Project Name Project Code Contractor Rev. Contract Duration Time Elapsed %
Albatha land port essential face lifting works 21SACG00025ALFL Al Joudah 18 Months 74.82%
Milestones as per revised Program Completion Due Date Status % complete Penalty
Submitted
COMMENT
MILESTONE
Overall Project
Construction
57.13%
97.81%
48.38%
-
Time Elapsed
Albatha land port essential face lifting works Al Joudah 18 Months 74.82%
Stakeholder Engagement Plan Plan to setting out the strategy for what Required 11.11% 0.56% 100.00% 0.56%
stakeholders will be engaged and when
E.1.2 Deliverable Description Detailed Design Stage Weighting Over All Weight % Complete Progress % Complete
Contract Schedule Monthly update of the 7.70% 3.47% 100.00% 3.47%
schedule
Weekly Reports (Construction Progress Tracker) Required 7.70% 3.47% 100.00% 3.47%
Monthly reports along with Dashboards Required 7.70% 3.47% 100.00% 3.47%
Risk, Change and trend Management Report Required 7.70% 3.47% 100.00% 3.47%
Quality Plan Required 7.70% 3.47% 100.00% 3.47%
Safety, Health and Environmental Plan Required 7.70% 3.47% 100.00% 3.47%
Hazard Elimination and Risk Reduction Document Required 7.70% 3.47% 100.00% 3.47%
Safety in Design Reviews and Workshops Report Required 7.70% 3.47% 100.00% 3.47%
Hazard Register Required 7.70% 3.47% 100.00% 3.47%
Pre-Construction Information Required 7.70% 3.47% 100.00% 3.47%
Project Execution Plan Required 7.70% 3.47% 100.00% 3.47%
Presentation slides and minutes of meeting
Presentation from a presentation to be given to the HE Required 7.70% 3.47% 100.00% 3.47%
DG.
Stakeholder Engagement Plan Required 7.60% 3.42% 100.00% 3.42%
E.1.3 Deliverable Description Construction Weighting Over All Weight % Complete Progress % Complete
Monthly reports along with Dashboards Required 5.00% 2.50% 76.43% 1.91%
Risk, Change and trend Management Report Required 5.00% 2.50% 76.43% 1.91%
Quality Plan Required 5.00% 2.50% 100.00% 2.50%
Method Statement Required 5.00% 2.50% 76.43% 1.91%
Inspection and Testing Plan Required 5.00% 2.50% 76.43% 1.91%
Zatca Quality Forms Required 5.00% 2.50% 100.00% 2.50%
Safety, Health and Environmental Plan Required 5.00% 2.50% 100.00% 2.50%
Hazard Elimination and Risk Reduction Document Required 5.00% 2.50% 100.00% 2.50%
Safety in Design Reviews and Workshops Report Required 5.00% 2.50% 100.00% 2.50%
Hazard Register Required 5.00% 2.50% 76.43% 1.91%
Pre-Construction Information (PCI)
containing the available H&S information
Pre-Construction Information needed to identify hazards and risk Required 5.00% 2.50% 100.00% 2.50%
associated with the proposed design and
construction work
Provision of Information for the Health and Safety File Required 5.00% 2.50% 100.00% 2.50%
Local Content Score Card Required 5.00% 2.50% 0.00% 0.00%
Project Execution Plan Required 5.00% 2.50% 100.00% 2.50%
Presentation Summary of project status to be presented. Required 5.00% 2.50% 76.43% 1.91%
Stakeholder Engagement Plan Plan to setting out the strategy for what Required 5.00% 2.50% 100.00% 2.50%
stakeholders will be engaged and when
E.2.1 Deliverable Description Detailed Design Stage Weighting Over All Weight % Complete Progress % Complete
List of Deliverables
submitted at this stage.
Indicate if a required
List of Deliverables deliverable for this stage 7.69% 7.31% 100.00% 7.31%
submission (as per
agreement
at Commencement Stage)
has not been included.
Construction Phasing Detailed Report and drawings (all phases Required 7.69% 7.31% 100.00% 7.31%
and individual phases) with required
applicable information to form
construction work plan and land port
operations mitigation plan and are Subject
to No Objection by the First Party
Specification Required 7.69% 7.31% 100.00% 7.31%
Schedules Required 7.69% 7.31% 100.00% 7.31%
Calculations Required 7.69% 7.31% 100.00% 7.31%
Presentation Required 7.69% 7.31% 100.00% 7.31%
Comment Response Sheet (CRS) Required 7.69% 7.31% 100.00% 7.31%
Bill of Quantities Required 7.69% 7.31% 100.00% 7.31%
Quality checklists Required 7.69% 7.31% 100.00% 7.31%
Issued for Construction Documentation Required 7.69% 7.31% 100.00% 7.31%
E.2.2 Deliverable Description Project Inception Weighting Over All Weight % Complete Progress % Complete
List of Deliverables Required 33% 1.67% 100.00% 1.67%
second party site areas Required 33% 1.67% 100.00% 1.67%
construction phasing Required 33% 1.67% 100.00% 1.67%
E.3.1 Deliverable Description Construction Stage Weighting Over All Weight % Complete Progress % Complete
Requirement
Construction Execution Plan Required 3.571% 3.571% 100.00% 3.57%
Shop Drawings documentation Required 3.571% 3.571% 96.04% 3.43%
Logistic Plan Required 3.571% 3.571% 100.00% 3.57%
Long lead items List with P.O. planned dates and P.O. numbers Required 3.571% 3.571% 100.00% 3.57%
Construction Health and Safety Plan Required 3.571% 3.571% 100.00% 3.57%
Mobilization Report Required 3.571% 3.571% 100.00% 3.57%
Construction Constructability Report Required 3.571% 3.571% 100.00% 3.57%
Project Construction Electrical Works Procedure Required 3.571% 3.571% 100.00% 3.57%
Project Construction Mechanical Works Procedure Required 3.571% 3.571% 100.00% 3.57%
Project Construction Piping Works Procedure Required 3.571% 3.571% 100.00% 3.57%
Project Construction Welding Works Procedure Required 3.571% 3.571% 100.00% 3.57%
Project Construction Field Material Management Procedure Required 3.571% 3.571% 100.00% 3.57%
Project Construction Quality Management System Procedure Required 3.571% 3.571% 0.00% 0.00%
Project Construction Control of Non-Conforming Items Required 3.571% 3.571% 100.00% 3.57%
Procedure
Project Construction Control of Material Testing Procedure Required 3.571% 3.571% 100.00% 3.57%
Project Construction Method Statement Guideline Required 3.571% 3.571% 100.00% 3.57%
Project Construction Progress Reports Procedure Required 3.571% 3.571% 0.00% 0.00%
Project Construction Technical Query Procedure Required 3.571% 3.571% 100.00% 3.57%
E.4.1 Deliverable Description Construction Stage Weighting Over All Weight % Complete Progress % Complete
Requirements
Project Construction Punch List Procedure Required 12.500% 2.50% 100.00% 2.50%
Project Construction Completions and Turnover Procedure Required 12.500% 2.50% 100.00% 2.50%
Project Construction As-Built Drawings Required 12.500% 2.50% 0.00% 0.00%
Testing Plan Detailed plan 12.500% 2.50% 100.00% 2.50%
Maintinance plan Detailed plan 12.500% 2.50% 0.00% 0.00%
Commissioning Plan Detailed plan 12.500% 2.50% 100.00% 2.50%
Hand-over Plan Detailed plan 12.500% 2.50% 0.00% 0.00%
Quality Records Detailed plan 12.500% 2.50% 100.00% 2.50%
Deliverable Description Handing Over Weighting Over All Weight % Complete Progress % Complete
As Constructed Drawings Required 33.3% 33.30% 0.00% 0.00%
Maintenance Records Required 33.3% 33.30% 0.00% 0.00%
Punch List Required 33.3% 33.30% 0.00% 0.00%
Weekly Progress of Al Batha Land Port Essential Face Lifting Works updated as of 9 September 2023