work area  Ensure competent/ designated person will perform this activity.
 Ensure remove flammable material from working area before starting
the work.
 Cordoning of the area.
 Ensure near man hole, OWS drain properly covered with fire blanket
before starting the work (if applicable)
 Ensure proper cylinder trolley
 Ensure fire extinguisher at cutting area.
 Make sure spark containment is used such as a fire blanket.
 Ensure All electrical cable over had.
 Use of job specific PPE

Day-1 Day-2 Day-3

Permit issuer

Permit acceptor

Page 1 of 2
Format No.: EHS-006/F06-00 Effective Date:
Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS
Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety officer

Approved By HOD

Page 2 of 2
Format No.: EHS-006/F06-00 Effective Date:

You might also like