MS-0007 Hardscape Works
MS-0007 Hardscape Works
Project:
Method Statement
for
HARDSCAPE WORKS
Ref. BAS-MS-0007-00
Contents
1. PURPOSE .......................................................................................................................... 3
2. SCOPE .............................................................................................................................. 3
3. LEGISLATION AND CODE OF PRACTICE .............................................................................. 3
4. REFERENCES ..................................................................................................................... 4
5. DEFINITIONS .................................................................................................................... 4
6. RESOURCE ........................................................................................................................ 5
6.1 MATERIAL AND THEIR APPROVAL ........................................................................................................................... 5
6.2 SUBCONTRACTOR APPROVAL ................................................................................................................................ 5
6.3 TOOLS & EQUIPMENT ......................................................................................................................................... 5
6.4 SHOP DRAWING APPROVAL .................................................................................................................................. 5
7. RESPONSIBILITIES ............................................................................................................. 5
7.1 SR. PROJECT MANAGER ...................................................................................................................................... 5
7.2 CONSTRUCTION MANAGERS AND PROJECT ENGINEERS.............................................................................................. 6
7.3 TECHNICAL ENGINEER ......................................................................................................................................... 6
7.4 QA/QC ENGINEER............................................................................................................................................. 6
7.5 SITE ENGINEER .................................................................................................................................................. 7
7.6 QUANTITY SURVEYOR ......................................................................................................................................... 7
7.7 SAFETY OFFICERS ............................................................................................................................................... 7
7.8 SURVEYOR ........................................................................................................................................................ 8
7.9 SITE SUPERVISORS .............................................................................................................................................. 8
7.10 FOREMAN ...................................................................................................................................................... 8
7.11 DOCUMENT CONTROLLER .................................................................................................................................. 8
1. PURPOSE
This method statement is applicable to define the step-by-step procedures and to ensure that the
procedures for Hardscape works in the project are executed safely and in accordance with the contract
requirements, hazard and safety precautions implemented and all the Quality Assurance / Quality
Control activities are conducted in a systematic manner, work inspected and documented.
2. SCOPE
This method statement pertains to the hardscape works outlined in the project, encompassing the
following:
4. REFERENCES
1. Project Specifications
2. IFC Drawing and Shop Drawings.
3. Material Approvals / Manufacturer Recommendation
4. BOQ
5. Approved Project Quality Plan
6. Approved HSE Plan
7. No Objection Certificate
8. Permit to work.
5. DEFINITIONS
Definitions used within this document is detailed within the text shall have the meanings indicated
below unless otherwise clearly indicated by context of the use.
1. Project :
2. Employer :
3. Engineer :
4. Contractor : Basatin Landscaping LLC
5. PQP : Project Quality Plan.
6. MS : Method Statement.
7. ITP : Inspection & Test Plan.
8. RA : Risk Assessment
9. ITL : Independent Testing Laboratory.
10. WIR : Work Inspection Request.
11. MIR : Material Inspection Request.
12. HSEW : Health, Safety, Environment and Welfare.
13. IFC : Issued for Construction.
14. SD : Shop Drawing.
6. RESOURCE
Material List
7. RESPONSIBILITIES
Create and manage the master construction schedule for more than one project.
All operational issues, involving, people, skills, plant, financial.
Responsible for effectiveness, and efficiency of staff, plant, materials, logistics, Procurement,
subcontractor, management.
Client relationship & Staff relationships, grading, training, recruitment, and terminators.
Coordinates all facets of construction to ensure overall performance, with regards to budget,
planning, technical, and value engineering.
Manage staff development and ensure performance standards.
Ensure efficient use of human resources, and grading of staff, to increase or decrease current
positions.
Mange subcontractor performance.
Responsible for site cost implementation records and monitoring of set budget.
Ensure QA-QC Standards are set to be implemented and met.
Ensure HSE Standards are set, implemented, and met.
Overall responsibility or site safety.
Checking compatibility between production processes, test procedures and the applicable
documentation through review and circulation of the technical and administration document
related to the various activities.
Ensuring all personnel are fully aware with all the quality requirements and application for all
quality documents as relevant to their discipline.
Ensuring appropriate supervision for all work activities enabling quality related operations to be
effectively covered.
Coordinate with the Independent Testing laboratory representative so that all test is carried out
as required by specification and records as per the Quality Control Plan.
Stop all unsafe and substandard work activities.
7.8 Surveyor
The Surveyor will be responsible for all survey activities, control points, recording of survey data
as well as control and calibration of survey instruments.
7.10 Foreman
Preparation and execution the works at site as per the approved drawings.
Mange the required team at site.
Ensure the quality and safety of the work being performed and proper housekeeping.
Make the necessary preventive action to minimize the noise production during working hours.
Monitor that new employees are adequately trained and supervised always and comply with
safety precautions.
Organize the site activities safely and systematically so that work can be carried out as per the
required standard without any impact to workforce, equipment, materials and to the
environment.
Monitor that the Personal Protective Equipment of the work force are enough for current work
at hand.
Conduct daily "Toolbox Talks” and in advance of any critical work and enforce proper PPEs as
per task.
Attend weekly progress meeting and responsible for preparing Minutes of Meeting.
8.1 General:
Method listed in the references above shall be followed for the relevant works.
Relevant Personal Protective Equipment shall be provided and utilized by the workforce.
Appropriate Safety guidelines must be adhered during all stages of construction activity.
Necessary & mandatory work permit from the Authority shall be available prior to the start of the
activities.
Work area shall be barricaded as applicable and necessary.
Required safety sign boards shall be placed at the area.
1. Site Preparation: Adequate stock of material, testing equipment and consumables along with
sufficient manpower shall be arranged to carry out the work. Prior to start of activity, area and
access will be inspected to ensure that the area is ready for the work to start and already
approved by the Consultant/Engineers.
2. Setting Out: All the foundation co-ordinates as per the approved shop drawings were set out
on site and approved by the consultant.
3. Mortar bed: Dry Pack Mortar shall be cement/sand mortar (1:3) composed of one-part ordinary
Portland cement to three parts of sand by volume of works above damp-proof course level and
mortars for below damp-proof course shall be one-part sulphate resisting cement to three-part
sands.
4. Concrete haunching will be provided as per shop drawings approved by Engineer to support the
kerbs.
5. Kerb blocks will be set using a string line as a guide where possible and tapped into a place with
non-marking rubber mallet. It shall be placed over a 30mm thick dry mortar bed. The final level
and locations of kerb blocks will be checked at regular intervals by the Basatin Lands site
surveyor to ensure correct placement and heights in accordance with approved shop drawing
and specifications.
6. WIR shall be submitted as per approved ITP.
8.3 Method For Paving Installation On 50mm Thick Black Sand Bedding ((Vehicular &
Pedestrian)
Any loose material shall be compacted or removed. The site shall be wet down to ensure
compaction and if required compacted further with a plate compactor or vibrating roller.
8.3.2 Sub-grade:
Upon approval of setting out from the Engineer, A task briefing and walk of work area will take
place to ensure all labor & machine operatives are aware of the task ahead.
When all the above is complete the bobcats and excavators will then proceed to excavate/grading
pre-determined areas to design specification.
The sub-grade shall be graded and compacted to not less than 95% of MDD as per required level
to receive sub-base. Frequency of test one test per 1000m2 or as directed by the Engineer.
8.3.3 Sub-base:
All aggregates for use in the construction of the pavement Layer shall be obtained only from
sources approved by the Engineer.
The sub-base material shall consist of furnishing, spreading and compacting sub-base in
accordance with the details shown on approved shop drawings and the specification.
Each sub-base material layer shall be spread by finisher and/or grader or other approved
mechanical methods, watered shaped to a compacted thickness not exceeding 150mm and
compacted to the required grade and cross-section.
The sub-grade and sub-Base shall be compacted to not less than 98% maximum dry density
determined in accordance with BS 1377. Field density tests shall be carried out at a frequency of
one test per 1000m2 laid or as directed by the Engineer.
1. Setting out of granite paver shall be done as per shop drawing approved by Engineer.
2. The section detail or the shop drawing approved by Engineer shall be followed for installation.
3. Existing soil shall be compacted to 95% in accordance as mentioned above.
4. 1 layer of 1000G polythene sheet shall be laid with overlapping 150mm at joints.
5. Side shutters shall be installed in the setout area. Ensure line, level, and rigidity of shutters.
6. A393 mesh shall be installed with 350mm lapping. Cover block shall be provided so that the
mesh lays middle of concrete section. Side cover shall be minimum 40mm.
7. Concrete mix of C40 grade shall be poured and finished properly.
8. Once concrete is cured, the preparation for granite installation shall begin.
9. Cement sand mortar shall spread and levelled as per requirements and to an average thickness
of 50mm.
10. Approved granite slabs shall be then installed as per shop drawing approved by Engineer.
11. Expansion joints shall be provided as per article as per drawings.
12. Surveyor to ensure the levels and coordinates are as per approved shop drawing.
13. WIR shall be submitted as per ITP for Engineer’s inspection and approval.
8.6.2 Materials:
All materials used on site have to be approved prior to start any work. The following list is a summary
of key materials to be used for the activities.
1. Concrete mix as per design mix 3. Warning Tapes
2. A393 mesh 4. Emergency Kits
8.6.3 Preparation Prior To Concrete Placement:
1. Mechanical vibrators with adequate capacity needles ensured must be available in working
condition for placing concrete.
2. All the debris/binding wire pieces/unwanted materials shall be removed from the pouring
location.
3. Necessary prior information shall be provided to the Engineer and Testing agency prior to
starting concrete placement.
4. Formwork, steel reinforcement and accessories shall be ensured in proper locations, clean, free
of loose scale, dirt or other foreign coatings that may reduce bond to concrete.
5. Sub-base shall moisture uniform without pools or dry areas.
6. Necessary reference mark shall be provided to maintain the required finish level.
7. Ensure the curing arrangements are ready in place to cover the concrete immediate after finish
and before final setting time starts.
8. Ensure the necessary clearance has been taken from MEP & Precast team prior to proceed for
concrete.
8.6.5 Curing:
1. Curing activity begins as soon as free water has disappeared from concrete surface and finishing
has been completed.
2. Curing methods shall be of: Cure concrete by curing compound, by moist curing, by moisture-
retaining cover curing or by combining these methods.
3. Approved Curing compound shall be applied as per Manufacture recommendation.
4. If any surface defects observed after de-shuttering, it shall be notified to Engineer. The surface
shall be prepared for the acceptance of Engineer. Approved repair material shall be applied as
per manufacturer’s recommendation. Curing for the same shall be done accordingly.
1. Clear the area where the crosswalk raised platform will be installed. Remove any existing
pavement or materials as needed.
2. Excavate the area to the required depth according to the design specifications. This may include
removing existing soil or materials to make way for the base layers.
3. Install a well-compacted base coarse layer. The thickness and compaction requirements should
be in accordance with the shop drawing approved by the Engineer.
4. Install kerb stones and pavers as mentioned above.
5. Install bollards at designated locations along the crosswalk raised platform. Secure them firmly
to the pavement as per drawings / manufacturer recommendation.
6. Install tactile tiles on the sides of the crosswalk to assist visually impaired pedestrians as
mentioned above.
7. Apply crosswalk markings and install appropriate signage to indicate the presence of the
crosswalk raised platform.
8. A reflective solid triangle pavement marking in yellow shall be applied on the inclined surface
with pavers where vehicles will approach, in accordance with the approved drawing and using
materials that have been approved.
9. WIR shall be submitted as per approved ITP. Wheel Stopper Installation
1. Mark the positions for the wheel stopper on the asphalt road or pavers using chalk or spray
paint by the Surveyors.
2. Use a drill with a masonry bit to drill holes into the asphalt or pavers at the marked locations.
The hole diameter should be slightly larger than the diameter of the steel rod.
3. Remove any debris or loose material from the drilled holes using a brush or compressed air.
This ensures a better bond with the concrete.
4. Cut the 19mm diameter steel rods to the desired length. The length will depend on the
thickness of the precast wheel stopper and the depth of the drilled holes.
5. Insert the steel rods into the drilled holes. Ensure they are securely positioned and extend to
the recommended depth.
6. Prepare the non-shrink epoxy grout according to the manufacturer's instructions. Use a mix
suitable for outdoor applications and compatible with the surrounding environment.
7. Position the precast wheel stopper over the steel rods, ensuring a snug fit.
8. Adjust the position of the wheel stopper to align with the markings on the asphalt or pavers.
9. Pour the prepared non-shrink epoxy grout mix around the base of the precast wheel stopper,
filling the drilled holes.
10. Use a level to check and adjust the alignment of the precast wheel stopper. Make sure it is level
and straight.
11. Allow the non-shrink epoxy grout to cure according to the recommended time frame provided
by the manufacturer.
9. HSEW REQUIREMENTS:
Step-1: If a person is injured/need medical assistance, remove the injured person from where
danger still exists and get first aid, do not leave the injured person until help arrives.
Step-2: For major injuries and incidents, call emergency service required and give location and
nature of emergency.
HSE Officer -
CM -
PM -
Police - 999
Ambulance - 998
Civil Defense (Fire) - 997
PPE requirement
The following PPEs shall be worn by workers involved:
Helmet, safety goggles, hand gloves, overall, safety shoes and ear plugs
9.4 Housekeeping
Housekeeping of fabrication and installation sites will be done in accordance with the OSHAD, DMT
and project safety manual.
11. RECORDS:
1. Work inspection request approvals.
2. Material inspection request approvals
3. Test reports
12. DISTRIBUTION: -
Copies of this Method Statement shall be circulated to the following for Information & action.
1. Project Manager. 4. HSE officer.
2. Project Engineer / Site Engineer. 5. Supervisors
3. QC Engineer / Inspector. 6. Foremen.
13. ATTACHMENT
1. Inspection and Testing Plan (ITP)
2. Inspection Check List (ICL)
3. Risk Assessment (RA)
*****************
Responsibility
Frequency of Test Applicable Specification /
SN Inspection / Test to be carried out Acceptance Criteria Control Data / Forms Inspection Method Sub Main
/ Inspection Standard Engineer Third Party
contractor Contractor
I Pre- Construction Activities
Prior to start the Employer's/ Authority/Engineer Approved Method Document
1 Approval of Method Statement 1. Standard Specification- ADM N/A H R/A N/A
activity Approval Statement Verification
Landscape spceifications
Prior to start the Employer's/ Authority/Engineer Approved Material Document
2 Approval of Materials N/A H R/A N/A
activity Approval 2. Landscape specification: Submittal Form Verification
Prior to start the Employer's/ Authority/Engineer Division 32: Document
3 NOC's and Permits Section-321400: Paver Authority Approval N/A H R/A N/A
activity Approval Verification
Section-321600 Curbs And
Prior to start the Employer's/ Authority/Engineer Approved Shop Drawing Document
4 Approval of Shop Drawing Edgings N/A H R/A N/A
activity Approval Submittal Form Verification
II Main Activities (Installation)
Pre-examination of the site done Visual inspection of
by the contractor. Site daily excavation side
1 Safety and Cleanliness Each area HSE plans N/A P&H H&A N/A
activities have been supervised by slopes & formation;
the safety officer. Survey check on
Material sample shall meet the
1 sample every
2 Sampling and Testing 3 minimum requirements as per Test Report Document Review N/A P&H W&A P
1,000m
specification
1. Standard Specification- ADM
Hardscaping work alignment, levels
Landscape spceifications
and locations carried out by the Survey Visual Inspection
3 Setting out Each area N/A P&H W&A N/A
Surveyor to the approved drawings records/WIR/Checklist /WIR
2. Landscape specification:
and specifications.
Division 32:
As per approved shop drawing and
Excavation & Formation of Sub Section-321400: Paver
Each area 1 test approved method statement, Excavation Permit/WIR/
4 Section-321600 Curbs And Visual Inspection N/A P&H H P
grade every 500 sq. m. Subgrade 200mm thk layer min. checklist
Edgings
MDD 95% & CBR 30
Sub base shall be laid at the depth
specified in the specification and
Each area 1 test approved shop drawing. Survey records/WIR/ Visual Inspection/
5 Sub base Laying & Compaction N/A P&H W&A P
every 300 sq. m. Compacted subbase of 150mm Test Report Hold Point
thickness shall have minimum of
98% MDD
Page 1 of 2
INSPECTION & TEST PLAN (ITP) FOR HARDSCAPE WORK
Employer Project ITP Ref. No. BAS-ITP-0012-00
Engineer Discipline HARDSCAPING WORKS Date 22-03-24
Contractor Basatin Landscaping MS Ref. No. BAS-MS-0012-00
Responsibility
Frequency of Test Applicable Specification /
SN Inspection / Test to be carried out Acceptance Criteria Control Data / Forms Inspection Method Sub Main
/ Inspection Standard Engineer Third Party
contractor Contractor
Pre- Construction Activities Formwork shall be constructed
accurately to represent the shape
6 Shuttering Each area Checklist Visual Inspection N/A P&H S N/A
of the concrete as detailed on the
kerb location/layout plan
Approved design mix for Concrete
7 Concrete Blinding Each area blinding. Concrete pouring shall Checklist Visual Inspection N/A P&H S N/A
follows the standard procedures
Approved Sand bedding shall be
laid at the depth specified in the
8 Sand Bedding Each area 1. Standard Specification- ADM Checklist Visual Inspection N/A P&H S N/A
specification and approved shop
drawing. Landscape spceifications
Page 2 of 2
Check List for Hardscape Works
Project Name Employer
Contractor Basatin Landscaping Engineer
Checklist Title: Check List for Hardscape Works Checklist No. BAS-ICL-0007-00
Works Location: Related ITP # BAS-ITP-0007-00
Related Drawing(s) Related MS # BAS-MS-0007-00
Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
Preliminary
Accompanying document :
Name
Designation
Date
Page 1 of 1
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 1 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 2 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 3 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 4 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 5 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 6 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 7 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 8 of 11
Project CLIENT CONSULTANT CONTRACTOR
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 9 of 11
Project CLIENT CONSULTANT CONTRACTOR
RISK MATRIX
SEVERITY (CONSEQUENCE)
PROBABILITY
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent (5) 5 10 15 20 25
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 10 of 11
Project CLIENT CONSULTANT CONTRACTOR
YES NO
E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 11 of 11