Quantity Estimate
Section-1 : All Civil works
S.No. Description of works No. Length Breadth Height Quantity Unit Remarks
1 Lintel Above Compound Wall
1 21.67 21.670 ru ft
1 46.50 46.500
Total 68.170
2 PLASTERING WORKS sq ft
2.1 Plaster through cirter 1 1.33 11.00 14.630
1 35.00 1.67 58.450
1 18.00 11.00 198.000
6 SOILING sq ft
Around Manhole 1 8.50 3.00 25.500
Around Toilet 1 6.00 7.50 45.000
Aound Main Gate 1 19.50 3.50 68.250
Total 138.750
7 PCC
Around Manhole 1 8.50 6.00 51.000
Around Toilet 1 6.00 7.50 45.000
Total 96.000
8 RCC
Around main gate 1 19.50 3.50 68.250
Abstract Of Cost
Rate Amount
Item No Description of Work Unit Quantity Remarks
(Npr) (Npr)
1 Soiling sq ft 138.750 10.00 1,387.50
2 PCC sq ft 96.00 35.00 3,360.00
3 RCC sq ft 68.25 45.00 3,071.25
4 Lintel Work running ft 68.17 45.00 3,067.65
5 Brick Work 9" sq ft 156.62 28.00 4,385.36
6 Brick Work 4" sq ft 341.87 25.00 8,546.75
7 Plastering Work sq ft 1650.95 20.00 33,019.00
8 Kora Masino sq ft 355.23 22.00 7,815.06
Total 64,652.57
Total Labours Rate Amount
Item No Mistri Labor Remarks
Needed (Npr) (Npr)
1 For Plumber 2 2
For Breaking of
2 1 2
Toilet
Deposit of Soil over
3 1 1
Compound
4 5.00 11,000.00
GRAND TOTAL 75,652.57