Professional Documents
Culture Documents
Operation Research MCQ (Answers)
Operation Research MCQ (Answers)
Operations Research
65. Any feasible solution which optimizes (minimizes or maximizes) the objective function of the LPP is
called as _______
a. Optimal solution
b. Non-basic variables
c. Solution
d. Basic Feasible solution
66. Which method is an iterative procedure for solving LPP in a finite number of
steps? a. Simplex algorithm
b. Slack variable
c. Big M method
d. Simplex method
67. In simplex algorithm, which method is used to deal with the situation where an infeasible starting
basic solution is given?
a. Slack variable
b. Simplex method
c. Big M Method
d. Surplus variable
68. When the elements of net evaluation row of simplex table are equal, the situation is known as
a. Tie
b. Degeneracy
c. Break
d. Shadow price
69. The number at the intersection of key row and key column is known as
a. Column number
b. Row number
c. Key elements
d. Cross number
70. Which variables are fictitious and cannot have any physical meaning?
a. Optimal variable
b. Decision variable
c. Artificial variable
d. Surplus variable
71. An objective function which states the determinants of the quantity to be either maximized or
minimized is called_______
a. Feasible function
b. Optimal function
c. Criterion function
d. Objective function
72. To transfer the key row in simplex table we have to
a. Add the elements of key row to key number
b. Subtract the elements of key row from topmost no key row
c. Divide the elements of key row by key number
d. Multiply the elements of key row by key number
73. A set of values X1,X2……..Xn which satisfies the constraints of the LPP is
called_______
a. Solution
b. Variable
c. Linearity
d. Decision
74. A basic solution which also satisfies the condition in which all basic variables are non-negative is
called ___
a. Basic feasible solution
b. Feasible solution
c. Optimal solution
d. Unbounded solution
75. The cost coefficient of slack variable is
a .Zero
b. One
c. > than one
d. < than one,
76. An objective function is maximized when it is a _______ function
a. Passive
b. Profit
c. Cost
d. Non-profit
77. To convert ≤ type of inequality into equations, we have to
a. Assume them to be equations
b. Add surplus variables
c. Subtract slack variables
d. Add slack variables
78. Currently, LPP is used in solving a wide rangrae of practical ___________
a. Business problems
b. Agricultural problems
c. Manufacturing problems
d. Processing problem
79. _____ refers to the combination of one or more inputs to produce a particular
output
a. Solution
b. Variable
c. Process
d. Decision
80. An optimum solution is considered the _____ among feasible solutions
a. Worst
b. Best
c. Ineffective
d. Desirable
81. The key row indicates
a. Incoming variable
b. Outgoing variable
c. Slack variable
d. Surplus variable
82. ________ which is a subclass of a linear programming problem (LPP)
a. Programming problem
b. Transportation problem
c. Computer problem
d. Technical problem
83. The key column indicates
a. Outgoing variable
b. Incoming variable
c. Independent variable
d. Dependent variable
84. In simplex method, we add _______ variables in the case of “=”
a. Slack variable
b. Surplus variable
c. Artificial variable
d. Optimal variable
85. In simplex method, if there is tie between a decision variable and a slack (or surplus) variable, ______
should be selected
a. Slack variable
b. Surplus variable
c. Decision variable
d. Artificial variable
86. A BFS of a LPP is said to be ______ if at least one of the basic variable is zero
a. Degenerate
b. Non-degenerate
c. Infeasible
d. unbounded
87. Every LPP is associated with another LPP is called_____
a. Primal
b. Dual
c. Non-linear programming
d. Alternative
88. Dual of the dual is _______
a. Primal
b. Dual
c. Alternative
d. Non-linear programming
Module 2: Assignment and Transportation Models
Unit 1 : Assignment Problem: Hungarian Method (MCQ = 26)
89. If the number of jobs is equal to the number of resources, then the problem is term as _____
assignment problem
a. Balanced
b. Unbalanced
c. Equal
d. Unequal
90. If the number of jobs is not equal to the number of resources, then the problem is term as _____
assignment problem
a. Balanced
b. Unbalanced
c. Equal
d. Unequal
91. Hungarian Method is used to solve
a. A transportation problem
b. A travelling salesman problem
c. A LP problem
d. A transportation problem and A LP problem
115. To find initial feasible solution of a transportation problem the method which starts allocation from
the lowest cost is called ________
a. North west corner method
b. Least cost method
c. South east corner method
d. Vogel’s approximation method
116. In a transportation problem, the method of penalties is called
a. North west corner method
b. Least cost method
c. South east corner method
d. Vogel’s approximation method
117. Which of the following considers difference between two least costs for each row and column while
finding initial basic feasible solution
a. North west corner method
b. Least cost method
c. South east corner method
d. Vogel’s approximation method
118. When the total of allocations of a transportation problem match with supply and demand values, the
solution is called _________ solution
a. Non-degenerate
b. Degenerate
c. Feasible
d. Infeasible
119. When the allocations of a transportation problem satisfy the rim condition (m+n-1) the solution is
called as ___ solution
a. Degenerate
b. Infeasible
c. Unbounded
d. Non-degenerate
120. When there is a degeneracy in the transportation problem, we add an imaginary allocation called
______ in the solution
a. Dummy
b. Penalty
c. Epsilon
d. Regret
121. If m+n-1 = number of allocations in transportation, it means ______
a. There is no degeneracy
b. Problem is unbalanced
c. Problem is degenerate
d. Solution is optimal
122. There are ______ types of techniques available to find the Initial basic feasible solution
a. Two
b. Three
c. Four
d. One
123. When demand is not equal to supply, we need to add _____
a. Variable
b. Resources
c. Dummy
d. Events
124. When demand is equal to supply it is ____ problems
a. Maximization
b. Minimization
c. Unbalance
d. Balance
125. When demand is not equal to supply it is ______ problems
a. Maximization
b. Minimization
c. Unbalance
d. Balance
126. A dummy variable is simply a _______ variable
a. Slack
b. Indicator
c. Compress
d. Fictional
127. If the number of occupied cells is equal to m+n-1 i.e. number of independent constraint equations,
then it is
a. Basic feasible solution
b. Degenerate
c. Non-degenerate
d. Initial Basic feasible solution
128. If the number of occupied cells is less than m+n-1 then the solution is known as ______ solution
a. Basic feasible solution
b. Degenerate
c. Non-degenerate
d. Initial Basic feasible solution
129. MODI stands for
a. Modern distribution,
b. Mendel's distribution method
c. Modified distribution method
d. Model index method
130. The dummy source or destination in a transportation problem is added to
a. Satisfy rim conditions
b. Prevent solution from becoming degenerate
c. Ensure that total cost does not exceed a limit
d. None of the above
131. The occurrence of degeneracy while solving a transportation problem means that
a. Total supply equals total demand
b. The solution so obtained is not feasible
c. The few allocations become negative
d. All are negative
132. To convert the transportation problem into a maximization model we have to
a. write the inverse of the matrix,
b. Multiply the rim requirements by –1,
c. To multiply the matrix by –1,
d. We cannot convert the transportation problem into a maximization problem, as it is
basically a minimization problem.
133. One disadvantage of using North-West Corner rule to find initial solution to the transportation
problem is that
a. It is complicated to use
b. It does not take into account cost of transportation
c. It leads to a degenerate initial solution
d. it cannot find proper initial basic feasible solutions
134. The solution to a transportation problem with ‘m’ rows(supplies) & ‘n’ columns(destination) is
feasible if number of positive allocations are
a. M+n
b. M*n
c. M+n-1
d. M+n+1
135. If an opportunity cost value is used for an unused cell to test optimality, it should be
a. Equal to zero
b. Most negative number
c. Most positive number
d. Any value
136. During an iteration while moving from one solution to the next, degeneracy may occurs
when
a. The closed path indicates a diagonal move
b. Two or more occupied cells are on the closed path but neither of them represents a corner of
the path
c. Two or more occupied cells on the closed path with minus sign are tied for lowest circled
value
d. The closed path indicates a cross move
137. The large negative opportunity cost value in an unused cell in a transportation table is chosen to
improve the current solution because
a. It represents per unit cost reduction
b. It represents per unit cost improvement
c. It ensures no rim requirement violation
d. It ensures rim requirement violation
138. If ui and vj are row and column numbers respectively, then the implied cost is given by:
a. ui + vj
b. ui – vj
c. ui × vj
d. ui / vj Program Evaluation and Review Technique
139. When total supply is equal to total demand in a transportation problem, the problem is said to
be
a. Balanced
b. Unbalanced
c. Degenerate
d. None of the above
140. Which of the following methods is used to verify the optimality of the current solution of the
transportation problem
a. Least cost method
b. Vogel’s approximation method
c. Modified distribution method
d. Hungarian method
141. If total supply is equal to total demand and the matrix elements are time elements then the
problem is
a. Balanced and Minimization Transportation problem
b. Unbalanced and Minimization Transportation problem
c. Balanced and Minimization Assignment problem
d. Unbalanced and Minimization Assignment problem
142. The solution of any transportation problem is obtained in how many stages?
a. Five
b. Four
c. Three
d. Two
143. An optimal solution is the ______ stage of a solution obtained by improving the initial
solution a. Third
b. First
c. Second
d. Final
144. MODI method is used to obtain____
a. Optimal solutions
b. Optimality test
c. Optimization
d. Optimal solutions and Optimality test
145. Any feasible solution to a transportation problem containing m origins and n destinations is said to
be
a. Independent
b. Degenerate
c. Non-degenerate
d. Feasible
146. A path formed by allowing horizontal and vertical lines and the entire corner cells of which are
occupied is called as _______
a. Occupied path
b. Open path
c. Closed path
d. Semi-closed path
147. Transportation algorithm can be used for minimizing the transportation cost of _____ from O origins
and D destinations
a. Goods
b. Products
c. Items
d. Resources
148. If demand is lesser than supply then dummy demand node is added to make it a
____
a. Simple problem
b. Balanced problem
c. Transportation problem
d. Unbalanced Problem
Module 3: Network Analysis
CPM, Project Crashing, PERT (MCQ = 55)
149. What network model enables engineer managers to schedule, monitor and control large and
complex projects by using only one time factor per activity
a. Forecasting
b. Program evaluation review technique
c. Critical path method
d. Simulation
150. What network model enables engineer managers to schedule, monitor and control large and
complex projects by employing three time estimates per activity
a. Forecasting
b. Program evaluation review technique
c. Critical path method
d. Simulation
151. For a project manager to have an effective means of identifying and communicating the planned
activities and their interrelationships, he must use a network technique. One of the network techniques
is commonly known as CPM, what does CPM stands for?
a. Critical plan method
b. Coordinated plan method
c. Critical project method
d. Critical path method
152. For a project manager to have an effective means of identifying and communicating the planned
activities and their interrelationships, he must use a network technique. One of the network techniques
is commonly known as PERT, what does PERT stands for?
a. Project evaluation review technique
b. Program evaluation review technique
c. Path evaluation review technique
d. Project execution review technique
153. What is the benefit of using PERT/CPM network as integral component of project management
a. They furnish a consistent framework for planning, scheduling, monitoring and controlling
project
b. They illustrate the interdependencies of all tasks
c. They can be used to estimate the expected project completion dates as well as the probability
that the project will be completed by a specific date
d. All of the above
154. The CPM was developed by Rand and Walker in which year?
a. 1957
b. 1958
c. 1959
d. 1960
155. In what year was PERT developed?
a. 1957
b. 1959
c. 1960
d. 1958
156. PERT stands for
a. Program Evaluation and Review Technique
b. Project Evaluation and Review Technique
c. Program Execution and Review Technique
d. Path Evaluation and Review Technique
157. At the completion of the forward and backward passes, the slack for an activity is given by
the
a. Difference between early start and early finish
b. Difference between early start and latest finish
c. Difference between latest start and early finish
d. Difference between latest start and latest finish
158. The basic difference between PERT and CPM is that
a. PERT deals with events and CPM with activities
b. Critical Path is determined in PERT only
c. Costs are considered on CPM only
d. Guessed times are used in PERT and evaluated times in CPM.
159. In a PERT network, the earliest (activity) start time is the
a. Earliest time that an activity can be finished without delaying the entire project
b. Latest time that an activity can be started without delaying the entire project
c. Earliest time that an activity can be started without violation of precedence
requirements
d. Latest time that an activity can be finished without delaying the entire project
160. The time by which activity completion time can be delayed without affecting the start of
succeeding activities, is known as
a. Interfering float
b. Total float
c. Duration
d. Free float
161. Completion of an activity on CPM network diagram, is generally known
a. Event
b. Node
c. Connector
d. Event, Event and Connector
162. The performance of a specific task in CPM is known
a. Dummy
b. Event
c. Activity
d. Contract.
163. Forward pass calculations are done to find _____ occurrence times of
events
a. Exact
b. Earliest
c. Latest
d. Approximate
164. Backward pass calculations are done to find ________ occurrence times of
events
a. Tentative
b. Definite
c. Latest
d. Earliest
165. An activity whose start or end cannot be delay without affecting total project completion time is
called ______ activity
a. Dummy
b. Non-critical
c. Critical
d. Important
166. Floats for critical activities will be always _____
a. One
b. Zero
c. Highest
d. Same as duration of the activity
167. The artificial activity which indicates that an activity following it, cannot be started unless the
preceding activity is complete, is known as
a. Free float
b. Event
c. Dummy
d. Constant
168. An important assumption in PERT calculations is
a. Activity times are normally distributed
b. Activity times are independent
c. Activity times are net calculation
d. Activity times are dependent
169. In PERT, slack time equals
a. EST + t
b. LST-EST
c. Zero
d. EFT-EST
170. A dummy activity is required when
a. Two or more activities have the same starting events
b. Two or more activities have different ending events
c. Two or more activities have the same ending events
d. The network contains Two or more activities have the identical starting and ending
events
171. PERT analysis computes the variance of the total project completion time as
a. The sum of the variances of all activities in the project
b. The sum of the variances of all activities not on the critical path of the project
c. The variance of the final activity of the project
d. The sum of the variances of all activities on the critical path
172. _________ an activity that must be completed prior to the start of another
activity
a. Sequential activity
b. Preceding activity
c. Succeeding activity
d. Concurrent activity
173. Two or more activities are _________ in nature if the end of one activity is the start of
another
a. Sequential activity
b. Preceding activity
c. Succeeding activity
d. Concurrent activity
174. _______ is an activity that cannot be started till one or more preceding activities are
complete
a. Sequential activity
b. Preceding activity
c. Succeeding activity
d. Concurrent activity
175. Activities that can be performed simultaneously are called ____
a. Sequential activity
b. Preceding activity
c. Succeeding activity
d. Concurrent activity
176. If an activity has zero activity slack it
a. Means that the project is expected to be delayed
b. Must be a dummy activity
c. Is on the critical path
d. Must be artificial activity
177. Pick the wrong relationship
a. Interfering float = total float – free float
b. Total float = free float + independent float
c. Total float > free float > independent float
d. Free float = total float – head event slack
178. Chose the correct condition of the following
a. Crash Direct Cost > Normal Direct Cost, Crash time > Normal time
b. Crash Direct Cost < Normal Direct Cost, Crash time > Normal time
c. Crash Direct Cost < Normal Direct Cost, Crash time < Normal time
d. Crash Direct Cost > Normal Direct Cost, Crash time < Normal time
179. The project cost in general involves _________ types of costs
a. Three
b. One
c. Two
d. Four
180. The rate at which the cost increases is called as the _______
a. Crash slope
b. Crash time
c. Crash cost
d. Total crash
181. It is assumed that less is the project duration more is the _______ associated
with
a. Profit
b. Cost
c. Sales
d. Revenue
182. The total completion time is referred as the
a. Crash slope
b. Crash time
c. Crashing cost
d. Total crash
183. The two types of costs involved in project crashing are
a. Direct and indirect
b. Total and partial
c. Visible and invisible
d. Measurable and non-measurable
184. In project crashing, rent and overheads are treated as
a. Significant
b. Insignificant
c. Direct
d. Indirect
185. In project crashing, the costs associated with actual activities (e.g. material, machinery,etc) are called
___ costs
a. Visible
b. Measurable
c. Direct
d. Indirect
186. In project crashing, as we systematically, crash the project, direct cost of project
______
a. Increases
b. Decreases
c. Remain same
d. None of the above
187. In project crashing, as we systematically, crash the project, indirect cost of
project________
a. Increases
b. Decreases
c. Remain same
d. None of the above
188. In project crashing, as we systematically, crash the project, total project cost before reaching optimal
point
a. Increases
b. Decreases
c. Remain same
d. None of the above
189. In project crashing, as we systematically, crash the project, total project cost after reaching optimal
point
a. Increases
b. Decreases
c. Remain same
d. None of the above
190. When the normal period is reduced to some extent to the period called
_______
a. Crash slope
b. Crash time
c. Crash cost
d. Total crash
191. Indirect cost ______ when the project is crashed
a. Increases
b. Decreases
c. Becomes zero
d. Becomes one
192. The longest of all paths through the network is the ______
a. Crucial path
b. Time taking path
c. Dummy path
d. Critical path
193. Activity to be crashed is selected based on
a. Critical activity with minimum crash cost
b. Non- Critical activity with minimum crash cost
c. Critical activity with maximum crash cost
d. Non-Critical activity with maximum crash cost
194. In PERT, the time estimate calculated by using formula (a+4m+b)/6 is called _____
time
a. Optimistic
b. Pessimistic
c. Most likely
d. Expected
195. In PERT, the expected project completion time is also called as ______ project completion
time
a. Average
b. Normal
c. Mean
d. Critical
196. The maximum time in which an activity will be completed assuming all possible delays and
postponements is termed as
a. Optimistic time
b. Most likely time
c. Pessimistic time
d. Expected time
197. The probability of normal curve is ______
a. 60%
b. 50%
c. 45%
d. 55%
198. Optimistic time is the ________ possible time required for the completion of the
activity
a. Longest
b. Shortest
c. Unequal
d. Normal
199. Pessimistic time is the ___________ time period expected to complete the
activity
a. Longest
b. Shortest
c. Unequal
d. Normal
200. _________ is the time estimate within which the activity is completed more
often
a. Optimal time
b. Optimistic time
c. Pessimistic time
d. Most likely time
201. When we combine the value of optimistic time, most likely time and pessimistic time in a statistical
manner, we can arrive at the _________ time of an activity
a. Optimal
b. Expected
c. Normal
d. Equal
202. The ________ analysis completion time of the activity is a random variable characterized by some
probability distribution
a. CPM
b. Graphical
c. LPP
d. PERT
203. Which of the following is not a concept associated with CPM
a. Normal time
b. Probability
c. Normal cost
d. Crash cost
Module 4: Job Sequencing and Theory of Games
Unit1 : Job Sequencing Problem (MCQ = 24)
204. S.M. Johnson’s algorithm derives the minimum completion times for all “no passing” cases. “no
passing” means
a. The order of processing jobs through the first facility must preserved at the last facility
b. The order of processing jobs through the first facility must preserved for next facility
c. The order of processing jobs through the first facility must preserved for all subsequent
facility
d. The order of processing jobs through the first facility must preserved only first facility
205. An approach that minimizes the total time for sequencing a group of jobs through two week centres
while minimizing total idle time in the work Centre
a. Gross materials requirement plan
b. Load report
c. Lot-for-lot
d. Johnson’s rule
206. When a set of jobs must pass through two workstations whose sequence is fixed, _______ is the rule
most commonly applied
a. Johnson’s rule
b. Earliest due date rule
c. First come, first serve rule
d. Slack time remaining
207. __________ is the process of determining which job to start first and in what order other jobs should
be processed on the machine or in work Centre
a. Job sequencing
b. Priority rules
c. Batch production
d. None of these
208. The technological order of machine to be operated is fixed in a problem having
a.1 machine and ‘n’ jobs
b.2 machines and ‘n’ jobs
c. 3 machine and ‘n’ jobs
d.‘n’ machines and 2 jobs
209. In sequencing if smallest time for a job belongs to machine-1 then the job has to placed
a. In the middle
b. In the starting
c. At end
d. At bottom
210. In sequencing the time involved in moving jobs from one machine to another
is
a. Negligible
b. Positive number
c. Significant
d. None of them
211. ____ operation is carried out on a machine at a time
a. Two
b. At least one
c. Only one
d. None of them
212. Processing time Mij’s are _______ of order of processing the jobs
a. Dependent
b. Negligible
c. Independent
d. None of them
213. If there are n jobs to be performed, one at a time, on each of m machines, the possible sequences
would be
a. (n!)m
b. (n)m
c. (m!)n
d. (m)n
214. In a 2 job and ‘n’ machine sequencing problem we find that
a. Sum of processing time of both the jobs is same,
b. Sum of idle time of both the jobs is same,
c. Sum of processing time and idle time of both the jobs is same
d. Sum of processing time and idle time of both the jobs is different
215. The fundamental assumption of Johnson‘s method of sequencing is
a. No Passing rule
b. Passing rule
c. Same type of machines are to be used
d. Non zero process time
216. ____________ to be used are of different types
a. Variable
b. Resources
c. Machine
d. Articles
217. Each _______ started on a machine is to be performed up to the completion on that
machine
a. Time
b. Job
c. Sequence
d. Slot
218. The time taken by the jobs in moving from one machine to another is very negligible and is taken as
equal to
a. One
b. Three
c. Two
d. Zero
219. ______ on machine refers to the time a machine remain idle during the total elapsed
time
a. Optimal time
b. Minimum time
c. Idle time
d. Maximum time
220. _______ time is the time interval between starting the first job and completing the last job
a. Total elapsed
b. Total slack
c. Total time
d. Total cost
221. The time required by each job on each machine is called _____
a. Elapsed
b. Idle
c. Processing
d. Average
222. The order in which machines are required for completing jobs is called _____
a. Machines order
b. Working order
c. Processing order
d. Job order
223. The time between the starting of the first job and completion of the last job in sequencing problems is
called
a. Total time
b. Assignment time
c. Elapsed time
d. Idle time
224. The time during which a machine remains waiting or vacant in sequencing problem is called _____
time
a. Processing
b. Waiting
c. Idle
d. Free
225. In sequencing problem, the order of completion of jobs is called ______
a. Completion sequence
b. Job sequence
c. Processing order
d. Job order
226. The total time required to complete all the jobs in a job sequencing problems is known as
_____
a. Idle time
b. Processing time
c. Elapsed time
d. Processing order
227. In sequencing if smallest time for a job belongs to machine-2 then the job has to
placed
a. In the middle
b. In the starting
c. At end
d. At the bottom
Module 4: Job Sequencing and Theory of Games
Unit2 : Theory of Games (MCQ = 23)