Professional Documents
Culture Documents
Project Cost Estimation
Project Cost Estimation
Project Cost Estimation
(1) Direct Construction Cost (Direct Cost, Base Cost for Construction)
National standards for estimating costs do not exist in Fiji, so direct construction costs were calculated
based on work item in Chapter 18.7 Construction Figures and on the unit prices in Chapter 19.2. The
unit price for each type of construction was set based on bidding prices pf past projects implemented
by the Ministry of Infrastructure and Transportation (MoIT1) and Fiji Road Authority2, reference
documents (Australian Construction Handbook 20153, Study on The Transportation and Hydropower
Projects for The Mining Development in Waisoi Area, The Republic of Fiji4), and on market price of
recent constructions within Fiji and Public works multiplication standard unit price in Japan5.
According to interviews with the Ministry of Agriculture and local construction workers, most of
required materials, equipment and workforce can be produced from within Fiji.
(6) Contingency
Five percent of the project was added as a contingency allowance to the costs both in foreign and domestic
currencies.
construction completion and defect correction, and thus covers the defect liability period.
(Standard Bidding Documents under Japanese ODA Loans, Procurement of Works, JICA,
October 2012)
Table 19-1 Ratio of foreign currency (FC) and local currency (LC) of unit prices
Table 19-2 Unit Prices for river work project cost estimation
Refer to Direct construction cost 10)
Sorce of cost Fiji Japan
Item Direct construction cost
Interviewed MOIT1) Interviewed FRA 2) Reference Reference Reference
Reference documents 6)
(2014) (2014) documents 3) documents 4) documents 5)
item
Region Application Cost 11) Setting basis and Ratio 9) Fiji Fiji Fiji Fiji Fiji Tokyo
Remarks
Unit Currency FJD Reference documents FC LC FJD FJD YEN YEN YEN YEN
Excavation m3 6.61 Interviewed MOIT1) 60% 40% 11.86 12.21 736 5,305 245 270.0
Back fill7) m3 5.24 Interviewed MOIT1) 60% 40% 4.36 - 5,407 5,246 289 454.9
Banking from Excavated Materials m3 13.81 Interviewed FRA 2), include material cost 60% 40% 11.51 - - - -
Banking from Borrow Materials m3 48.13 Interviewed FRA 2), include material cost 60% 40% 40.11 4,948 4,346 - -
Earth work Banking m3 5.15 Reference documents5) 60% 40% - - - 234 281.4 Leveling and Compaction
Trimming of slope (Cuting) m2 7.07 Reference documents 3) 60% 40% - 322 2,268 376 815.9
Trimming of slope (Banking) m2 4.21 Reference documents 4) 60% 40% - 322 - 191 673.3
Stripping topsoil m2 1.08 Interviewed FRA 2) 60% 40% 0.9 1,701 1,701 - 120.9 Leveling of ground
Tree trimming m2 6.08 Interviewed FRA 2) 40% 60% 20.28/a tree - - - 277.0 Tree trimming and Transfer
(2m ×2m:FJD5.07/m2)
Concrete 25MPa m3 479.76 Interviewed MOIT1) 80% 20% 399.79 1293.7 21,173 36,540 16,051 19350
Concrete work Form work m2 114.32 Interviewed MOIT1) 20% 80% 95.27 include avobe 4,633 9,227 1,463 7789
Rebar for the reinforcement of concrete ton 4,016.81 Interviewed MOIT1) 80% 20% 3347.34 6652.08 163,500 556,970 139,725 150,000 Labor cost and Material cost
Work Gavion mattress m2 331.60 Interviewed MOIT1) 60% 40% 276.33 - - - - 12320
Item 6)
Geotextiles m2 15.41 Reference documents 80% 20% - - - - 693.1
Revetment work Concrete blocks for bank protection m2 220.18 Reference documents 6) 80% 20% - - - - 9529
Concrete pavement for revetment crest m3 479.76 Interviewed MOIT1) 80% 20% 398.76 - - - - 41530
Formed of cast-in-place concrete m3 479.76 Interviewed MOIT 1) 80% 20% 398.76 - - - - 53980
Prevent of Crown of levee m2 6.61 Reference documents 6) 20% 80% - - - - 286.0 Road upper subbase
Dike work
Sodding work m2 4.73 Interviewed FRA 2) 20% 80% 3.96 - - -
Coffering work (embankment made of earth) m3 5.06 Reference documents 6) 60% 40% - - - - 222.9 Leveling and Compaction
Temporary work
Temporary road work m2 3.30 Reference documents 6) 60% 40% - - - - 141.0 Unevenness correction
Removal of Dozing and Loading m3 6.61 Reference documents 6) 60% 40% - - - - 291.2 Dozing and Loading
Surplus Filling ,aterials transport (≦5.5km) m3 17.61 Reference documents5) 20% 80% - - - 725 876.6 ≦5.5km
Soil work Banking m3 5.15 Reference documents5) 60% 40% - - - 234 222.9 Leveling and Compaction
Steel bridge breaking work ton 330.28 Past implemented projects in Japan 20% 80% 122946.11/a Bridge - - - 15,000
removal work
Concrete breaking work m2 115.07 Interviewed FRA 2) 20% 80% 96.13 - - - 6903
1) Unit price used by Ministry of Infrastructure and Transportation (MoIT)
2) Interviewed Fiji Road Authority
3) Australian Construction Handbook 2015
4) Interveiwed Flecher Construction Company
5) Study on The Transportation and Hydropower Projects for The Mining Development in Waisoi Area, The Republic of Fiji
6) Public works multiplication standard unit price in Japan
7) Include purchasing soil by Australian Construction Handbook 2015
8) Include purchasing soil by Australian Construction Handbook 2015
9) Based on information interviewed MoIT, FRA, Rocal contructors
10) Shaded sells in the table is application cost
*) Exchange Rate(2016.4 JICA)
1 FJD= 54.5
1 YEN= 0.0183
11) According to information Interviewed FRA
Table 19-3 Unit Prices for bridge work project cost estimation (1)
Quantity FC & LC
Old Ratio (%)
No. item unit
Nadi Town Queens
Foreign Local
Bridge Road
Currency Currency
Bridge
0000 Earth work
0001 Excavation(soil) m3 15,457 14,646 60 40
0005 Backfill(clean sand) m3 4,718 4,649 60 40
0007 Banking m3 1,414 990 60 40
0009 Cutting (soil) m3 3,890 0 60 40
0010 Trimming of slope (Cutting) m2 148 211 60 40
0011 Trimming of slope (Banking) m2 318 193 60 40
0100 Foudation Work
0103 casing cast-in-place pile(φ1.0m) m 682 630 80 20
0200 Substructure Work
0201 cobble foundation of structure excavation(t=0.2m) m2 277 485 60 40
0202 levelling concrete(t=0.1m) m2 277 485 80 20
0210 abutment/pier base concrete m3 1,458 2,108 80 20
0220 form (for wall, pier) m2 1,380 1,738 80 20
0221 form (for levelling concrete) m2 15 21 20 80
0230 Rebar for the reinforcement of concrete ton 209 301 80 20
0300 Superstructure Work
0301 produce,transport & erection of main beam(PC I-Beam, L=32m)
unit 0 21 80 20
0302 produce,transport & erection of main beam(PC T-Beam, L=36m)
unit 21 0 80 20
0350 Steel Girder Bridge (Through Bridge)L=96m(3@32m) m2 0 691 80 20
0400 Floor Slab Work
0402 floor slab concrete c=400kg m3 555 298 80 20
0403 form (for slab) m2 704 969 20 80
0404 Rebar for the reinforcement of concrete ton 56 30 80 20
0405 supporting (for slab) m2 1,771 1,286 60 40
0500 Bridge Attachment Work
0501 bearing unit 42 50 80 20
0502 expansion joint m 26 34 80 20
0600 Bridge Surface Work
0604 Guard fence m 216 192 80 20
0605 Waterproofing m2 1,404 960 80 20
0606 Asphalt pavement for bridge 50thick m2 1,404 960 80 20
Table 19-4 Unit Prices for Bridge work project cost estimation (2)
Quantity FC & LC
Old Ratio (%)
No. item unit
Nadi Town Queens
Foreign Local
Bridge Road
Currency Currency
Bridge
0700 Removal of Existing Bridge Work
0701 concrete bridge breaking work m3 563 294 20 80
0702 concrete waste disposition m3 611 335 20 80
0703 steel bridge breaking work ton 92 146 20 80
0704 Removal of Existing Pile m 400 460 20 80
0800 Pavement Work
0801 road upper subbase m2 1,756 3,092 60 40
0803 Asphalt pavement for approach m2 1,756 1,200 60 40
0850 Tramline Orbit ton 0 17 80 20
0900 Temporary Work
0901 Temporary bridge with H beam m2 576 576 80 20
0902 Pile with H Beam(H=350) m 35 35 80 20
0904 Big sandbag unit 750 420 60 40
0905 temporary construction road m2 2,000 2,840 60 40
0906 Hume Pipe (φ1.0m) m 0 150 80 20
0907 Coffeing Works m3 8,515 3,720 60 40
1000 Concrete Work
1011 Concrete 18Mpa m3 632 447 80 20
1020 Form m2 1,275 951 20 80
1040 Crushed Stone (t=0.2m) m2 538 406 60 40
1100 Dike Works
1101 Pavement of Crown of levee m2 264 376 20 80
1102 Plant spraying m2 148 211 20 80
1200 Revetment Work
1203 Concrete blocks for bank protection m2 918 1,776 80 20
1300 Removal of Surplus Soil Works
1301 Dozing and Loading m3 4,700 5,287 100 0
1302 Filling materials transport (≦5.5km) m3 4,700 5,287 20 80
1303 Banking m3 4,700 5,287 100 0
2000 Other Work
2001 removal / relocation of utility pole unit 6 2 80 20
Compensation Works
Pavement pavement (t=0.4m) m² - 6,724.0 - - - 6,724.0
No. item unit Nadi Town Bridge Old Queens Road Bridge
Land Acquisition
Breakdown by Land Freehold Land ha 18.66 - - - -
ownership State Land ha 20.14 - - - -
Native Land ha 39.96 - - - -
Breakdown by LanduseAgricultural ha - 243.50 1.40 6.69 4.26
Commercial ha - - - 0.36 -
Residential ha - - - 0.21 -
Others ha - - - 0.04 -
Total ha 78.76 243.50 1.40 7.31 4.26
Total 40 1 76 1.4
TOTAL 486,011 3,257 663,531 12,175 612,329 3,748 816,581 14,983 1,480,111 27,158
Source: Department of Land, Fiji, for further details see Data Book
Component
① River Widening
② Retarding Basin A, B
③ Surrounding Dike
④ Ring Dike
⑤ Shortcut of tributaries
⑥ Rebuilding of Bridge (Nadi town bridge)
Malakua River
⑦ Rebuilding of Bridge (Old Queens Road bridge)
1
When the Master Plan will be completed, since the upstream dam will be constructed, the discharge of 1,800 m3/s can flow
down in the cross section considered free-board. In the Priority Project the discharge is permitted to flow down with water
section at the Back Road Bridge. The structural measures of the Priority Project are river improvements
(levee construction and river-bed excavation) necessary for the design flow, construction of two retarding
basins for storage of design flood discharge, construction of ring dike for protecting the downstream
community, construction of surrounding dike for protecting Nadi town, and shortcut in Malakua River for
reducing negative impact,. These components are included in the Master Plan as the Priority Project to be
implemented in advance. Two bridges exist in the river widening section, and they have to be rebuilt.
[Upper]: Flood Discharge before Flood Control ※Flow volume after the priority project include natural
Lower: Target Flood Discharge after the Priority Project flood volume at outside section of Important Protected Area
V=7,200 thousand m3
NaditownBridge BackroadBridge
B
Votualevu
-510
Nadi Town
A: 178 ha
Outline Profile L=13 km L=4.5 km L=1.8 km L=0.5 km L=108 m L=96 m
B: 35 ha
Total
Total M/M for Professional A 255
Total M/M for Professional B 447
Grand Total for Professional (A+B) 702
The project cost has been calculated under the following conditions:
a. Base for unit prices: Apr. 2016
b. Exchange rate: US$1 = ¥118.3, 1 US$1 =F$2.17, F$1=¥54.5
c. Combination of currency: Local currency portion , Foreign currency portion
d. Inflation rate: 1.8 % for Foreign currency portion, 4.8% for Local currency portion
e. Consultant labor cost:
Table 20-5 Annual Fund Requirements and Breakdown (M JPY (& Million F$))
in case of yen loan project
Breakdown of million (Yen) million (F$)
Cost Total JICA Portion Others Total JICA Portion Others
2016 252 0 252 4.6 0.0 4.6
2017 966 123 843 17.7 2.3 15.5
2018 1,266 381 885 23.2 7.0 16.2
2019 4,525 3,507 1,019 83.0 64.3 18.7
2020 3,901 3,389 513 71.6 62.2 9.4
2021 3,808 3,291 517 69.9 60.4 9.5
2022 3,035 2,601 434 55.7 47.7 8.0
2023 2,750 2,339 410 50.4 42.9 7.5
2024 467 336 132 8.6 6.2 2.4
Total 20,971 15,967 5,004 384.8 293.0 91.8
※ Year in above table shows the fiscal year of Fiji (August 1st to July 31th of following year)
Source: Calculation Result for Annual Fund Requirement based on the Cost Estimate Kit (JICA Study Team)
As shown in the table above, the project cost from the start of constructions in fiscal year 2019 to fiscal
year 2023 in Fiji is 2.8 ~ 4.5 billion yen. The following table shows the breakdown of the annual fund
requirements into the foreign currency portions (JICA portion) and the local currency portion.
Table 20-6 Breakdown of Annual Fund Requirements (2015-2025, FC: M JPY, LC: M FJD)
Item Total 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total FC LC Total
A. ELIGIBLE PORTION
Ⅰ) Procurement / Construction 6,778 134 14,074 0 0 0 0 0 0 0 0 0 0 0 0 1,601 30 3,244 1,536 29 3,097 1,450 28 2,985 1,079 23 2,310 973 21 2,127 139 3 311 0 0 0
Package 1 River Widening 4,213 77 8,432 0 0 0 0 0 0 0 0 0 0 0 0 1,024 19 2,049 784 14 1,568 784 14 1,568 784 14 1,568 733 13 1,467 105 2 211 0 0 0
Package 2 Retarding Basin 1,281 19 2,299 0 0 0 0 0 0 0 0 0 0 0 0 421 6 756 458 7 822 370 5 663 32 0 57 0 0 0 0 0 0 0 0 0
Package 3 Ring Dike 40 1 76 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 13 0 25 14 0 27 11 0 22 1 0 2 0 0 0 0 0 0
Package 4 Surrounding Dike 392 5 657 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 107 1 179 96 1 161 96 1 161 84 1 140 10 0 16 0 0 0
Base cost for JICA financing 5,926 102 11,464 0 0 0 0 0 0 0 0 0 0 0 0 1,445 25 2,805 1,362 23 2,594 1,263 21 2,419 923 16 1,809 818 15 1,609 115 2 227 0 0 0
Price escalation 529 26 1,940 0 0 0 0 0 0 0 0 0 0 0 0 79 4 285 101 5 355 118 6 423 104 5 392 109 6 416 18 1 69 0 0 0
Physical contingency 323 6 670 0 0 0 0 0 0 0 0 0 0 0 0 76 1 154 73 1 147 69 1 142 51 1 110 46 1 101 7 0 15 0 0 0
Ⅱ) Consulting services 933 18 1,893 0 0 0 0 0 0 69 1 123 214 3 381 136 2 262 133 3 292 136 3 307 137 3 290 100 2 213 8 0 25 0 0 0
Base cost 828 14 1,579 0 0 0 0 0 0 65 1 114 197 3 342 123 2 227 118 2 243 118 2 247 117 2 227 84 1 161 7 0 18 0 0 0
Price escalation 60 3 223 0 0 0 0 0 0 1 0 4 7 0 21 7 0 23 9 0 35 11 1 45 13 1 49 11 1 41 1 0 6 0 0 0
Physical contingency 44 1 90 0 0 0 0 0 0 3 0 6 10 0 18 6 0 12 6 0 14 6 0 15 7 0 14 5 0 10 0 0 1 0 0 0
Total (Ⅰ+Ⅱ) 7,711 151 15,967 0 0 0 0 0 0 69 1 123 214 3 381 1,737 32 3,507 1,669 32 3,389 1,586 31 3,291 1,216 25 2,601 1,073 23 2,339 148 3 336 0 0 0
B. NON ELIGIBLE PORTION
a Procurement / Construction 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
E. JICA finance portion (A) 7,711 151 15,967 0 0 0 0 0 0 69 1 123 214 3 381 1,737 32 3,507 1,669 32 3,389 1,586 31 3,291 1,216 25 2,601 1,073 23 2,339 148 3 336 0 0 0
※ Year in above table shows the fiscal year of Fiji (August 1st to July 31th of following year)
Source: Calculation Result for Annual Fund Requirement based on the Cost Estimate Kit (JICA Study Team)
Table 20-7 Time Periods Required for Major Processes and their Contents
No. Process Required Contents
time period
1 Yen loan procedures - Mar 2017 Pledge
2 Land acquisition 35 months After Pledge and before the start of construction
3 Selection of consultants 12 months Creation of RFP and short list and consent of JICA
Invitation and submission of proposal
Evaluation of the proposal and consent of JICA
Contract negotiation
Preparation and conclusion of contract
Consent of JICA on contract and notice to commence
4 Detailed design 12 months Location survey and research
Detailed design related to river improvement, bridges and river
structures
Volume calculation and estimation of accumulation
Preparation of bidding documents
5 Selection of contractors 12 months Prequalification of bidders, creation of bidding documents and
consent of JICA
Bidding
Bidding evaluation
Consent of JICA
Negotiation and conclusion of contract
JICA’s consent to contract, opening of L/C and issue of L/Com
6 Implementation of main 48 months River improvement, Rebuilding of Bridge, Retarding basins,
construction works Ring dike, Surrounding dike, Shortcut
7 Completion of - Completion of construction and delivery
construction and delivery
Note: The time period required for JICA’s consent on procurement differs depending on the type (consultant or
contractor) and the amount.
Table 20-8 below shows the implementation schedule of the Project under the above-described conditions.
Land acquisition has to be completed before the initiation of the Project.
0
1
Pledge 1
1
Signing of Loan Agreement 1
1 1 1 1 1 1 1 1 1 1 1 1
Selection of Consultant (12 months) 12
1 1 1 1 1 1 1 1 1 1 1 1
Tender Assistance (12 months) 12
1 1 1
Preparation of Bid Document & JICA Concurrence (3 months) 3
1 1
Tender Period (2 months) 2
1 1
Evaluation of Bids (2months) 2
1
JICA Concurrence of Bid Evaluation (1 month) 1
1 1
Contract Negotiation (2 months) 2
1
JICA Approval of Contract (1 month) 1
1
Opening of L/C and Ussurance of L/Com (1 month) 1
0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Consulting Services (84 months) 84
1 1 1 1 1 1 1 1 1 1 1 1
Detailed Design (12 months) 12
1 1 1 1 1 1 1 1 1 1 1 1
Tender Assistance (12 months) 12
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Construction Supervision (50 months) 50
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Project Management Unit Supporting (84 months) 84
0
0 4 12 12 7 0 0 0 0 0
Land Acquisition 35
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 6 12 12 12 8 0 50
Package 1 River Widening 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
0 0 0 0 6 12 8 0 0 0 26
Package 2 Retarding Basin 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
0 0 0 0 0 6 12 8 0 0 26
Package 3 Ring Dike 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
0 0 0 0 0 6 12 12 8 0 38
Package 4 Surrounding Dike 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
※ Year in above table shows the fiscal year of Fiji (August 1st to July 31th of following year)
Source: JICA Study Team
Table 20-9 Procurement Methods for the Main Construction Works of the Project
Package Target zone Approximate Outline of the construction Procurement method
construction
cost
Package-1 River Improvement 8.43 B yen River improvement (levee, excavation, International
(155MF$) disposal of waste soil) competitive bidding
Rebuilding bridge
(ICB) with
Rebuilding bridge
prequalification
Package-2 Retarding basinA,B 2.30 B yen Constructing retarding basins
(42MF$)
Overflow weir facilities
Package-3 Ring dike 0.076Byen Levee, Installation of river structures
(1.4MF$)
Package-4 Surrounding dike 0.66 Byen River improvements (levee, excavation,
Shortcut (12MF$) disposal of waste soil)
US$1=F$2.17, F$1=¥54.5
Therefore, we propose Project Management Unit ( PMU) will launch. Draft project implementing structure
is shown below.
Implementation Agency
MOIT *2)
MOL
MOA
,
,
Supervision
Contractors
,
Contractors ,
Im p l ementatio n of Works
Figure 20-5 PMU Organizations and Functions in Execution of Yen Loan and Technical
Cooperation Project
Operation Annual maximum water level (m) *1 2,450 m3/s 1,800 m3/s
indicator (Calculated flood (Channel Full
discharge before Flow)
flood control) (Design Discharge:
Q50)
Effect indicator Annual maximum inundation area (km2) *2 9,137 ha 0 km2
(houses) *2
*1:Discharge in Nadi Town Bridge
*2: Due to destruction or overflow of dike (river water inundation) except inland inundation by rainfall
21.2 Preconditions
Preconditions applied for the evaluation are stated below.
The year means here the fiscal year of Fiji, from August 1 to July 30 of next year
Forecasting the long-term inflation rate involves many uncertainties and not reliable. Price
escalation of benefit and cost will balance out if the escalation rate is the same for the both of
them in this investment plan.
And it is necessary to avoid introduction of assumption which is price escalation rate during
long project period, and to secure the logical consistency the EIRR estimated by the present
value and capital opportunity cost. Therefore, the analysis is based on 2015 price, and price
escalation in evaluation period is not considered.
Final Report, Volume II Main Report, Part II: Feasibility Study
21-1
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Market price is converted to economic price for the project valuation. The following items are
considered in calculating the economic price of the project.
1) Tax and public dues
Tax and public dues are not included in the economic price. Value added tax that is 9% is not included
in the calculation of the benefits and costs.
2) Land price
Land price is calculated through deducting the cash flows from land usage when there is a big gap
between market and economic price. Market price of land is used for the project valuation as such
price gap does not exist in project area.
3) Standard Conversion Factor (SCF)
SCF is used to convert domestic price to market price. The SCR used by ADB for development
projects in Fiji is 0.986, which shows very small difference between domestic and market prices.
Therefore, SCF of 1.0 is used for this project.
Social Discount Rate (SDR) is set at cut off line of 10–12% level in the economic analysis
guidelines of the World Bank, Asian Development Bank and Inter-American Development
Bank. The discount rate applied to the project is set at 10% as this rate is often applied to Fiji
aid projects by Asian Development Bank, the World Bank and other international aid
agencies.
21.3 Project Cost
The total project cost used in this study for the economic evaluation is ¥16.4 billion
(F$ 301million). This cost does not include tax, price escalations and public dues. Operational
and maintenance cost is set at 0.5% of the capital expenditure in reference to the cases of
other countries.
21.4 Benefits
Benefit of the flood control project is the economic value of damage and loss that can be reduced through
the implementation of the project (With Project).
A practical method for calculating benefits is as follows.
a) Organize the assets within the expected inundation area.
b) Calculate the amount of flood damage/loss without the project for the probability of flooding
( 1/2, 1/3, 1/5, 1/10, 1/20, 1/30,1 / 50 Years).
Final Report, Volume II Main Report, Part II: Feasibility Study
21-2
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
c) The expected yearly average damage reduction amount is calculated based on the flood
damage/loss with the project and the flood damage/loss amount without project shown in b).
Collect and arrange the following asset data within the expected inundation area.
Table 21-1 Total appraised value and number of houses in Viti Levu Island in Fiji
Average Number of Total Value of houses
House material prices Ratio JPY(,000)
House (FJD)
(FJD)
Concrete 90,189 68,111 39.27% 6,173,304,597 336,445,101
Wood 60,989 41,765 24.08% 2,559,844,438 139,511,522
Tin, or iron 36,216 58,453 33.70% 2,127,440,896 115,945,529
Thatched wood 431 3,152 1.82% 1,365,707 74,431
Makeshift 593,597 32,351
539 1,096
materials 0.63%
Other 323 880 0.51% 285,967 15,585
Total 173,457 100.00% 10,862,835,203 592,024,519
Source: JICA Study team based of PDNA data
house is 39% for concrete, 24% for wood and 34% for tin and iron, therefore the average ownership is
calculated as 0.56 (=0.39x 0.9+0.24x0.7+0.34x0.12). The value of passenger car is set at FJD7, 000.001
Total value of household goods plus the car is stated in Table 21-3.
Table 21-5 Depreciable property and stocks per each worker in expected inundation area
Industrial Sector Depreciable Commercial Number of Depreciable Depreciable
property per stocks per workers in property property and
worker(FJD) worker(FJD) the possible and stocks stocks by
flood area by sector(JPY,
sector(FJD) thousand)
Agriculture, Fishing 3,113 713 580 2,219,608 120,969
Agricultural processing 3,113 713 18 68,884 3,754
Mining, Quarrying 20,149 4,727 21 522,390 28,470
Processed foods products 4,671 2,389 25 176,495 9,619
Tobacco, Beverages、Feed 21,218 11,986 22 730,470 39,811
Products
1
Value of general secondhand sedan car obtained by hearing from car dealer in Nadi
Final Report, Volume II Main Report, Part II: Feasibility Study
21-4
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
6) Crops
Table 21-6 shows planting acreage, yield, and gates price of major crops. Planting acreage for each crop
is calculated from the division map of planting acreage of major crops (GIS data, refer to Figure 21-1).
Each crop prices are obtained from the Fiji Ministry of Agriculture, Fiji Bureau of Statistics and the PDNA.
Table 21-6 Planting acreage, yield and gate price of major crops in expected inundation area
Type of crops Crop type for Planting Yield per Crop Gate price Total Total
damage ratio acreage(ha) hectare yield per ton shipment shipment
value value
(FJD) (JPY, 000)
Field crops 1,457.21 42.4 61,742.0 84 5,186,327 282,655
Sugarcane
Cassava Field crops 89.87 7.8 704.6 755 531,959 28,992
Papaya(paw paw) Field crops 5.72 8.4 48.3 2,500 120,692 6,578
Source: JICA Study team based on data of MOA, Bureau of Statistics and PDNA
Summary of Assets that are objected for the damage and loss calculation is listed in the Table 21-7. These
items will be separated in damage and loss categories and calculated respectively.
Firming facility
2.Loss Business loss due to Loss estimation of each business size, Business loss per day x number of days of
the suspended and data supplied from PDNA. business suspension/disruption
disrupted business Number of business in the possible
activities(Excluding flood area is picked up from GIS data
tourism sector) from Fiji government.
Number of days of business
suspension and disruption is
calculated based on the interview and
[H17 flood control economic
evaluation manual] is also referenced.
Tourism business loss Tourism business data in the possible Tourism business loss per day x number of
due to the business flood area are supplied from FBOS days of business suspension/disruption
suspension and and PDNA.
disruption Number of business suspension and
disruption is calculated based on the
interview and [H17 flood control
economic evaluation manual] is also
referenced.
Business opportunity Annual number of visitors supplied Annual Tourism Income x reduction rate
loss in tourism due to from FBOS. of visitors
the reduction of annual
visitors after the flood.
Cost for emergency Number of household and business Number of households in a mesh of the
measure in household entity in expected inundation area is possible inundation zone x total number of
picked up from GIS data from Fiji days of cleaning per household by
government. inundation depth x cleaning cost per day
Cleaning cost per day in household is Increased expense of alternative activities
set at FJD30 based on the daily in household x number of household in
allowance of unskilled labour in Nadi expected inundation area.
Total number of days of cleaning per
household is set base on the interview
by the Study team.
Increased expense of alternative
activities in household is based on
[H17 flood control economic
evaluation manual] adjusted by GNI
ratio between Japan and Fiji
Cost for emergency Number of household and business Number of business entity in expected
measures in business entity in expected inundation area is inundation area x Cost for emergency
picked up from GIS data from Fiji measures in business.
government.
Increased expense of alternative
activities in business entity is based on
[H17 flood control economic
evaluation manual] adjusted by GNI
ratio between Japan and Fiji.
Public utilities and Loss and expense for restoration of Loss and restoration expense for the flood
infrastructures public services after the flood. 2012 that is published by NDMO is used.
Airport cleaning expense is set based
on the interview with Airport Fiji.
21.5.2 Damage
The damage of the following assets in the estimated inundation area is estimated as an example of the
flood with occurrence probability of once in 50 years (1/50).
Inundation depth 0.5m or less 0,5m 〜 0.99m 1.0m or over Burial depth from the
ground
Inundation No. of 1〜 3〜 5〜 7 or 1〜 3〜 5〜 7or 1〜 3〜 5〜 7or 0.5m 0.5〜 1.0m
days 2 4 6 over 2 4 6 over 2 4 6 over or 0.99m or
less over
Crop Paddy rice 21 30 36 50 24 44 50 71 37 54 64 74 70 100 100
Type
Rice 20 34 47 60 31 40 50 60 44 60 72 82
Sweet 11 30 50 50 27 40 75 88 38 63 95 100
potato
Cabbage 42 50 70 83 58 70 83 97 47 75 100 100
Vegetables 19 33 46 59 20 44 48 75 44 38 71 84
Beans 23 41 54 67 30 44 60 73 40 50 68 81
Farmland 27 42 54 67 35 48 67 74 51 67 81 91 68 81 100
crops
Source: Rate of damage to agricultural crops by inundation depth (average per unit area of farmland, Flood Control Economic Research
Manual (Draft) (April 2005, River Bureau, Ministry of Land, Infrastructure, Transport and Tourism)
Final Report, Volume II Main Report, Part II: Feasibility Study
21-10
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
6) Damage to livestock
Following table 22-13 indicates the damage of livestock with flooding expected in 1 / 50 probability. The
damage amount is based on the Government announcement with flood damage report in 2009. The
number is adjusted by the consumer price index by the year 2015 converted into (2009 value x 1.20).
Table 21-13 Damage of livestock in the expected inundation area (1/50 probability)
Damage(FJD) Damage(JPY,000)
Livestock 4,794,959 261,325
21.5.3 Loss
Loss for business =Business loss per day x number of days of business suspension and disruption
Final Report, Volume II Main Report, Part II: Feasibility Study
21-11
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Loss amount per day is referenced from Fiji Bureau of Statistics and the PDNA in each categories of
business entity size. (Micro: less than five people, Small/Medium: 6-20 people, Medium/Large: more than
21 people).
Table 21-15 Loss for business in the expected inundation area (1 / 50 probability, except
tourism)
Size of commercial entity Micro Small/Medium Medium/Large Total
(1~5 people) (6~20 people) (more than 20 people)
Number of business entity in a 688 241 119 1,048
possible flood area
Loss per business entity in a day 166 422 1,080
Expected number of business 20 20 20
disruption
Total loss Amount 2,288,563 2,035,390 2,570,400 6,894,353
Yasawa
Mamanuca
Number of days for suspension and stagnation for tourism in the Nadi area is set at 20 days2 referring to the
flood disaster in 2009 and 2012. Number of days for suspension and stagnation in Yasawa-Mamanuca
Islands is set at 7 days as most tourists move from Denarau Marina via Nadi Airportconsdering close of
airport, marina and road.
2
It took 20days for the restoration and cleaning of road and 7days for business suspension and stagnation
due to close of airport, marina and road in flood damage in 2009 and 2012 from the hearing with FRA.
The following formula is used for calculation of the loss for tourism.
Loss for tourism = Tourism profit per year x numbers of days of business suspension and stagnation /365
Table 21-16 Loss for tourism in the expected inundation area (1 / 50 probability)
Annual tourism profit in Fiji (FJD)2 1,488,900,000
3
Annual l tourism profit in Nadi area (FJD) 550,893,000
Annual l tourism profit in Yasawa-Mamanuca Islands (FJD) 357,336,000
Number of days of business suspension and stagnation in Nadi 20
Loss of tourism in Nadi(FJD) 30,185,918
Number of days of business suspension and stagnation in Yasawa-Mamanuca 7
Loss of tourism in Yasawa-Mamanuca (FJD) 6,853,019
Total loss of tourism in Nadi and Yasawa-Mamanuca (FJD) 37,038,937
Loss of tourism in Yasawa-Mamanuca (JPY, 000) 2,018,622
Source: JICA Study team
Decrease in the number of tourists is seen throughout Fiji in case of the massive flood damage occurred,
according to the Fiji Bureau of statistics. Rate of tourist arrivals in 2009 decreased 7.3% in 2009 and 2.1
percent in 2012. Decrease of number of tourism is set at 2.0% with probability of 1/50 flood in the
following formula.
Loss from the decreased number of tourist = Annual tourism income x reduction rate of visitors
Table 21-17 below indicates the opportunity loss due to decrease in tourist visitors.
Table 21-17 Loss for tourism in reduction of tourist arrivals (1 / 50 probability)
Annual tourism profits in Fiji3(FJD) 1,488,900,000
Reduction rate of tourists 2.0%
Loss from the decreased number of tourist(FJD) 29,778,000
Loss from the decreased number of tourist(JPY, 000) 1,622,901
Source:JICA Study team
Following table 21-18 shows the total loss of tourism in the expected inundation area
Table 21-18 Total loss for tourism
Loss (FJD) Loss(JPY,000)
2
Expected profits in 2015 based of Fiji Bureau of Statistics
3
2015 tourism industry revenue is expected by the Fiji Bureau of Statistics
Final Report, Volume II Main Report, Part II: Feasibility Study
21-13
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
4
No unit cost of standard cost of alternative activity in Fiji. The unit cost in Japan converted to that in Fiji is FJD 440 which
is approximately JPY 25,000 and 1/10 of Japanese cost. The cost seems to be reasonable from hearing of unskilled labor in
Nadi of which daily allowance is approximately JPY 1,600.
Final Report, Volume II Main Report, Part II: Feasibility Study
21-14
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Items of damage and loss are listed in the table 21-22 and table 21-23 respectively.
Table 21-22 Items of Damage (Without Project, 1/50 probability)
Damage
FJD (000) JPY (000)
Value of Residential house and commercial buildings FJD 601,148 ¥32,762,586
Damage to house and building FJD 62,500 ¥3,406,243
5
FJD 6,000 is likely to be reasonable which is converted from damage in Japan to Damage in Fiji in proportion to GNI and
checked by comparing with data obtained from hearing with trader in Nadi such as car dealer, spare parts trader, restaurant
business
Final Report, Volume II Main Report, Part II: Feasibility Study
21-15
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
1/3 18 7.50 11
30 0.133 4 5
1/5 65 16.43 49
61 0.100 6 11
1/10 102 28.33 74
86 0.050 4 16
1/20 136 37.68 98
106 0.017 2 17
1/30 159 45.89 113
108 0.013 1 18.8
1/50 159 55.53 104
(Formula)
𝐵𝑡 𝐶𝑡
B/C Ratio = ∑𝑟𝑡=0 ÷ ∑𝑟𝑡=0 (r: discount rate)
(1+𝑟)𝑡 (1+𝑟)𝑡
𝐵𝑡 𝐶𝑡
NPV = ∑𝑟𝑡=0 − ∑𝑟𝑡=0 (r: discount rate)
(1+𝑟)𝑡 (1+𝑟)𝑡
𝐵𝑡 𝐶𝑡
EIRR = discount rate when NPV = ∑𝑟𝑡=0 − ∑𝑟𝑡=0 =0
(1+𝑟)𝑡 (1+𝑟)𝑡
Cash flow with the priority project is stated in the following Table 21-27.
Table 21-27 Cash flow with the priority project (JPY, 100 million)
Construction Maintenance Total cost Benefit Net
Total period Period after
cost (JPY100 cost (JPY100 (JPY100 (JPY100 (JPY100
(year) construction (year)
million) million) million) million) million)
1 2.32 0.00 2.32 0.00 -2.32
2 8.23 0.00 8.23 0.00 -8.23
3 10.74 0.00 10.74 0.00 -10.74
4 37.50 0.00 37.50 5.04 -32.46
5 Construction Period 31.29 0.00 31.29 9.24 -22.04
6 29.40 0.00 29.40 13.19 -16.20
7 22.44 0.00 22.44 16.21 -6.24
8 19.52 0.00 19.52 18.83 -0.69
9 2.70 0.00 2.70 18.83 16.13
10 1 0.58 0.58 18.83 18.25
11 2 0.58 0.58 18.83 18.25
12 3 0.58 0.58 18.83 18.25
13 4 0.58 0.58 18.83 18.25
14 5 0.58 0.58 18.83 18.25
15 6 0.58 0.58 18.83 18.25
16 7 0.58 0.58 18.83 18.25
17 8 0.58 0.58 18.83 18.25
(Calculation)
= 120.90
= 102.82
𝐵𝑡 𝐶𝑡
NPV = ∑𝑟𝑡=0 (1+𝑟)𝑡 − ∑𝑟𝑡=0 (1+𝑟)𝑡 = 120.90 − 102.82 = 18.08
𝐵𝑡 𝐶𝑡
EIRR is discount rate in case NPV = ∑𝑟𝑡=0 (1+𝑟)𝑡 − ∑𝑟𝑡=0 (1+𝑟)𝑡 = 0
Here,
𝑟 𝑟
𝐵𝑡 𝐶𝑡 0 0 0 5.04 18.83 18.83
∑ − ∑ ={ + + + + ・・・ + + }
(1 + 𝑟)𝑡 (1 + 𝑟)𝑡 (1 + 𝑟)1 (1 + 𝑟)2 (1 + 𝑟)3 (1 + 𝑟)4 (1 + 𝑟)58 (1 + 𝑟)59
𝑡=0 𝑡=0
Sensitivity analysis shall be conducted to deal with future uncertainties caused by fluctuation of social and
economic circumstances. For cost-benefit analysis, we need to predict future costs and benefits concerning
the project to be evaluated. However, as public work projects, characterized by a long period from planning
to start of service as well as a long service period, they have a large number of uncertain factors that have a
great impact on the future costs and benefits and it is impossible to accurately predict such costs and
benefits. Therefore, pre-defined premises and assumptions often lose touch with the reality and therefore
the result of cost-benefit analysis can differ from the reality.
Therefore, the result of the cost-benefit analysis involving such uncertainties should be calculated and
presented as a range rather than something absolute based on a single scenario. One of the methods for this
is sensitivity analysis.
By conducting sensitivity analysis and presenting the result of cost-benefit analysis with some margin, we
will improve accuracy and reliability of the project evaluation as well as fulfilling our responsibility for
appropriate supervision of the project and accountability to the public.
The method of factorial sensitivity analysis is conducted, which is generally used in public work projects.
The following cases shall be subject to sensitivity analysis.
Table 21-28 Cases subject to sensitivity analysis
Indicator Range of factors
Cost Cases where the cost increases by 5%, 10% and 15%
Benefit Cases where the benefit decreases by 5%, 10% and 15%
Sensitivity analysis is conducted with fluctuating benefits and costs for analyzing changes of EIRR. As
shown in Table 21-29, the EIRR of Case 1 (5% benefit decrease and 5% cost increase) is 10.7%, 9.60%
for Case 2 (10% benefit decrease and 10% cost increase), and 8.5% for Case 3(15% benefit decrease and
55% cost increase). Although, these EIRR results of Case 2 and Case 3 are slightly below the target rate of
10%, their possibility possibilities are estimated to be low based on the prospect of increase of the benefits
by economic growth in Nadi area.
Table 21-29 Result of sensitivity analysis
Case 1 Case 2 Case 3
Benefit -5% -10% -15%
Cost +5% +10% +15%
EIRR 10.7% 9.6% 8.5%
Malakua River
2) Disposal Site
According to the site survey, confirmed candidates of dumping area are the following nine (9) locations.
Topsoil stripping soil occurred in excavation of river bank is transported to disposal sites and general soil is
diverted to materials for embankment and backfilling, and surplus soil is transported to disposal sites.
Transportation distance is about 5km from each site to the nearest disposal site.
Though approx. 2.7 million m3 surplus soils are generated in this project, it is acceptable by these disposal
sites since total amount of acceptable volume becomes approx. 2.4 million m3 (h=2.0m) except proposed
town boundary area, approx. 3.0 million m3 (h=2.0m) including proposed town boundary area and approx.
3.5 million m3 (h=3.0m).
However, it is required that possibility for use as disposal site shall be reviewed with related agencies and
land owner during detailed design stage.
Upstream G Upstream I
Middle stream E
Middle stream D
Middle stream C
Middle stream H
Downstream A
Downstream B Middle stream F
2) Survey Results
In the target area (Nadi River Basin), there are no large scale of factory, high traffic roads existed. In
addition, there are no environment where particularly high concentrate for pollutant by topographical,
structural layout etc. In general, the air quality in the area is evaluated as good.
Table 22-3 Result of Impact Assessment for Construction of Central High Speed Railway in
Japan (Air Pollution)
Item Condition/Target Results of Estimation (daily average)
Work of vehicle nitrogen dioxide 0.00332 ~ 0.03076 (ppm)
concentration
airborne particulate matter 0.00043 ~ 0.01060 (mg/m3)
Transportation for caring Number of Annual 20,135 ~ 135,213 (cars)
materials and machines working cars
nitrogen dioxide 0.00004 ~ 0.00046 (ppm)
concentration
airborne particulate matter 0.00001 ~ 0.00006 (mg/m3)
Source: EIA report of Central High Speed Railway (Yamanashi Prefecture) (written in Japanese)
In Fiji, there is no standards for air quality, but the impact to air quality by the construction work in the
Project, the situation which exceeding the Japanese standard (see Table 22-4) is not anticipated.
[For Air pollution by dust due to earth works for dike and excavation, etc.]
Excavation materials must be properly stockpiled and properly disposed of immediately from the
construction site when not needed.
Provision of covers to stockpiles that will be left idle for a long time,
Dust generation will be mitigated with watering at dusty place and covering the load of trucks by
tarpaulin,
Periodical and timely cleaning of the spilled materials on road or other public space along the
transportation route of construction materials and spoil materials
[For Air pollution by emission gas due to the operation of construction equipment and vehicles]
Using a low emission type construction equipment and vehicles,
Regular maintenance of construction equipment and vehicles,
Consideration of operation manner of the equipment due to the regular education to the operators.
Figure 22-3 Situation of water sampling (sampling for lab test and in site measurement)
b) Survey Locations
Locations of sampling five (5) sites are shown in Figure 22-4.
Site4
Site5
Site3
2) Survey Results
The Results of water quality test are shown in Table 22-5. Salinity and Conductive are high in Site1 and 2
due to these sites are located in the tidal area. In addition, the value of Phosphors and Nitrate are also high
in Site1 and 2. The possible reason of high value is influence of drainage from Water Treatment Plant at
upstream of Site2. In Site 3,4 and 5, the Total Suspended Solids are relatively high, however, the water
quality in these area are in good condition.
[for Water pollution by waste water (effluent and used oil) from construction yards and offices, and
accidental oil spill]
To ensure not to directly drain the waste water from construction yard and offices to the river,
Waste water is to be properly treated and disposed using septic tank or other appropriate treatment
method
Provision of portable toilet for the workers at the construction work sites.
To ensure not to cause accidental oil spill and other chemicals.
b) Survey Locations
Locations of sampling five (5) sites are shown in Figure 22-5.
Site4
Site5
Site3
Figure 22-5 Riverbed Material Sampling Sites along the Nadi River
2) Survey Results
Results of riverbed survey are shown in Table 22-6 and Table 22-7. The conditions of river bed are almost
same in all stations and no extensive accumulation of heavy metals are observed.
Table 22-6 Result of Riverbed (General Conditions)
Sediment Analysis Unit
Site 1 Site 2 Site 3 Site 4 Site 5
Parameters
pH unit 8.0 7.5 7.4 7.6 8.0
Organic Matter g/100g 2.4 5.6 1.43 1.33 1.78
Dry Matter g/100g 76 55 86 79 82
Ash g/100g 98 94 99 99 98
Manganese mg/kg 420 520 840 570 500
Phosphorous mg/kg 370 610 750 350 380
Nitrite + Nitrate mg/kg <1.0 <1.0 <1.0 <1.0 <1.0
Sediment
Analysis
Unit Site 1 Site 2 Site 3 Site 4 Site 5 Guidelines*
Parameters –
Heavy metals
Nickel (Ni) mg/kg 22 28 23 25 28 21
Zinc (Zn) mg/kg 58 68 39 39 37 200
*ANZECC (2000) recommended guideline values, tabulated as Interim Sediment Quality Guideline (ISQG) – Low (Trigger
value).
2) Survey Results
In the Project area (Nadi River Basin), there are no large factories and high traffic load is not identified.
The noise and vibration environment in the area is evaluated as good condition.
Quietness is specially required, such as those Less than 50dB Less than 40dB
AA where convalescent facilities and welfare
institutions are concentrated.
The major construction equipment utilized in the project is backhoe for excavation. The distance depression
of noise and vibration are reported as shown in Figure 22-7 and Figure 22-8. Noise and vibration level
may be affected depend on the ground and weather conditions, but the noise and vibration levels are
decrease enough by the distance. Therefore, in this project, generation of noise and vibration exceedance
standards may not be anticipated.
Noise Level (dB)
2) Survey Results
During the riverbed survey, limited algae accumulation is identified. However, the area and quantity are
relatively small in the Nadi River environment. The possibility of occurrence of offensive odor caused by
these algae is not anticipated.
Figure 22-9 Condition of Algae in Namosi River which Identified during Water and Riverbed
Survey
1) Survey Method
The hydrological situation of Nadi River is estimated through the non-uniform flow calculation. Therefore,
by using the results of non-uniform calculation, variation of water level in major sections are confirmed.
2) Survey Results
The section average water level is decreased, however, to generate initial water-route even in just after the
excavation, required water depth in normal condition may be secured.
Site3
Site2
Site1
Site4
Site7 Site5
Site6
2) Survey Results
The result of inventory survey for benthos and fish are shown in Table 22-10 and Table 22-11 respectively.
Trichoptera Triaenodes
2 1 - 1 - - - 4
fijianus
Decapoda Macrobrachium
5 10 12 6 - - - 33
equidens
Macrobrachium
3 2 4 2 - - - 11
lar
Sorbeoconch Melanoides
tuberculata - - 10 5 - - - 15
Thiaridae
Total 10 13 26 14 63
Family Species Status Site Site Site Site Site Site Site Total
1 2 3 4 5 6 7
Gobiidae Stenogobius Native - 1 - - - - - 1
genivitattus
Glossogobius Native - - - - 3 - - 3
aureus
Anguillidae Anguilla Native 2 1 1 - - - - 4
marmorata
Syngnathidae Microphis retzi Native 2 - - - - - - 2
(Ragged tail
pipe-fish)
Ambassidae Ambasis miops Native - - - - 8 - - 8
Hemiramphida Zenarchopterus Native - - - 1 - - -
e dispar 1
Leiognathidae Leiognathus Native - - - - - 1 -
equlus 1
Carangidae Caranx Native - - - - - 1 - 1
papuensis
Cichlidae Oreochromis Introduc 4 3 2 1 - - - 10
mossambicus ed
Oreochromis Introduc 2 3 1 2 - - - 8
niloticus ed
Poeciliidae Gambusia Introduc 6 5 4 3 - - - 18
affinis ed
b) Survey Locations
During survey, the areas shown in Figure22-11 were surveyed and the appeared plants, animals, insects and
birds are recorded.
Figure 22-11 Survey Locations for Land Area Ecological Inventory Survey
2) Survey Results
The result of inventory survey for plants and animals are shown in Table 22-12 and Table 22-13
respectively.
22.2.10 Ecosystem
(1) Potential Impacts
Possible impacts by the project implementation are follows;
Loss of vegetation cover and change of habitat of wildlife
Change of frequency of flood and river velocity
The impact changes of ecosystem by the loss of vegetation during the construction period. However,
changes of ecosystem due to implementation of project may be occurring continuously after the
construction work finished.
22.2.11 Topography
(1) Base line Environment
1) Survey Method
Based on the topographical map and visual inspection, the current condition of the river has been grasped.
In addition, long term variation of riverbed has been grasped by riverbed fluctuation calculation.
2) Survey Results
Results of the riverbed fluctuation analysis, the riverbed is stable during 50 years (calculation period), there
are not expected major variation of riverbed. But in the local erosion and accumulation will occur.
Therefore, to conduct countermeasures based on the monitoring results.
[for Accumulation of sand and soil will cause the medium and long term variation of riverbed topography]
To grasp the variation of riverbed topography, regular survey may be conducted.
Based on the results of survey, necessary measures such as installation of riverbed girdle, riverbed
protection work, riverbank protection, dredging etc. will be exanimated.
b) Target Group
The social and economic survey in the project area has conducted in the area shown in Figure 22-12. The
survey target are randomly selected from households inside the survey area. The households which located
inside the project area by basic design level are included as target. In addition, Moala village where ring
dike will be constructed are included for all households in the village.
The distributions of survey target community are shown in Table 22-14. The survey was conducted during
2nd March 2016 to 3rd March.
2) Survey Results
a) Number of Households for Resettlement
Table 22-15 shows the number of household which need to be relocated. As a result, household with
residents are 6 households. All of them are located in the project area for river widening. Regarding land
tenure, 4 households are Native Land, other 2 households are located in the Free Hold Land.
Table 22-18 Survey Results on Income of Households around the Project area
House Holds Total No. %
35,001 - 40,000FJD 1 - - - 1 1%
30,001 - 35,000FJD 1 - - - 1 1%
25,001 - 30,000FJD 1 - - - 1 1%
20,001 - 25,000FJD 1 1 2 - 4 3%
15,001 - 20,000FJD 2 - - - 2 2%
Table 22-19 Survey Results on Type of Livelihood of households near the Project Area
Sector No. of People Sector No. of People
Tourism 37 Marketeer 2
Farming 16 Manufacturing 1
Government 11 Construction 1
Sales & Retail 7 Management 1
Tradesman 6 Professional 1
Aviation 5 Services 1
Education 5 Domestic Services 1
Security Services 5 Administration 1
Fisheries 3 Civic (Religious) 1
Regarding discontinuance of business, the proper compensations shall be provided as shown in RAP
Table 22-20 Survey Results for Energy Use around the Project Area
Housing on
Type of Electricity
Native State Free Undisclosed
Main Supply 67 10 30 14
Solar Lighting 1 - - -
Kerosene 3 2 1 -
Battery 1 - - -
Non - 1 1 1
94% of household connected to Fiji Water Authority water supply system. 84% out of 94% answer that the
water is clean.
The example of condition of traffic infrastructure, schooling mode has been surveyed. The Results of
schooling mode. 36 % of kids are used micro-bus.
[for Misdistribution of benefit will be occurring between developed and non-developed area.]
To make an opportunity of communication among stakeholders about the components, area and
benefit of the project, and build consensus among stakeholders.
Condition of existing cultural heritage was surveyed through the social and economic survey and existing
reports.
2) Survey Results
The important cultural heritage is not identified through the survey. 74% of households answered that there
is no important cultural heritage along the Nadi River. On the other hand, 22% of households answered that
they have an experience to bury in/near the Nadi River. Therefore, the monitoring for construction, the
consideration to the site for bury is important.
22.2.21 Landscape
(1) Base line Environment
There are no la structures in the project area. There is only low-height residence or commercial facilities.
[For Decreasing of visibility due to the construction of dike and other river facilities]
To exam the mitigation measures for the impacts
To maintain the facilities adequacy to prevent decreasing of visibility and landscape quality
2) Survey Results
according to the results of interview survey, there are no subjected household. Only one (1) household has
disabled family member.
Table 22-22 Comparison of Scoping and Impact Assessment based on Survey Results
River Widening / River short cutting / Construction of Bridges Surrounding Dike Ring Dike Retarding Basin
Assessment Assessment Assessment Assessment
Assessment at Assessment at Assessment at Assessment at
based on based on survey based on survey based on survey
Environmental Components scoping
survey results
scoping
results
scoping
results
scoping
results
Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation
Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period
I & II III I & II III I & II III I & II III I & II III I & II III I & II III I & II III
[Construction] Air pollution due to dust [Construction] Air pollution due to dust [Construction] Air pollution due to dust [Construction] Air pollution due to dust
and emission gas by construction and emission gas by construction and emission gas by construction and emission gas by construction
equipment and vehicles as well as earth equipment and vehicles as well as earth equipment and vehicles as well as earth equipment and vehicles as well as earth
Air works will occur. works will occur. works will occur. works will occur.
1 B- D B- D B- D B- D B- D B- D B- D B- D
Pollution
[Operation] No air pollution which is [Operation] No air pollution which is [Operation] No air pollution which is [Operation] No air pollution which is
attributed to the project components will attributed to the project components will attributed to the project components will attributed to the project components will
occur because the project facilities are occur because the project facilities are occur because the project facilities are occur because the project facilities are
not pollution source. not pollution source. not pollution source. not pollution source.
[Construction] Suspension of sediments
[Construction] Suspension of sediments
and release of sediment pollutants will
and release of sediment pollutants will
occur as a result of excavation/dredging
[Construction] Creation of bare land and [Construction] Creation of bare land and occur as a result of construction a
for river widening, river short cutting
waste water from contractor base camp waste water from contractor base camp facilities and excavation/dredging in the
and construction of bridges. Creation of
Water and/or office would also cause water and/or office would also cause water river. Creation of bare land and waste
2 B- D B- D bare land and waste water from B- D B- D pollution in the river. B- D B- D pollution in the river. B- D B- D water from contractor base camp and/or
Pollution
contractor base camp and/or office
office would also cause water pollution
would also cause water pollution in the [Operation] There will be no pollution [Operation] There will be no pollution
source of water. source of water. in the river.
river.
Physical-Chemical Environment (Pollution)
River Widening / River short cutting / Construction of Bridges Surrounding Dike Ring Dike Retarding Basin
Assessment Assessment Assessment Assessment
Assessment at Assessment at Assessment at Assessment at
based on based on survey based on survey based on survey
Environmental Components scoping
survey results
scoping
results
scoping
results
scoping
results
Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation
Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period
I & II III I & II III I & II III I & II III I & II III I & II III I & II III I & II III
No land subsidence is anticipated during No land subsidence is anticipated during No land subsidence is anticipated during No land subsidence is anticipated during
both construction and operation stage both construction and operation stage both construction and operation stage both construction and operation stage
Land
6 D D D D because pumping of groundwater, deep D D D D because pumping of groundwater, deep D D D D because pumping of groundwater, deep D D D D because pumping of groundwater, deep
Subsidence
excavation work, or tunneling work is excavation work, or tunneling work is excavation work, or tunneling work is excavation work, or tunneling work is
not included in the project activities. not included in the project activities. not included in the project activities. not included in the project activities.
[Construction] Offensive odor during
construction work will be minimal
because the sludge or other cases of odor
accumulation is not recognized based on
Offensive the field survey results. No occurrence of offensive odor is No occurrence of offensive odor is No occurrence of offensive odor is
7 B- B- D D D D D D anticipated during both construction and D D D D anticipated during both construction and D D D D anticipated during both construction and
Odor
[Operation] Generation of offensive odor operation stage operation stage operation stage
is not anticipated because there is no
possibility of generation of closed water
area which cause a blooming of algae in
the river area.
No riverbed sediment contamination is No riverbed sediment contamination is No riverbed sediment contamination is No riverbed sediment contamination is
Riverbed anticipated during both construction and anticipated during both construction and anticipated during both construction and anticipated during both construction and
Sediment operation stage because survey results of operation stage because survey results of operation stage because survey results of operation stage because survey results of
8 D D D D the riverbed sediment quality indicate D D D D the riverbed sediment quality indicate D D D D the riverbed sediment quality indicate D D D D the riverbed sediment quality indicate
Contamina that the river sediment is non-hazardous that the river sediment is non-hazardous that the river sediment is non-hazardous that the river sediment is non-hazardous
tion materials, and hazardous level of heavy materials, and hazardous level of heavy materials, and hazardous level of heavy materials, and hazardous level of heavy
metals is not detected. metals is not detected. metals is not detected. metals is not detected.
Protected There is no protected area in and around There is no protected area in and around There is no protected area in and around There is no protected area in and around
9 D D D D D D D D D D D D D D D D
Area the presumed project area. the presumed project area. the presumed project area. the presumed project area.
[Construction] Changing of river flow
would occur as a result of temporally
river closure works.
Hydrologic
al [Operation] Result of the Project, river
C discharge capacity will increase and the No impact to hydrological situation No impact to hydrological situation No impact to hydrological situation
10 Situation B- B- B- flood risk will be mitigated. On the other D D D D (river flow) is anticipated during both D D D D (river flow) is anticipated during both D D D D (river flow) is anticipated during both
+/- construction and operation stage construction and operation stage construction and operation stage
hand, result of widening of the river,
(River water depth will be decrease in a
flow) non-flood situation. But the impact of
decreasing of water depth is not
significant and can be mitigated by a
Natural Environment
River Widening / River short cutting / Construction of Bridges Surrounding Dike Ring Dike Retarding Basin
Assessment Assessment Assessment Assessment
Assessment at Assessment at Assessment at Assessment at
based on based on survey based on survey based on survey
Environmental Components scoping
survey results
scoping
results
scoping
results
scoping
results
Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation
Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period
I & II III I & II III I & II III I & II III I & II III I & II III I & II III I & II III
Forest +/- located in Nadi River mouth, however, project site. No impact to mangrove project site. No impact to mangrove project site. No impact to mangrove
the project area is upstream form forest is anticipated. forest is anticipated. forest is anticipated.
5.75km. There is no direct impact to the
mangrove forest. There is possibility to
generate turbid water from the
construction sites. However, the
possibility of reaching turbid water from
construction site to mangrove forest is
quite small. The impact of construction
works for mangrove forest is not
anticipated.
[Operation] In case of flood situation,
mangrove forests located in Nadi River
mouse would be inundated, however, this
phenomenon is also observed in this area
before the project. So, the impact of the
project is not anticipated.
[Construction] River widening would
[Construction] Construction of dike [Construction] Construction of dike [Construction] Construction of dike
Topograph cause the change of topographical
would cause the change of topographical would cause the change of topographical would cause the change of topographical
y and features along the Nadi River.
features. features. features.
14 Geographi B- C+/- B- B+/- [Operation] From the long term point of B- D B- D B- D B- D B- D B- D
cal view, sand accumulation and bank
erosion will occur. Adequate monitoring [Operation] No impact to topography [Operation] No impact to topography [Operation] No impact to topography
Features activities will be needed to grasp and geographical features is anticipated. and geographical features is anticipated. and geographical features is anticipated.
accurate conditions.
[Pre-Construction / Construction] There
will be a total of 6 households of
involuntary resettlement required by
river widening. Resettlement of the [Pre-Construction / Construction] No [Pre-Construction / Construction] No [Pre-Construction / Construction] No
Involuntar
affected households needs to be involuntary resettlement is anticipated in involuntary resettlement is anticipated in involuntary resettlement is anticipated in
y
15 B- D B- D completed before construction is B- D D D the surrounding dike construction area. B- D D D the surrounding dike construction area. B- D D D the surrounding dike construction area.
Resettleme commenced.
nt [Operation] There is no impact to [Operation] There is no impact to [Operation] There is no impact to
involuntary resettlement. involuntary resettlement. involuntary resettlement.
[Pre-Construction/Construction] As the
[Pre-Construction/Construction] As the [Pre-Construction/Construction] As the [Pre-Construction/Construction] As the
result of survey, 41% of households (4
result of survey, 41% of households are result of survey, 41% of households are result of survey, 41% of households are
households are required for involuntary
living with less than 5,000FJD income living with less than 5,000FJD income living with less than 5,000FJD income
resettlement) are living with less than
per annum. Measures aimed to per annum. Measures aimed to per annum. Measures aimed to
5,000FJD income per annum.
Poverty improving standard of living need to be improving standard of living need to be improving standard of living need to be
16 C- C- B- B- Measures aimed to improving standard C- C- B- B- C- C- B- B- C- C- B- B-
Group provided to project affected households provided to project affected households provided to project affected households
of living need to be provided to project
before construction begins. before construction begins. before construction begins.
affected households before construction
begins. [Operation] There is possibility of [Operation] There is possibility of inflow [Operation] There is possibility of inflow
inflow of informal settlers to Nadi River of informal settlers to outside of ring of informal settlers to inside of retarding
[Operation] There is possibility of inflow side and dike side. dike. basins..
of informal settlers to Nadi River side.
Fiji’s indigenous people, Fijian is one of Fiji’s indigenous people, Fijian is one of Fiji’s indigenous people, Fijian is one of Fiji’s indigenous people, Fijian is one of
Indigenous the major ethnic group in Fiji. There is the major ethnic group in Fiji. There is the major ethnic group in Fiji. There is the major ethnic group in Fiji. There is
17 C+/- C+/- D D C+/- C+/- D D C+/- C+/- D D C+/- C+/- D D
Peoples no indigenous groups are observed in the no indigenous groups are observed in the no indigenous groups are observed in the no indigenous groups are observed in the
project area. project area. project area. project area.
River Widening / River short cutting / Construction of Bridges Surrounding Dike Ring Dike Retarding Basin
Assessment Assessment Assessment Assessment
Assessment at Assessment at Assessment at Assessment at
based on based on survey based on survey based on survey
Environmental Components scoping
survey results
scoping
results
scoping
results
scoping
results
Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation
Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period
I & II III I & II III I & II III I & II III I & II III I & II III I & II III I & II III
River Widening / River short cutting / Construction of Bridges Surrounding Dike Ring Dike Retarding Basin
Assessment Assessment Assessment Assessment
Assessment at Assessment at Assessment at Assessment at
based on based on survey based on survey based on survey
Environmental Components scoping
survey results
scoping
results
scoping
results
scoping
results
Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation
Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period
I & II III I & II III I & II III I & II III I & II III I & II III I & II III I & II III
Local
Decision -
making
Institutions
[Pre-Construction] Misdistribution of
benefits and damage could be observed [Pre-Construction] Misdistribution of [Pre-Construction] Misdistribution of [Pre-Construction] Misdistribution of
among the people who need resettlement benefits and damage could be observed benefits and damage could be observed benefits and damage could be observed
Misdistrib and those who do not need along the among land owners who are targeted of among land owners who are targeted of among land owners who are targeted of
ution of river when land acquisition is required land acquisition and not. land acquisition and not. land acquisition and not.
23 Benefits C- C- B- B- for the project facilities. C- C- B- B- C- C- B- B- C- C- B- B-
and [Operation] There is possibility of [Operation] There is possibility of [Operation] There is possibility of
[Operation] There is possibility of generation of misdistribution of generation of misdistribution of generation of misdistribution of
Damage generation of misdistribution of benefits and damage between priority benefits and damage between priority benefits and damage between priority
benefits and damage between priority project area and other areas, inside and project area and other areas, inside and project area and other areas, inside and
project area and other areas, inside and outside of dykes etc. outside of dykes etc. outside of dykes etc.
outside of dykes etc.
[Pre-Construction] Local conflicts of
Interest could be observed among the [Pre-Construction] Local conflicts of [Pre-Construction] Local conflicts of [Pre-Construction] Local conflicts of
people who need resettlement and those Interest could be observed among land Interest could be observed among land Interest could be observed among land
who do not need along the river when owners who are targeted of land owners who are targeted of land owners who are targeted of land
Local land acquisition is required for the acquisition and not. acquisition and not. acquisition and not.
24 Conflicts C- C- B- B- C- C- B- B- C- C- B- B- C- C- B- B-
project facilities.
of Interest [Operation] There is possibility of [Operation] There is possibility of [Operation] There is possibility of
[Operation] There is possibility of generation of local conflicts of interest generation of local conflicts of interest generation of local conflicts of interest
generation of local conflicts of interest between priority project area and other between priority project area and other between priority project area and other
between priority project area and other areas, inside and outside of dykes etc. areas, inside and outside of dykes etc. areas, inside and outside of dykes etc.
areas, inside and outside of dykes etc.
[Pre-Construction/Construction] As the [Pre-Construction/Construction] As the [Pre-Construction/Construction] As the [Pre-Construction/Construction] As the
result of the survey, there is no cultural result of the survey, there is no cultural result of the survey, there is no cultural result of the survey, there is no cultural
facilities, sensitive facilities such as facilities, sensitive facilities such as facilities, sensitive facilities such as facilities, sensitive facilities such as
grave site, shrine etc. in the project area. grave site, shrine etc. in the project area. grave site, shrine etc. in the project area. grave site, shrine etc. in the project area.
Cultural
25 C- D D D However, during project implementation, C- D C- D However, during project implementation, C- D C- D However, during project implementation, C- D C- D However, during project implementation,
Heritage
it is required to observe the actual it is required to observe the actual it is required to observe the actual it is required to observe the actual
situations. situations. situations. situations.
[Operation] There is no possibility of [Operation] There is no possibility of [Operation] There is no possibility of [Operation] There is no possibility of
influence for cultural heritage. influence for cultural heritage. influence for cultural heritage. influence for cultural heritage.
[Construction] Change of landscape is
evaluated by the generation of bare lands
and movement of construction [Construction] Change of landscape is [Construction] Change of landscape is [Construction] Change of landscape is
equipment during construction works. evaluated by the situation of after evaluated by the situation of after evaluated by the situation of after
construction phase. construction phase. construction phase.
26 Landscape C- B+/- B- B- [Operation] River widening would be C- B- B- B- C- B- B- B- C- B- B- B-
changed. However, river itself is part of [Operation] Existence of dyke would [Operation] Existence of dyke would [Operation] Existence of dyke would
nature scenery. So that negative impact cause obstruction to landscape views cause obstruction to landscape views cause obstruction to landscape views
to social and economy is limited. In especially at the vicinity where the dike especially at the vicinity where the dike especially at the vicinity where the dike
addition, there is positive impact for is relatively high. is relatively high. is relatively high.
urban design by re-construction of
bridges.
Negative impact for gender is not Negative impact for gender is not Negative impact for gender is not Negative impact for gender is not
Gender / anticipated in this project. The rsults of anticipated in this project. Results of anticipated in this project. Results of anticipated in this project. Results of
Socially survey indicate that very few number of survey indicate that very few number of survey indicate that very few number of survey indicate that very few number of
27 C- C+/- D D C- C+/- D D C- C+/- D D C- C+/- D D
Vulnerable disability persons are identified, and they disability persons are identified, and they disability persons are identified, and they disability persons are identified, and they
Groups are not included to resettlement are not included to resettlement are not included to resettlement are not included to resettlement
households. households. households. households.
River Widening / River short cutting / Construction of Bridges Surrounding Dike Ring Dike Retarding Basin
Assessment Assessment Assessment Assessment
Assessment at Assessment at Assessment at Assessment at
based on based on survey based on survey based on survey
Environmental Components scoping
survey results
scoping
results
scoping
results
scoping
results
Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation Explanation for the evaluation
Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period Period
I & II III I & II III I & II III I & II III I & II III I & II III I & II III I & II III
Negative impact to the children rights is Negative impact to the children rights is Negative impact to the children rights is Negative impact to the children rights is
Rights of not anticipated by the project. The results not anticipated by the project. The results not anticipated by the project. The results not anticipated by the project. The results
28 C- D D D C- D D D C- D D D C- D D D
Children of survey did not find the any issues of survey did not find the any issues of survey did not find the any issues of survey did not find the any issues
regarding children’s rights. regarding children’s rights. regarding children’s rights. regarding children’s rights.
[Construction] Number of infected [Construction] Number of infected [Construction] Number of infected [Construction] Number of infected
Infectious
person in Fiji is increasing. So that there person in Fiji is increasing. So that there person in Fiji is increasing. So that there person in Fiji is increasing. So that there
Diseases
29 C- D B- D is possibility of HIV infected worker C- D B- D is possibility of HIV infected worker C- D B- D is possibility of HIV infected worker C- D B- D is possibility of HIV infected worker
such as
would participate to the construction would participate to the construction would participate to the construction would participate to the construction
HIV/AIDS
works. works. works. works.
Labor
Environme
nt [Pre-Construction/ Construction] The [Pre-Construction/ Construction] The [Pre-Construction/ Construction] The [Pre-Construction/ Construction] The
construction works of the Project is in a construction works of the Project is in a construction works of the Project is in a construction works of the Project is in a
30 (Including B- D B- D B- D B- D B- D B- D B- D B- D
certain scale. So that it is required to certain scale. So that it is required to certain scale. So that it is required to certain scale. So that it is required to
Occupatio consider safety and work environment. consider safety and work environment. consider safety and work environment. consider safety and work environment.
nal
Safety)
[Construction] Construction related [Construction] Construction related [Construction] Construction related [Construction] Construction related
accidents by heavy equipment and accidents by heavy equipment and accidents by heavy equipment and accidents by heavy equipment and
transportation vehicles might occur. transportation vehicles might occur. transportation vehicles might occur. transportation vehicles might occur.
31 Accidents B- B- B- B- B- B- B- B- B- B- B- B- B- B- B- B-
[Operation] There is a possibility to [Operation] There is a possibility to [Operation] There is a possibility to [Operation] There is a possibility to
occur of accidents in the maintenance occur of accidents in the maintenance occur of accidents in the maintenance occur of accidents in the maintenance
road along the river. road along the river. road along the river. road along the river.
The scale of changes are large. However, The scale of changes are large. However, The scale of changes are large. However, The scale of changes are large. However,
the project will be conducted in the river the project will be conducted in the river the project will be conducted in the river the project will be conducted in the river
Global
32 D D D D area. The impact will not exceeding the D D D D area. The impact will not exceeding the D D D D area. The impact will not exceeding the D D D D area. The impact will not exceeding the
Warming
area. In addition, no impact for global area. In addition, no impact for global area. In addition, no impact for global area. In addition, no impact for global
warming is anticipated. warming is anticipated. warming is anticipated. warming is anticipated.
Responsible Org.:
Proponent
21) Existing Social Infrastructures and Services
Decreasing of During detailed design phase, measures Implementation: Design is
accessibility due to the to increase the accessibility to affected Proponent included to
existence of dike facilities will be considered. (maintenance) , detail
Consultant (Detailed design cost
design)
Responsible Org.:
Proponent
23) Misdistribution of Benefits and Damage
Misdistribution of benefit To make an opportunity of Implementation: To be
will be occurring between communication among stakeholders Proponent confirmed
developed and about the components, area and benefit
non-developed area. of the project, and build consensus Responsible Org.:
among stakeholders. Proponent ,
Consultant
(supervise)
24) Local Conflicts of Interest
Causes of this item is same as “23) Misdistribution of Benefits and Damage”.
25) Cultural Heritage
No items are tagged during operation phase
26) Landscape
Decreasing of visibility To exam the mitigation measures for the Implementation: Design is
due to the construction of Proponent included to
Report Communication
Report Directions
Report
Project Management
Consultant (PMC)
The Contractor
Construction monitoring Expert for Environmental and
Team Social Considerations
Instructions for
construction works Monitoring Team
Report Communication
(if any)
PMU: Project Management Unit
Department of Environment (Proponent)
(DOE) Manager for Environmental
Report
and Social Considerations Complains / Concerns
submission
Sub‐Contract for
monitoring (if any)
The roles for PMU, Consultant and Contractor are shown below:
PMU: The PMU is proponent of the Project. PMU also proponent for implementation of land
acquisition and EIA study based on the laws and regulations in Fiji before the construction.
Consultant: The Consultant formulates the project supervise group. The Consultant conducts
detailed design, and supervises for environmental and social monitoring based on the decision from the
Proponent (PMU).
Contractor: The Contractor conduct construction works. The contractor conduct neseesary
environmental monitoring based on the environmental monitoring plan.
Monitoring Frequency
Monitoring Frequency
Once per Month
Continues turbidity Monitoring Method Downstream of The Consultant
monitoring during Continues monitoring by turbidity construction Site conducts
construction in the meter measurement. The
river Proponent coordinates
Monitoring Frequency and informs to DOE.
Continues monitoring during
construction phase
Condition of Monitoring Method Construction Site The Contractor
maintenance of Condition of storage of equipment prepares the
construction and vehicle related oils at the maintenance record
equipment and construction site. (Storage, and submits the
Monitoring Frequency::
Record of original inventory
(once per before the
construction)
Record of after construction
inventory and draw the
vegetation map (twice per year)
Condition of Monitoring Method:: Construction Site The Consultant
changes and Visual monitoring of aquatic conducts
re-habitation of environment in the construction measurement. The
aquatic ecosystem site. Condition of rehabilitation Proponent coordinates
after the construction. and informs to DOE.
Monitoring Frequency::
Record of aquatic environment
(once per before the
construction)
Record of after construction
inventory and draw the
vegetation map (twice per year)
of leases and to facilitate leasing of lands, which are currently idle or unutilized, under terms and conditions
which are meant to be attractive to both the landowners and tenants. The decree provides for longer tenure
leases (up to 99 years) for agricultural and commercial development.
Table 22-28 Gaps between Land Acquisition and Resettlement Laws of Fiji and JICA
Guidelines
Gaps Between Laws of Implementation Policy
No. JICA Guidelines Laws of Fiji Fiji and JICA of Resettlement in the
Guidelines Project
3 People who must be General principles of FIJI Laws do not Measures to restore /
resettled involuntarily compensation for land prescribe measures to improve standard of
and people whose and assets are set out in restore/ improve living will be included
means of livelihood will the Constitution and standard of living. in the Abbreviated
be hindered or lost must State Acquisition of Resettlement Action
be sufficiently Land Act. Plan.
compensated and
supported, so that they
can improve or at least
restore their standard of
living, income
opportunities and
production levels to
5 Compensation and other State Acquisition of SALA states within 30 Measures on full
kinds of assistance must Land Act sets timing for days of notification, but payment of
be provided prior to payment of does not specifically compensation for
displacement. (JICA compensation. state before affected assets before
GL) displacement. DOL start of civil works on
Procedure provides for affected land will be
75% before construction included in the
and 25% after Abbreviated
construction. Resettlement Action
Plan.
Plan.
15 Particular attention must State Acquisition of No specific provisions Measures on
be paid to the needs of Land Act sets out the for preparing and consultations with
the vulnerable groups process of notification implementing based on displaced persons
among those displaced, of the land acquisition. meaningful including vulnerable
especially those below consultations with groups will be included
the poverty line, displaced person in the Land Acquisition
landless, elderly, women including the poor, the and Resettlement Policy
and children, ethnic landless, elderly, and Abbreviated
minorities etc. (WB women, and other Resettlement Action
OP4.12 Para.8) vulnerable groups Plan.
Table 22-29 Total population of the Nadi Town and Rural Areas, 2007 Census
Population House Hold (HH)
Population / HH
Person % HH %
Total 59,485 100.0% 12,858 100.0% 4.63
iTaukei 24,759 41.6% 4,542 35.3% 5.45
Indo-Fijian 31,557 53.1% 7,490 58.3% 4.21
Ethnicity
Rotuman 628 1.1% 146 1.1% 4.30
Other 2,541 4.3% 680 5.3% 3.74
Source: Fiji Bureau of Statistics, census 2007
Table 22-30 Number of Project Affected Units (PAUs) and Affected Persons (APs)
No. of Number of Family
Location Owner Structure Tenure
structures member
Yavusania 2 5
Paula Timber/ Iron Native
Village
Nadi Town Timber 1 -
Vinal Naidu Native
/Concrete (Commercial Property)
Saunaka Timber 1 9
Josateki Sovau Native
Village /Concrete
Nadi Back Timber 1 2
Razia Bibi Free Hold Land
Road /Concrete
Kulaia Timber 1 6 Free Hold Land
Area (sqm)
0 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000 1,600,000
River Widening
River Widening (NT Bridge)
Free Hold Land
River Widening (OQ Bridge)
State Land
Retarding Basin A (Dike)
Native Land
Retarding Basin A (Basin) Other (Existing River)
Retarding Basin B (Dike)
Retarding Basin B (Basin)
Surrounding Dike
Ring Dike
River Shortcut
Non-titled
displaced persons
(3) Loss of Loss of structures or Affected p1ersons / Displaced person will be provided PMU
structures / other resources communities and compensation at replacement cost; (LWRM)
property / groups (only having salvaged materials and assistance
community legal title to land) in finding an alternative site.
resources
Replacement or restoration of
community property and
resources.
(4) Need of Affected facilities Owners of facilities A Compensation at replacement PMU
improvements such as fences, wells, cost including the market (LWRM)
outdoor toilets, material, labor, and transportation
animals shed, etc. costs.
(5) Loss of Standing crops, trees, All affected persons Affected persons will be given PMU
crops and trees and other agricultural affected of their notice to harvest crops and trees (LWRM)
products to be legal rights/status before site clearance or removal
affected from required land. If displaced MOFF
person are not able to harvest,
they will be paid cash
compensation at replacement cost.
In case of perennial crops and
trees, the compensation will also
include loss of income for a
period until new crops or trees
produce an equivalent income.
Compensation will be provided
similarly for loss of fishing, etc.
(6) Loss of Land and access to Landowners, Compensation for direct income PMU
income and income generating lessees, displaced loss as applicable. Compensation (LWRM)
livelihood resources persons, right and/or income restoration
holder for resources assistance for indirect losses also
paid, particularly for vulnerable
groups, including women.
Compensation Responsible
Type of loss Application Entitled Persons
/Entitlements Organization
(7) Impact on Impacts on Vulnerable Vulnerable displaced persons will PMU
vulnerable particularly displaced persons receive additional or priority (LWRM)
groups vulnerable groups identified by social assistance.
survey
(8) Unforeseen All other matters Concerned To be determined as per principles PMU
impacts or displaced persons of the RAP and JICA policy. (LWRM)
losses
I. The PMU (Project Management Unit in Fiji Government) as the Implementing Agency will have
overall responsibility of the Project including safeguards. The LWRM responsibilities are (a)
identification of affected areas; (b) all community liaison; (c) budgetary provision; (d)
supervision of Social Impact Manager to be appointed by PMU.
II. PMU’s social impact manager will ensure that compensation is paid as required under the RAP. If
needed, a top-up resettlement budget will be made available to the safeguards unit to provide the
additional compensation/assistance (if any).
III. The Valuation Division, DOL will be responsible for (a) all initial valuations; (b) identification of
owners and leaseholders and (c) negotiations with land owners.
IV. The TLTB, which represents and negotiates on behalf of the mataqali land owners, will sign
agreements on their behalf and is responsible for securing the consent of mataqali members prior
to making such agreements.
V. Nadi Town Council and Nadi Provincial Council will facilitate discussions around land
acquisition, between the Project’s EIA and RAP specialists and communities.
relevant fees. Cheques are then processed and paid to the TLTB, based on estimated area, to be adjusted
after the final survey and completion of works.
Leasehold native land follows a similar process, where a field inspection is carried out, a Valuation Report
prepared and a Price Agreement executed. The Agreement is sent to the TLTB with relevant consent fees
for the Board to approve. If the lease is a registered one, then a caveat is lodged in the Titles Office, (as an
interim arrangement to prevent changes before the agreement can be finalized). The price paid for land will
sometimes need to be divided between lessees and owners.
In the case of freehold lands, the Valuation Division, DOL will prepare a Sale and Purchase Agreement and
negotiate the purchase.
When compensation has been paid, a Certificate of Transfer is prepared and sent for execution. The PMU is
then able to begin construction.
Following completion of the construction work, if the land used is found more than the original estimate
then compensation will be adjusted to the exact size of the land used.
PMU will recruit a social impact manager, and PMU will recruit design and supervision consultants, with
international and national environmental and social considerations specialists to implement the
environmental and social considerations tasks, as required by the RAP and Environmental Management and
Monitoring Plan. The environmental and social considerations related staff will work closely with the DOL,
DOH, MoSW and LWRM to ensure environmental and social considerations are implemented as set out in
the RAP for the Project.
JICA
Community / Stakeholders
Report
PMU: Project Management Unit
(Proponent)
Manager for Environmental
and Social Considerations
Complains / Concerns
After Preparation of certificate of land transfer,
Construction will be started
Evaluation Division,
Department of Lands
Negotiation Coordination
Update of RAP
Confirm land requirements based on detailed design of the river widening, Consulting
1 TBD
retarding basins and bridges. engineers
3 Determine type of affected land tenure (Native, leased, or freehold) DOL, TLTB TBD
Determine numbers in mataqali group, land owners and users affected, and
4 PMU, DOL, TLTB TBD
identify any vulnerable households
Cadastral survey of land if not previously done, and submission for land
7 PMU, DOL TBD
registration
9 Determine and mark areas for each land unit required DOL, PMU TBD
Conduct inventory of losses – land, trees, crops and provide valuation for
10 DOL, PMU TBD
compensation
RAP Implementation
14 Preparation of Sale and Purchase Agreement. Endorsed by TLTB. DOL, TLTB TBD
Monitoring
21 PMU submit progress report to JICA on implementation of the RAP PMU TBD
1. Compensation Cost: compensation for land, building etc. including temporary relocation and
replacement cost for public infrastructures;
2. Relocation Cost: cost for transportation, moving, tax and operational cost, placement fee for new
3. Restoring of Living Cost: budget for purchase of asset for alternative income source, occupational
training fee, assistance for farming management, job medication fee, assistance for small business
operation etc.;
4. Management Cost: labor cost, fuel and facility cost, technical assistance fee including training,
monitoring and evaluation fee. etc.; and
2) Relocation Cost
Cost for relocation is shown below.
Package-1 Package-2 Package-3
Unit Price Total
Item Main Works Description Unit River Widening Retarding Basin A, B Ring Dike
(FJD)
Quantity Cost (FJD) Cost (JPY) Quantity Cost (FJD) Cost (JPY) Quantity Cost (FJD) Cost (JPY) Cost (FJD) Cost (JPY)
Ⅲ . Co m pe ns a ti on C o st
Q ua nt i ty
House Relocation Concrete Building nos 90,636.0 - - - - - - - - - - -
Affected House Wooden Building nos 61,292.0 6.0 367,752 20,042,484 11 674,212 36,744,554 17 1,041,964 56,787,038 2,083,928 113,574,076
Tin Shack nos 36,396.0 - - - - - - - - - - -
Consultation, participation, and No. of consultation and participation programs held with various
grievance resolution stakeholders
No. of field visits by PMU
Land, economic trees & crops No. of households receiving agreed compensation for land, trees
and crops
Impact Household earning capacity Employment status of households having a formal job
indicators
Employment status of households being self-employed
Special assistance to women No. of women engaged as waged workers by the Project
Type of Project-related skills women received.
Average wage of women employed on Project compared to that of
men.
The examination done by JICA is based on the evaluation which the frequency of flood in
2015 is 1/50. Do you conduct the calculation for the 1/100, 1/25 flood? Can we review the
draft repot? (Civil Engineer)
How many years are needed for completion of the Project? (Housing Authority)
flooding.
of flood control facilities is not carried out sufficiently. The maintenance work of flood control facilities to
be constructed by the Project is inevitable; therefore, yearly budget has to be secured for continuous
maintenance work.
(10) Establishment of flood control master plan for overall Fiji and implementation
The flood control master plan in the Nadi River basin was established in this Study; however, there are 4
large river basins in Viti Levu island in addition to Nadi River, which are Rewa River, Navua River,
Sigatoka River and Ba River, without master plans. Master plans for these rivers is to be established and the
implementation of flood control facilities of it should be implemented step by step.
NAMOTOMOTO
Village
NAREWA Village
Figure 23-1 Drainage system of rainfall water in the central area of Nadi town
Council, LWRM, Western Drainage Board, National Disaster Management Committee, Nadi Rural Local
Authority.
In the plan, present situation and issues were studied, and the long-term, and short- and medium-term plans
were recommended to solve the issues (refer to Table23-1). However, the plan was studied without
demarcation of inland water and river water, without hydraulic analysis and verification, and scientific
ground.
In addition to the above, the plan included the diversion channel and short cut recommended by JICA study
carried out from 1996–1998, titled as [The study on watershed management and flood control for the four
major vitilevu rivers](herein after referred to as Development Study1998)
As the progress of Nadi Town Drainage Plan, although the retention dams are constructed by LWRM
separately, the other facilities are not confirmed remarkable progress in the investigation carried out by
JICA study team in 2016.
Table 23-1 Contents of the 2000 Nadi Town Drainage Plan
Period Contents of Plan
Short and medium term plan Widening drainage channel and review of the alignment
Long term plan Construction of retention dam, embankment, diversion channel, short cut and so on
Source:Nadi Town Drainage Plan (2000)
Accurate and comprehensive information on frequency of inundation, risk of loss of human life, capacity
and condition of facilities should be presented by the related agencies using hazard map or other
appropriate means. The measures reducing the disaster risk should be promoted by sharing disaster risk
information among agencies.
(2) Basic concept of implementation of adaptive measures
On the other hand, the increase of impact and risk of frequent and severe disasters of flood, sedimentation,
high tide and drought by climate change has become a major concern in recent years. The importance of
adaptive measures to the adverse effect of the climate change as well as mitigation measures is pointed out
in the Conference of the Parties to the United Nations Framework Convention on Climate Change (COP).
The measures were proposed considering change of future socioeconomic situation and uncertainty of risk
such as climate change and movement of population, economy, and technology level and so on. In order to
mitigate such disaster risk, it is important that adaptive measures are to be applied.
When adaptive measures are implemented as risk mitigation measures, the measures have to be promoted
based on the concept listed below. And the measures have o be implemented adaptively and verified and
reviewed based on the knowledge and experience of not only upgrading the basic technology on the
hydrology, which is based on scientific ground, but also promoting continuous monitoring of climate
change, prediction, investigation and research, technological development of climate change.
The basic concept of implementation of adaptive measures is as follows:
・Adaptive management based on uncertainty
・Coping with existing phenomena
・Consideration of impact on future
・Comprehensive structural and non-structural measures
・Consideration of climate change for each project plan
・Symbiosis with nature and conformity with environment
・Consideration of regional characteristics and promotion of activity in each level
1) Adaptive management based on uncertainty
The prediction of future impact of climate change (timing of occurrence, place, and extent) is accompanied
by uncertainty. When the adaptive measures are to be promoted, adaptive management has to be applied.
Moreover, appropriate measures have to be selected when necessary with continuous monitoring of climate
change, progress of climate change, up-to-date climate data, socio-economic reginal variation, effect of the
existing and new risk reduction measures.
2) Coping with existing phenomena at present
The influence of climate change has not been observed clearly in Nadi River basin, but if the climate
change will be observed and becomes obvious by observation and monitoring, the measures in the Priority
Project in this Study is basically to be adopted and promoted.
3) Consideration of impact on future
Although the extent of impact and time of occurrence of climate change is uncertain, the phenomena at
present may become worse and cause the large disaster in progress of climate change. Therefore, the study
on adaptive measures for various phenomena is to be carried out taking into consideration the change of the
frequency of occurrence of phenomena.
4) Structural and non-structural aspects of measures
The adaptive measures include structural measures such as construction of facilities and non-structural
measures such as early flood warning, town and land use planning based on the disaster risk. The
comprehensive measures have to be implemented immediately by appropriately combining the structural
and non-structural measures.
5) Consideration of adaptive measures and disaster prevention of each project plan
In order to implement the adaptive measures effectively and efficiently, the concept of adaptation to the
impact of climate change and disaster prevention should be involved in each project plan. If necessary,
concept of adaptive measures and disaster prevention should be considered in the design of facilities,
order to eliminate the inundation damage in Nadi town, rainfall water drainage system should be facilitated;
moreover, an integrated operation of the river and rainfall drainage systems is necessary for inundation
caused by river water and rainfall water. Therefore, a system connecting river and rainfall water drainage
systems is to be established to strengthen their function, and rainfall water reservoirs are to be promoted.
2) Disaster reduction measures for extraordinary floods
a) Enhancement hydrological observation network
The hydrological observation network is to be enhanced not only for rainfall and river water level but also
for inland water level and tide level (high tide) by improvement of observation equipment and promotion of
flood forecasting technique. Assistance to the related organizations and support system should be enhanced
so that the appropriate evacuation recommendation is possible in extraordinary flood situations, and in
normal time the detail information on disaster risk of dangerous location is to be supplied.
b) Evaluation of disaster risk for various external forces
The Master Plan for the external force of the maximum flood recorded in the past was established in this
Study. However, in the long-term, after continuous hydrological observation and monitoring is carried out,
it is necessary to estimate the external force of not only the recorded maximum flood, but also for that of
extraordinary floods that may result from exceptionally different rainfall pattern. And the occurrence
frequency of inundation above floor level and risk of loss of human life, capacity and conditions of
facilities are to be evaluated.
c) Structural inspection of Vaturu Dam
As for the Vaturu Dam located in the most upstream of Nadi River, the study is to be carried out on the
safety such as structural damage and its influence in case the external force exceeds the design capacity of
the dam, and counter measures are to be implemented, if necessary.
d) Restraining inundation area collaborated to town and regional planning
The embankment and rising of road in Back Road is examined to restrain development of the inundation
area collaborated to town and regional planning and respond to extraordinary flood.
e) Drainage of inundation water
It is very important in the large scale flood disaster to drain the inundation water as soon as possible to
prevent the expansion of inundation area, and for early restoration and rehabilitation. Therefore, the
drainage plan is to be examined beforehand and all necessary preparation regarding drainage water gate,
pumping station, secure of access road to supply fuel, reserve power, stock fuel and so on is to be
promoted.
f) Enhancement of emergency evacuation system
The number of the dead and isolated persons including travelers is estimated in case of large scale flood
disaster, based on this assumed damage, the timeline (action plan in time series) will be prepared in
cooperation with related organizations so that the evacuation, first aid service, emergency transportation
will be possible. The emergency evacuation system should include allocating boat, preparing evacuation
place, securing evacuation route, preparing stock of supplies and so on.
g) Presentation of understandable information to urge evacuation
Simple and easily understandable information on the approaching danger, such as flooding and high tide,
should be provided to the public.
Moreover, hazard map which is can be easily understood by residents and travelers has to be prepared, and
the installation of notice board in the town, on which the estimated inundation depth and the elevation at
the place, direction of evacuation, name and distance to the evacuation place are indicated, has to be
promoted.
Component
① River Widening
② Retarding Basin A, B
③ Surrounding Dike
④ Ring Dike
⑤ Shortcut of tributaries
⑥ Rebuilding of Bridge (Nadi town bridge)
Malakua River
⑦ Rebuilding of Bridge (Old Queens Road bridge)
A
【Case2】:River Widening in the middle stream
from 5.75km to 18.00km incl. rebuilding of 2
bridges and Ring Dike B
2.00 40.0
20.00 20.0
1.50 30.0
1.00 20.0
10.00 10.0
0.50 10.0
(m)
0.60 0.60
Depth is less than 30cm
0.40 0.40
0.20 0.20
0.00 0.00
1/50 1/30 1/20 1/10 1/5 1/3 1/2 1/50 1/30 1/20 1/10 1/5 1/3 1/2
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Legend Legend
Less than 0.5m Less than 0.5m
0.5m - less than 1.0m 0.5m - less than 1.0m
1.0m - less than 2.0m 1.0m - less than 2.0m
2.0m - less than 3.0m 2.0m - less than 3.0m
3.0m - less than 5.0m 3.0m - less than 5.0m
More than 5.0m More than 5.0m
24-4
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Legend Legend
Less than 0.5m Less than 0.5m
0.5m - less than 1.0m 0.5m - less than 1.0m
1.0m - less than 2.0m 1.0m - less than 2.0m
2.0m - less than 3.0m 2.0m - less than 3.0m
3.0m - less than 5.0m 3.0m - less than 5.0m
More than 5.0m More than 5.0m
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Mitigation Ratio(%)
3.50 Mitigation Ratio (Inundation Area) 70.0
Inundation Area (km2)
2.0m - less than 3.0m downstream area of Back Road Bridge since
3.0m - less than 5.0m 3.00 60.0 embankment of retarding basin along the
More than 5.0m 2.50 50.0 Nadi River confine flood water in the river
2.00 40.0 channel which widely spread before.
Important Protected Area 1.50 30.0
1.00 20.0 In case that larger scale of flood occurs than
0.50 10.0 20-year return period, Case1 is effective to
0.00 0.0 mitigate inundation and 10% of inundation
1/50 1/30 1/20 1/10 1/5 1/3 1/2 area is reduced.
Probability scale Effect:small
Case2: River Widening L=13km form 5.75 to 18.75km incl. rebuilding 2 bridges and Ring Dike
50-year probability 30-year probability
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Legend Legend
Less than 0.5m Less than 0.5m
0.5m - less than 1.0m 0.5m - less than 1.0m
1.0m - less than 2.0m 1.0m - less than 2.0m
2.0m - less than 3.0m 2.0m - less than 3.0m
3.0m - less than 5.0m 3.0m - less than 5.0m
More than 5.0m More than 5.0m
Figure 24-8 Flood Analysis Result (Case2: River Widening L=13km form 5.75 to 18.75km incl. rebuilding 2 bridges and Ring Dike)(1/2)
Case2: River Widening L=13km form 5.75 to 18.75km incl. rebuilding 2 bridges and Ring Dike
5-year probability 3-year probability
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Mitigation Ratio(%)
1.0m - less than 2.0m 3.50 70.0
2.0m - less than 3.0m
flood (50-year design return period).
3.00 60.0
3.0m - less than 5.0m 2.50 50.0 Even in small scale flood, effectiveness is
More than 5.0m 2.00 40.0 high and about 80% of inundation area is
1.50 30.0 reduced in case of smaller scale flood than
Important Protected Area 1.00 20.0 5-year return period scale.
0.50 10.0
0.00 0.0 Average inundation depth is reduced to 30
1/50 1/30 1/20 1/10 1/5 1/3 1/2 cm or less.
Probability scale
Figure 24-9 Flood Analysis Result (Case2: River Widening L=13km form 5.75 to 18.75km incl. rebuilding 2 bridges and Ring Dike)(2/2)
Case3: River Widening L=8.25km form 5.75 to 14.0km incl. rebuilding 1 bridges and Ring Dike
50-year probability 30-year probability
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Legend Legend
Less than 0.5m Less than 0.5m
0.5m - less than 1.0m 0.5m - less than 1.0m
1.0m - less than 2.0m 1.0m - less than 2.0m
2.0m - less than 3.0m 2.0m - less than 3.0m
3.0m - less than 5.0m 3.0m - less than 5.0m
More than 5.0m More than 5.0m
Figure 24-10 Flood Analysis Result (Case3: River Widening L=8.25km form 5.75 to 14.0km incl. rebuilding 1 bridges and Ring Dike)(1/2)
Case3: River Widening L=8.25km form 5.75 to 14.0km incl. rebuilding 1 bridges and Ring Dike
5-year probability 3-year probability
Legend
Legend Less than 0.5m
Less than 0.5m 0.5m - less than 1.0m
0.5m - less than 1.0m 1.0m - less than 2.0m
1.0m - less than 2.0m 2.0m - less than 3.0m
2.0m - less than 3.0m 3.0m - less than 5.0m
3.0m - less than 5.0m More than 5.0m
More than 5.0m
Important Protected Area
Important Protected Area
Figure 24-11 Flood Analysis Result (Case3: River Widening L=8.25km form 5.75 to 14.0km incl. rebuilding 1 bridges and Ring Dike)(2/2)
Case3: River Widening L=8.25km form 5.75 to 14.0km incl. rebuilding 1 bridges and Ring Dike
Amount of damage (100 million YEN) Expected
Sectional Amount of amount of
Average average average annual average annual
③Damage Sectional
annual damage damage damage
①Without project ②With project reduction probability
excess probability (100 million (100 million reduction
(①-②)
YEN) YEN) (100 million
YEN)
24.3 Summary
Summary of Phasing is as mentioned in Table 24-5 with result of full components of the Priority Project.
In addition, summary of flood analysis of each phase is as shown in Figure 24-12 to Figure 24-14.
1) 1/50 Design Return Period is a historical maximum flood scale (2012 Flood Scale).
2) Land Acquisition Cost is reviewed by MOL, 1F$=¥54.5, 1USD=¥118.3, 1USD=2.17F$
Figure 24-12 Flood Analysis Result by Full Components of the Priority Project
Eliminating fatal
inundations (more than
300cm depth),
Decreasing inundation
area by 50%,
Decreasing average
Legend
inundation depth to about
Less than 0.5m first floor level (more than
0.5m - less than 1.0m
1.0m - less than 2.0m
30cm)
2.0m - less than 3.0m
3.0m - less than 5.0m in Important Protected Area.
More than 5.0m
Figure 24-13 Flood Analysis Result by Case2: River Widening L=13km form 5.75 to 18.75km
incl. rebuilding 2 bridges and Ring Dike
Eliminating fatal
inundations (more than
300cm depth),
Decreasing inundation
area by more than 30%
Legend
Decreasing average
Less than 0.5m inundation depth by 50%,
0.5m - less than 1.0m
1.0m - less than 2.0m in Important Protected Area.
2.0m - less than 3.0m
3.0m - less than 5.0m
More than 5.0m
Figure 24-14 Flood Analysis Result by River Widening L=8.25km form 5.75 to 14.0km incl.
rebuilding 1 bridges and Ring Dike