Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

The Window Delay Analysis Technique: The Clear

Solution of the Coming Millennium


Anamaria I. Kohler, M.S., E.I.T, Carter & Burgess
Dr. John D. Borcherding, The University of Texas at Austin

Introduction analysis utilizes a scenario with a CPM program, which is ful-


ly implemented and updated frequently. This brings the
Delays in construction schedules are nothing new. Even when greatest benefit to both the owner and contractor and mini-
the Egyptians built the Great Pyramid of Gizeh around 2500 mizes controversy during dispute resolution.
BC, delays often surfaced, and finger-pointing became a pop- Using CPM-based networks, the window analysis breaks
ular pastime of all parties involved in the ancient project. Un- up the project into smaller time periods defined by major
fortunately for the Egyptian workers, the blame seemed to schedule revisions. These smaller time periods are referred to
consistently land on their shoulders regardless of the true as “windows.” Each succeeding window becomes the con-
cause of the delay. I assume that the Nile crocodiles were par- temporaneous “baseline” schedule, and previous windows
ticularly well fed during that century! are ignored. Each window is “framed” between two revisions
As the construction industry enters the twenty first centu- (Galloway 1990). Example: Window number one is framed
ry, are we less naive than the Egyptians? Both owners and between the initial as-planned schedule (baseline) and the
contractors have viewed delay analysis techniques as after- first schedule revision. There are two schedules for each win-
the-fact weapons to expediently slaughter one another in dow—an as-planned and an actual. The actual project com-
courtroom battles. This inefficient application of delay analy- pletion date is the end of the final window.
sis techniques must be tempered in order to propel the con- In other words, the window technique “relies on the sim-
struction industry into a new century where legal dramas are ulation of progressive updates of the as-planned schedule to
simply relics of a claims-conscious past. yield incremental extensions on the contract’s milestones as
The first section of this paper is a review of the most com- a result of each delay” (Fredlund 1990). The window tech-
mon delay analysis techniques applied in the construction in- nique is useful in proving that controlling critical paths
dustry. The successive sections deal with the results of a sur- change, pinpointing when these changes occur, and indicat-
vey designed to discover the most effective delay analysis ing what would have happened had the contractor been able
technique. The survey was given to a Delphi panel of twenty to adhere to his as-planned schedule (Fredlund 1990).
experts whose forte lies in the schedule analysis arena. Both Impacted As-Planned Technique
the strengths and the shortcomings of the “ideal” analysis
technique are brought into focus. Zafar (1996) believes “this is one of the simplest ways of do-
ing a delay analysis where the baseline schedule is affected for
different delays, one after another.” This technique also uses
Delay Analysis Techniques a CPM network to demonstrate delay impacts; however, the
original approved as-planned schedule is the only baseline uti-
Schumacher (1995) stated the following about the evolution lized to evaluate individual delays as they occur. This method
of delay techniques: does not update the schedule using actual as-built informa-
“At least three techniques have evolved over the last 30 tion, and there is no comparison of the “impacted” schedule
years. They are generically known as “what-if ” evaluations with the actual as-built information (Trauner 1990). Unlike
(otherwise known as impacted as-planned analysis), “but-for” the impacted as-planned technique, the window technique
evaluation, and Contemporaneous Period Analysis (window does update the as-planned schedule and uses the new im-
analysis). Primarily, they differ in the baseline that is used to pacted as-planned for comparison with the actual schedule.
measure the delays.” Callahan (1992) believes, “Under the as-planned method,
the contractor is entitled to a time extension only if the
Window Analysis Technique scheduled completion is delayed beyond the extended con-
The window analysis technique (WAT) is the most advanta- tract completion date. The as-planned method employs the
geous of all the as-planned approaches, according to C.Popes- planned schedule to measure the delay, regardless of whether
cu (1991). The most effective as-planned based delay impact the actual construction in the field differs from the planned.”

116

PROJECT MANAGEMENT INSTITUTE 28th Annual Seminars & Symposium


Chicago, Illinois: Papers Presented September 29 to October 1, 1997
In this statement lies the inherent problem with the impact-
ed as-planned technique. Exhibit 1. Characteristics of Delay Analysis
But-For Technique
Techniques
Attributes W I B
The but-for technique is considered to be “less of a CPM Based on Critical Path Method X X X
technique than a legal standard for evaluating delay claims”
Need Skilled Schedule Analyst X X X
(Barba 1994). This technique is commonly used in court to
prove specific delay claims due to its visual nature. A con- Based on Dynamic As-Planned Schedule X
tractor may use this technique to claim entitlement for com- Distinguishes between Delay Types X X X
pensation from a date earlier than the required contract com- Accounts for Critical Path Shifts X
pletion date. Barba states: Recognizes Concurrencey of Delays X X
“In determining the merit of such a claim the ‘but for’ ap- Degree of Data Intensity H M H
proach compares the actual date of project completion with Forward or Backward Based Analysis F F B
the point in time at which the work would have been com-
pleted but for delays caused by other factors or parties.”
The but-for technique essentially “pulls out all owner de- • Must be willing to be included in an iterative process that
lays that affected the as-built critical path. The amount of could last one year
compensable delay is the difference in time between the ac- • Must be comfortable sharing ideas with academia.
tual completion date shown on the as-built schedule and the The initial screening based on these criteria was conduct-
completion date shown on the but-for schedule” (Schumach- ed via telephone interviews. Twenty members were finally se-
er 1995). lected to become part of the Delphi panel. Sixty percent of
the panel participants had roles of project management con-
Summary of Techniques
sultants. Twenty percent were scheduling specialists, and the
It becomes clearly evident by examining Exhibit 1 that the other 20 percent were attorneys specializing in construction
window analysis technique is the most comprehensive of the claims.
three analysis techniques described in the preceding para-
graphs. WAT is the only technique out of the three that ac-
knowledges the dynamics of the schedule. The critical path is Survey Results
not static. In fact, it may go through dynamic fluctuations
upon every update. The windows technique captures these Exhibit 2 depicts the original thirteen questions asked in the
fluctuations. survey.
However, along with this advantage, the window tech-
Review of Responses
nique does have some drawbacks. It requires an extensive
amount of data input to maintain accurate results, and a Thirteen out of the twenty respondents indicated that the
skilled scheduler is essential to interpret and analyze the up- window technique is the delay analysis tool they apply in
dated reports. practice. In fact, eleven out of these thirteen people have ap-
plied the windows technique for at least five years, and eight
people have used it for over ten years.
Survey Methodology Eleven out of the thirteen respondents also answered affir-
matively to question 6, “Have you used this technique for allo-
The main intention of the survey was to determine the most cating delays among the GC and subcontractor?” This over-
frequently applied delay analysis technique in the construc- whelming response indicates that the windows technique
tion industry. Data collection was based on the Delphi contains a greater amount of flexibility than the other delay
method. The Delphi method requires the researcher to iden- analysis techniques, allowing you to pinpoint delays down to
tify a panel of experts with which to conduct his survey and the subcontractor level. This is extremely important on projects
have an iterative exchange of ideas over a substantial period where the general contractor plays the role of a broker, allow-
of time. ing the subcontractors to perform all of the project activities.
The selection criteria for the panel of experts was based on The way delays are represented in the analysis is ex-
the following: tremely important. All thirteen survey participants that im-
• Must have ten years or more delay analysis experience plement the window analysis technique stated that delays are
• Must have applied in practice at least one of the tech- represented as separate activities. The impacted activity is
niques on a regular basis broken into two separate activities and the delay activity is

117

PROJECT MANAGEMENT INSTITUTE 28th Annual Seminars & Symposium


Chicago, Illinois: Papers Presented September 29 to October 1, 1997
Exhibit 2. Summary of Questions

1. What techniques are you familiar with? 9. What do you believe to be the greatest strengths of
this technique?
2. Check the techniques that you have used or are 10. What do you believe to be the major limitations of
this technique?
using as a delay analysis tool.
11. What do you believe to be the perceived
3. Which one technique do you apply in practice? shortcomings of the remainder of the techniques?

4. How long have you been using this technique? 12. How do you represent delays?

5. Have you ever used this technique for allocating 13. How do you distinguish between owner-caused and
delays among the GC and the owner? contractor caused delays?
6. Have you ever used this technique for allocating
delays among the GC and subcontractor?
7. Why did you chose to apply this technique over the
others listed above?
8. Have you in any way modified this technique to suit
your needs? If yes, please describe these mods.

Exhibit 3. Top 10 Strengths of the Window Analysis Technique

1. Great visual impact.


2. Court Friendly: most effective on juries
3. Most credible delay analysis technique and the most persuasive.
4. Considers revisions in logic and critical path: dynamic.
5. Looks at delays contemporaneously giving the most accurate picture.
6. Analyzes delays caused by all project participants.
7. Easier to assign delay responsibility by viewing specific windows.
8. Gives contractors a “fresh start” by updating the baseline: eliminates focus on impacts of
past changes.
9. The project is divided into manageable parts for analysis.
10. Recognizes concurrency of delays.

inserted in-between. By using this method, the delay can be Concluding Remarks
coded so that a report can be easily generated. This report in-
dicates all delays, which activities they affect, and for what A progressive owner who recognizes the benefits of spending
duration. money initially on the preplanning stage of a project, instead
Top Ten Lists of after the fact on lawyers fees, will also embrace the appli-
cation of the windows analysis technique over all other delay
The top ten strengths of the window analysis technique, as analysis methods. An owner that exhibits these traits will be
indicated by the survey participants, are listed in Exhibit 3. ready for the future of project management.
The window analysis technique has a very persuasive list
of positive attributes that make it the logical choice for a References
schedule analysis tool. However, the windows technique does
Barba, Evans M., and Thomas C. Caruso. 1994. Approaches
have some limitations that should be a caveat to every pro- to Schedule Delay Analysis. Session 1012 Ninth Annual
fessional schedule analyst. Construction Superconference, Barba-Arkhon Interna-
tional Inc.

118

PROJECT MANAGEMENT INSTITUTE 28th Annual Seminars & Symposium


Chicago, Illinois: Papers Presented September 29 to October 1, 1997
Exhibit 4. Top 10 Limitations of the Window Analysis Technique

1. Need accurate and detailed contemporaneous documents to obtain accurate updates.


2. Excessive expenditures are incurred to analyze the windows when faced with inadequate
support data.
3. Schedules are not updated consistently and accurately to implement technique.
4. Not as accepted by seasoned construction lawyers.
5. The maximum number of Windows must be limited to 5 but no less than 2 for optimum
effectiveness.
6. The outcome can be manipulated by the selection of the Window cut-off dates.
7. A small delay could become a non-issue in later windows; therefore, a time extension
granted now could turnout to be a “gift” later.
8. The as-planned schedule must be well thought out and detailed in order to be an accurate
baseline for the first window.
9. The analysis must be done contemporaneously to be fully effective.
10. If the contract is not required to follow the guidelines, the technique is almost impossible to
apply.

Callahan, Michael T., Daniel G. Quackenbush, and James E.


Rowings. 1992. Construction Project Scheduling. Mc-
Graw Hill, New York.
Fredlund, Donald J., and Gui Ponce de Leon. 1990. “Delay
Evaluation Using Record Schedules.” 1990 AACE Trans-
actions. R.2.1-R.2.7.
Galloway, Patricia D., and Kris R. Nielsen. 1990. 1990 PMI
Seminar/Symposium. Calgary, Alberta: 412–418.
Popescu, Calin. 1991. “Selecting As-Planned Base in Project
Disputes.” 1991 AACE Transactions. C.2.1-C.2.4.
Schumacher,Lee. 1995. “Quantifying and Apportioning De-
lay on Construction Projects.” Cost Engineering (Febru-
ary): 11–13.
Trauner, Theodore J. 1990. Construction Delays. R.S Means
Company Inc., Kingston, MA.
Zafar, Zartab Q. 1996. “Construction Project Delay Analy-
sis.” Cost Engineering (March): 23–27.

119

PROJECT MANAGEMENT INSTITUTE 28th Annual Seminars & Symposium


Chicago, Illinois: Papers Presented September 29 to October 1, 1997

You might also like