Berdasarkan Hasil Join Survey Pada Bulan November 2023 Di Pit Nakula Dimana Deviasi -9.89 %
Antara Hasil Truck Count Dan Data Survey Maka Perlu Dilakukan Pengecekan Mengenai Kapasitas
Optimal Muatan DT Liugong Di Pit Nakula.
Berdasarkan Hasil Uji Petik Pada Bulan November 2023 Rata-rata Muatan DT Liugong Di Pit
Nakula Sebesar 19.87 BCM / Rit
WEEK 4
2
RATA-RATA 24.35 19.87
Justifikasi Perubahan Muatan Di Pit Nakula
“Come With Solutions”
Perhitungan
Hasil Uji Petik Muatan
Hasil Uji Petik OB Soil Lumpur
Liugong 19.86 17.6 13.2
Mercy 12 9.6 7.2
Jumlah Ritasi HRM (Rit) Data Survey Truk Count HRM (Bcm)
Truck Count Deviasi (Bcm) %
OB Soil Lumpur OB Soil Lumpur TOTAL OB Soil Lumpur TOTAL
Liugong 17797 15 353,940.08 353,940.08 391,534.00 0 198 391,732.00
Mercy 15 180 0 0 180.00
TOTAL 353,940.08 391,912.00 -37,971.92 -9.69%
Perhitungan Truck Count menggunakan 22 BCM/Rit
Jumlah Ritasi HRM (Rit) Data Survey Hasil Uji Petik (Bcm)
Truck Count Deviasi (Bcm) %
OB Soil Lumpur OB Soil Lumpur TOTAL OB Soil Lumpur TOTAL
Liugong 17797 15 353,940.08 353,940.08 353448.42 0 198 353,646.42
Mercy 15 180 0 0 180.00
TOTAL 353,940.08 353,826.42 113.66 0.03%
Perhitungan Truck Count menggunakan 19,86 BCM/Rit (Disesuaikan Dengan Rata-Rata Uji Petik Bulan November 2023)
Dari Hasil Perhitungan Diatas Dapat Disimpulkan Bahwa Dengan Perhitungan Truck Count Dirubah Menyesuaikan Rata-Rata Muatan
Optimal Di Pit Nakula Sebesar 19.86 BCM / Rit Deviasi Antara Truck Count Dengan Data Survey 113.66 BCM Atau 0.03 %