Professional Documents
Culture Documents
Ddd-Lmind-09-Pj-Wp-008 Weekly Progress Report 2 Feb 2024 - 8 Feb 2024
Ddd-Lmind-09-Pj-Wp-008 Weekly Progress Report 2 Feb 2024 - 8 Feb 2024
Ddd-Lmind-09-Pj-Wp-008 Weekly Progress Report 2 Feb 2024 - 8 Feb 2024
1. Project Summary
The achievement progress work for this weekly period:
Accumulative in Last Progress in Accumulative in This
Week This Week Week
Analysis:
(1) Concrete tank is under hydro test, diffusser installation work inside concrete tank is
postponed
2. EHS Performance
DDD Personnel on Board
Personnel on
02/02 03/02 04/02 05/02 06/01 07/02 08/02
No.
Board /24 /24 /24 /24 /24 /24 /24
Indirect
1 Personnel 3 3 0 3 3 3 3
Direct
2 Personnel 6 6 0 6 6 6 6
3 Camp 0 0 0 0 0 0 0
Total 9 9 0 9 9 9 9
Safety’s KPI
Fatality = 0 LTA = 0 FAC = 0 MTA = 0
Environmental Impact = 0
Weekly Report
Lamipak Indonesia New Plant Project
3. Weather Condition
Date/Time 02/02 03/02 04/02 05/02 06/02 07/02 08/02
00 – 01 AM
01 – 02 AM
02 – 03 AM
03 – 04 AM
04 – 05 AM
05 – 06 AM
06 – 07 AM
07 – 08 AM
08 – 09 AM R
09 – 10 AM R
10 – 11 AM R
11 – 12 PM
12 – 13 PM R
13 – 14 PM R
14 – 15 PM R
15 – 16 PM R
16 – 17 PM
17 – 18 PM
18 – 19 PM
19 – 20 PM
20 – 21 PM
21 – 22 PM
22 – 23 PM
23 – 24 PM
Note: R = Rain stopped the work.
Weekly Report
Lamipak Indonesia New Plant Project
4. Executive Milestones:
4.1 MEP
No Planned Actual
Description Status Remarks
(P) (A)
Intake Pipe
Influent Line Pipe Installation
7 Selector 4 Jan 2024 5 Jan 2024
has been completed 90%
Installation
5. Area of Concern
None
None
Weekly Report
Lamipak Indonesia New Plant Project
15. Filtration and RO pipe, Pipe Fabrication and Marking progress has been completed 37.93%
16. Submersible Pump, Skid Fabrication and Marking progress has been completed 42.37%
17. Dosing Pump Skid, Skid Fabrication and marking
18. Emergency Tank Pipe, Difusser Pipe Installation
19. Central Tube, Support Fabrication progress has been completed 25%
20. Chemical Dosing Pipe and Tubes, Pipe and support installation has been completed 24.14%
21. Sludge Transfer Pipe, Pipe and support installation has been completed 24.14%
Problems
None
Action to be taken
None
1. Weekly Direct Manpower Tracking.
Day Number 1 2 3 4 5 6 7
No
02/02/ 03/02/ 04/02/ 05/02/ 06/02/ 07/02 08/02/
Building 2024 2024 2024 2024 2024 2024 2024
P 11 11 11 11 11 11 11
Week Labor Force
A 9 9 0 9 9 9 9
P 11 11 11 11 11 11 11
1 WWTP
A 9 9 0 9 9 9 9
(REV B) (REV 0)
1 MEP 30 30 0 6
2 CSA 41 41 0 40
Total 71 71 0 46
Total Drawing Already Issued for Approval (IFA) 0%
Total Drawing Already Approved for Construction (AFC) 69%
Total Drawing already submission to Owner 31%
Notes:
IFA: Issue for Approval drawing. IFR: Issue for Review drawing. IFC: Issue for Construction
Weekly Report
Lamipak Indonesia New Plant Project
9.1 SI status
SI Receive VO Submission
No. Contens Description Status
Number Date Number Date
- - - - - - -
9.2 VO status
Date Return
Date
No. No. Document Description Back from Status
Submission
Owner
- - - - - -
1 MEP - - - -
2 CSA - - - -
Total - - - -
Total VO already Approved 0%
Weekly Report
Lamipak Indonesia New Plant Project
DDD-
LMIND-
Plumbing - Zuki -
10 09-MM- Zuki 05-Jan-2024 V -
Union Ball Valve PVC
LST-
S.0048
DDD-
LMIND- Plumbing - KDJ -
11 09-MM- Swing Check Valve KDJ 05-Jan-2024 V -
LST- PVC
S.0049
DDD-
LMIND-
MAS Pumping Brand
12 09-MM- Fastact 07-Jan-2024 V -
Fastact
LST-
S.0050
DDD-
LMIND- MAS Chemical
13 09-MM- Anchor Brand Fischer Fischer 12-Jan-2024 V -
LST- At WWTP
S.0051
DDD-
LMIND-
Conceptual Draw FRP Tank T-
6 09-MS- 7-Jun-2023 08-Jun-2023 Not Aproved
4000
DWG-
006
DDD-
LMIND-
Conceptual Draw FRP Tank T-
7 09-MS- 7-Jun-2023 08-Jun-2023 Not Aproved
4100
DWG-
007
DDD-
LMIND-
Conceptual Draw FRP Tank T-
8 09-MS- 7-Jun-2023 08-Jun-2023 Not Aproved
4200
DWG-
008
DDD-
LMIND-
Conceptual Draw FRP Tank T-
9 09-MS- 7-Jun-2023 08-Jun-2023 Not Aproved
4300
DWG-
009
DDD-
LMIND- Approved
Floor Plan Shelter Elevation And
10 09-CV- 12-Jul-2023 26-Oct-2023 With
Section(1 Sheet) (AWC)
DWG- Comment
014
DDD-
LMIND- Approved
Barbending Schedule ForRoofing
11 09-CV- 12-Jul-2023 26-Oct-2023 With
(1 Sheet) (Awc)
DWG- Comment
023
DDD-
LMIND- Approved
12 09-EL- 13-Jun-2023 Layout Panel MCC & PLC 15-Jun-2023 With
DWG- Cmment
001
DDD-
LMIND-
13 23-Jun-2023 P&ID Diagram 26-Jun-2023 Approved
09-PR-
PID-001
DDD-
LMIND-
14 18-Dec-2023 WWTP ITP 22-Dec-2023 Resubmit
09-QC-
PLA-001
DDD-
LMIND-
15 31-Mei-2023 Equipment LIST IO PLC 7-Jun-2023 Approved
09-EL-
EQL-001
Weekly Report
Lamipak Indonesia New Plant Project
No
Documentation Remark
1 Photo on 02
February 2024,
Support Agitator
Anti-Rust
Painting
Weekly Report
Lamipak Indonesia New Plant Project
2 Photo on 02
February 2024,
Blower Header
Pipe Installation
3 Photo on 03
February 2024,
Agitator Support
Fabrication
4 Photo on 03
February 2024,
Centraling Tube
Support
Installation
Weekly Report
Lamipak Indonesia New Plant Project
5 Photo on 05
February 2024,
Reverse Osmosis
Product Pipe
Installation
6 Photo on 05
February 2024,
NaOH Tank and
Coagulant Tank
Agitator support
Fabrication
7 Photo on 06
February 2024,
Break the wall
for the pipeline
Weekly Report
Lamipak Indonesia New Plant Project
8 Photo on 06
February 2024,
Agitators
Support Painting
9 Photo on 07
February 2024,
Inlet and Outlet
Filtration Pipe
Installation
10 Photo on 07
February 2024,
Sediment Tank
Outlet Pipe
Installation
Weekly Report
Lamipak Indonesia New Plant Project
11 Photo on 08
February 2024,
Sediment Tank
Reposition
12 Photo on 08
February 2024,
Sludge Pump
Inlet Pipe
Support
Fabrication
Weekly Report
Lamipak Indonesia New Plant Project
16. Outstanding
a. MAS
b. VO
- - -
c. Drawing
- - - -
d. RFI
- - -
FEBRUARI MARCH APRIL
JOB DESCRIPTION Progress Of January
## 02/2 03/2 04/2 05/2 06/2 07/2 08/2 09/2 ## ## 12/2 13/2 14/2 15/2 16/2 17/2 18/2 19/2 20/2 21/2 22/2 23/2 24/2 25/2 26/2 27/2 28/2 29/2 01/3 02/3 03/3 04/3 05/3 06/3 07/3 08/3 09/3 10/3 11/3 12/3 13/3 14/3 15/3 16/3 17/3 18/3 19/3 20/3 21/3 22/3 23/3 24/3 25/3 26/3 27/3 28/3 29/3 30/3 31/3 01/4 02/4 03/4 04/4 05/4 06/4 07/4 08/4 09/4 10/4 11/4 12/4 13/4 14/4 15/4 16/4 17/4 18/4 19/4 20/4 21/4
Mechanical
A-1 Submersible Pump 1 1 1 1 1 1
A-2 Centrifugal Pump 1 1 1 1 1 1
A-3 Ultra Screen 1 1 1 1 1
A-4 Box Screen 1 1 1 1 1
A-5 FRP Tanks & Platform Delivered & Installed
A-6 Agitators 1 1 1 Heavy
A-7 HDPE Tanks Delivered & Installed
A-8 Blower & Diffuser 1 1 1 1 1 1
A-9 Central Tubes 1 1 1 1 1
A-10 MBBR Media & Cage (SS) 1 1 1 1 1 1 1 1
A-11 Steel Tank 1 1 1 1 1
A-12 Filtration Tank & Skid Skid & Tank Delivered 1 1 1 1 1 1 1
A-13 Reverse Osmosis & Skid Skid Delivered 1 1 1 1 1 1 1 1 1 1 1 1 1 1
A-14 Dosing Pump & Skid 1 1 1 1 1 1 1
A-15Sludge Press Machine 1 1 1 1 1 1 1
Electrical
B-1 Panel Control & HMI Panel & PLC Delivered 1 1 1 1 1
B-2 Cable Tray & Supports Delivered & Installed 1 1 1
B-3 Power Cables Routing 1 1 1 1 1 1 1
B-4 Instruments Cables Routing 1 1 1 1 1 1
B-5 Power Cables Connecting 1 1 1 1 1
B-6 Instruments Cables Connecting 1 1 1 1 1
B-7 Grounding Works 1 1 1 1 1 1 1
Instruments
D-1 Ultra Sonic Level Transmitter 1 1 1 1 1 1 1 1
D-2 Water Level Switch 1 1 1 1 1 1
D-3 Flow Meter Inlet & Outlet 1 1 1 1 1 1
D-4 PH, ORP & Lab Instruments 1 1 1 1 1 1 1 1 1 1 1
Piping & Supports
C-1 Pipe Supports Delivered & Partial Installed 1 1 1 1 1 1 1 1 1 1 1 1
C-2 Intake Pipe Selector Delivered & Installed 1 1 1
C-3 Pump Pit Pipe Partial Delivered 1 1 1 1 1
C-4 Equalization Pump Pipe Partial Delivered 1 1 1 1 1
C-5 Emergency Tank Pipe Partial Delivered 1 1 1 1 1
C-6 Chemical Treatment Pipe Partial Delivered 1 1 1 1 1
C-7 Filtration & RO Pipe Partial Delivered 1 1 1 1 1 1 1
C-8 Sludge Transfer Pipe Partial Delivered 1 1
C-9 Chemical Dosing Pipe & Tubes 1 1 1 1 1 1
C-10 Blower Piping (GIP) Delivered & Installed 1 1 1
C-11 Diffusser & Piping Piping Installed 1 1 1
Test & Commisioning
Electrification
E-1 Main Panel 1 1 1 1
E-2 Grounding Test 1 1 1
E-3 Conectivity 1 1 1 1 1
E-4 Instruments 1 1 1 1 1 1
Hydrotest
Fresh Water
F-1 Concrete Tank 1 1 1 1 1 1 1 1 1 1 1 1 1 1
F-2 FRP Tank 1 1 1 1 1
F-3 HDPE & Steel Tank 1 1 1 1 1
F-4 Ultra Screen 1 1 1
F-5 Sludge Screw Press 1 1 1
F-6 Piping System 1 1 1 1 1 1 1 1 1 1 1 1
Equipments Test
G-1 Blower & Diffusser Test 1 1 1 1 1
G-2 Pumps Test 1 1 1 1 1
G-3 Dosing Test 1 1 1 1 1
G-4 Agitators 1 1 1 1 1
G-5 Instruments 1 1 1 1 1 1