Professional Documents
Culture Documents
Botswana North South
Botswana North South
Botswana North South
Dikgatlhong dam
PS1.2
2
1A
k
Lin
Letsibogo dam
PS1.1
Node 1.1 r
EMERGING ECONOMY
se rive
Motlout
Botswana C
Selebi-Phikwe
1
T1 2
A2
Lin
k
1A
A
1
2
C-2
Moralane Pumping Station Moralane BPT
NS
gion, Botswana is strongly reliant on its 2 BP k 1 No
Lin 2.1
2A T1 B1 de
PS
k
FT
A1
Lin 2A
1
2A
k No
2
2 Lin de
km 50
1A
Dikalate BPT
mining activities, especially of diamonds,
2
BP
T2
A1
No
.1
1
Lin
2B
.1
-2
k
Palapye SC
Lin
N
wellfield
Palapye km 100
W 3 river
k2
ane
Palapye WTW
C1
er
riv
Lin
PS
k2
.1
4 de Lim
Palapye Pumping Station PS 2B Lotsane
NS
3.1 river
No
A2
de
3
A1
Lin
k3
Lin
FT
3A
2
B1
Lin
k3
Lin
and WTW
C-2
SR3B Node 3B
r
e
riv
Pa
we lla R
po
llfi oad ha
Lim
la
eld km 200 py
C2
e riv
k3
Le
er
C1
ph
Lin
ala
No
k3
economic growth. de
la
Lin
3C
riv
er
No
de 3D
2
Palla Rd Injection
Serome river k 1
3D Lin 3D
k
E2
Lin
MEP emergency connection
k3
E1
Lin 3E
Moko
k3 2 er
Mmamabula Energy
k3
PS F2 riv
4.2
Serorome Pumping Station po
lo riv
7
BP
Lin T3E Project Bonwapitse river Lim
er
PS k 3 1 N
4.1 F1 od
A2
e3
No
k4
E
A1
FT de
4A
k4
Lin
8
No
de
4A
1
4B
Link
Link
(Mauruts
riv
well samahe
an
tla
tw
ba
field ) Nod
go
s ri
N
2
CA
e 4B
ve
1
r
k4
CA
Lin
k4
river
Lin
popo
Lim
km 300
Civil Engineering November 2012 49
FT4B
A2
9
South Africa
Link 4CB2
10 Node 4BA
Bokaa dam Link 4CB1
Cro
Node 4C
.3
Bokaa Discharge
co
km 350
dil
D2
e
NS
D1
a
riv
k4
ab
othl
er
k4
Lin
sem r C
Met
Lin
rive
Mmamashia Reservoir
work packages of the NSC
r
Mmamashia WTW
rive
W Node 4D
SR4D PS5.1
ico
Mmamashia PS5.2 11
Mar
Pumping Node 5
Station
Gaborone
LEGEND
Node 6 Power required
PS6.1 Node 6A NSC 1 NSC 2 C Operational control centre W Water Treatment Works Refer to application for reference numbers
Gaborone dam Gaborone Discharge
responsibility for water resource Shashe Dams which feed on three tribu- In order to protect and control
planning, control, legislation and taries of the Limpopo River in central access to the NSC, the MMEWR has
regulation, while the Water Utility Botswana – the Motloutse, Shashe resolved to acquire and register rights
Corporation is participating as op- and Tati Rivers. Construction of the to the NSC corridor from Dikgatlhong
erator and key technical partner. Dikgatlhong Dam also commenced, Dam to Mmamashia. A single cor-
The second phase of the NSC (NSC-2), along with its connection to the first- ridor, varying between 50 and 70 m in
of which the planning stage commenced phase break pressure tank number 1. width, will be acquired to accommodate
in 2007, is aimed at completing a water This dam is at present nearing comple- each of the three phases, the fibre-
transfer strategy that feeds on various tion and should be substantially filled optic communication backbone and
dams, existing or newly emerging from by the time the NSC is commissioned. the maintenance road. Environmental
the first phase (NSC-1, completed in Upgrading of various aspects of phase investigations have been undertaken
1999). Second-phase construction is one is still to be commissioned. for the primary corridor, and a manage-
set to commence in the second quarter Pumping stations are located at ment entity is in place. Further investi-
of 2012, with Bigen Africa acting Letsibogo, Moralane and Palapye (with gation and authorisations were pursued
as the MMEWR representative. another envisaged for Seroroue) and on bedding and gravel-wearing course
In the mid-1990s, the Botswana deliver from 1 175 ℓ/s to 2 300 ℓ/s, with materials along the route of the second
government adopted a national water operational capacity of between 2 MW phase. Borrow pit leases and mining
supply plan which identified the need and 3 MW respectively. The fi rst-phase licences are also a requirement.
for the NSC to connect Letsibogo pipe varies in diameter from 1 400 ND In phase two, the direct water transfer
Dam on the Motloutse River to the to 1 100 ND and was constructed from route will run primarily alongside north-
Mmamashia water treatment works in a combination of materials, including south traffic route A1 and pass the de-
northern Gaborone, and to supply the GRP and steel. Further pipes will be mand nodes of Palapye, Mahalapye and
Palapye and Mahalapye water treatment constructed from either steel or ductile Mmamabula, where raw water is treated,
works. Mmamashia is also supplied iron, while consistency in other principal en route to Mmamashia in northern
from the smaller Bokaa Dam, directly plant and material selections, including Gaborone. National electricity generation
north of it. The first phase included the the key requirement of local maintain- occurs at Morupule within the Palapye
importation of raw water into Gaborone ability, is required by the government. complex, and potential export generation
from the Moletedi Dam in the North Communication and control signals can be established in the future on the
West province of South Africa, and will mainly be by fibre-optic cable with Mmamabula coal field between Mahalapye
the construction of the Letsibogo and backup by wireless radio data link. and Gaborone. Water reclamation from
Source:
http://www.saice.org.za/downloads/monthly_publications/2012/2012-Civil-
Engineering-November/#/0
www.sappma.co.za
Southern African Plastic Pipe Manufacturers Association