Professional Documents
Culture Documents
Commissioning and Qualification - An Overview: Service Delivery Hubs
Commissioning and Qualification - An Overview: Service Delivery Hubs
Commissioning and Qualification - An Overview: Service Delivery Hubs
Call
Brad Henry
Commissioning
Commissioning is a systematic approach to the start-up and turnover of facilities, systems, and
equipment to end-users and ensuring that user requirements and design specifications are met
(International Society of Pharmaceutical Engineering [ISPE}, 2007). Activities within this phase may
include design reviews, factory acceptance testing, installation verification, and functional testing.
Summary reports are generated at the conclusion of commissioning activities and include an
overview of the results and any deviations encountered during testing. Commissioning, if well
documented, may be leveraged to reduce or eliminate qualification testing.
Qualification
As defined in the FDA Process Validation Guidance, qualification refers to the activities undertaken
to demonstrate that utilities and equipment are suitable for their intended use and perform properly.
As discussed previously there are multiple approaches that demonstrate suitability for intended use.
Under an ISPE Baseline Guide 5 approach, systems and equipment determined to have a
direct impact on product quality are typically qualified using Installation and Operational
Qualifications. While systems with an indirect impact on product quality may only be
commissioned.
Under an ASTM E2500 approach, testing typically considered as part of IQ/OQ is referred to
as verification. ASTM E2500 emphasizes utilizing a science-and-risk-based approach in order
to focus the verification activities on critical aspects of the system.
Commissioning activities, if performed to cGMP standards may be leveraged during the Qualification
phase as they verified the system is suitable for its intended use and demonstrated proper
functionality.
Acceptance
Multi-functional teams, which should include the Quality Unit for Direct Impact/Quality Critical
systems, provide final approval of qualification or testing documentation and deem the system or
equipment fit for its intended use. At this stage, a declarative statement is made on the disposition of
the system or equipment and the release for operational use. Summary reports are generated at the
conclusion of qualification and include an overview of the results and any deviations encountered
during testing.
Systems that have a direct impact to product quality are accepted by the organizations quality
unit among other SMEs (International Society of Pharmaceutical Engineering [ISPE}, 2007).
Systems with critical aspects are accepted by the organizations quality unit among other SMEs
(ASTM International, 2013)
As described in (USFDA, 2011, p. 11): Process Performance Qualification (PPQ) combines the
actual facility, utilities, equipment (each now qualified), and the trained personnel with the
commercial manufacturing process, control procedures, and components to produce commercial
batches A successful PPQ will confirm the process design and demonstrate that the commercial
manufacturing process performs as expected . PPQ is documented through an approved testing
protocol that specifies the manufacturing conditions, controls, testing, and expected outcomes .
The PPQ lots should be manufactured under normal conditions by the personnel routinely expected
to perform each step of each unit operation in the process. Normal operating conditions should
include the utility systems (e.g., air handling and water purification), material, personnel,
environment, and manufacturing procedures. PPQ must be successfully completed before product
can be distributed commercially (USFDA, 2011, p. 13). During PPQ, process data is collected and
evaluated to ensure the manufacturing process performs as expected.
On completion of testing, a summary report is created that includes analysis of data collected, a
discussion of any manufacturing nonconformance, description of corrective actions, any changes to
existing procedures and controls, and a conclusion stating whether or not the process meets
established acceptance criteria.
Acceptance of this report by a multi-functional team including Engineering, Area Manager, Quality
Assurance, and Quality Control releases lots for distribution, provides approval of the process, and
deems the process ready for Stage 3 – Continued Process Verification. Under stage 3, the
organization is responsible to establish one or more systems that will monitor the manufacturing
process to detect unplanned departures from the process. As defined by USFDA (2011, p. 14):
An ongoing program to collect and analyze product and process data that relate to product quality
must be established (§ 211.180(e)). The data collected should include relevant process trends and
quality of incoming materials or components, in-process material, and finished products. The data
should be statistically trended and reviewed by trained personnel. The information collected should
verify that the quality attributes are being appropriately controlled throughout the process.
Performance Validation has assisted large and small pharmaceutical manufactures in providing turn-
key or staff augmentation support for commissioning, qualification, and validation projects. We have
successfully worked with companies that have implemented an ISPE Baseline Guide methodology,
an ASTM E2500 methodology, and various combinations to achieve a compliant solution. For
services offered please see the Commissioning & Qualification page of our website. For
information on projects that we have successfully completed please see the Projects
Summaries page of our website. Our goal is to provide our customers with peace of mind
concerning their commissioning, qualification, and validation projects.
Please use our contact us page if you have a question on Commissioning, Qualification, and
Validation or would like further information on Performance Validation’s capabilities.
References:
ASTM International. (2013). E2500-13: Standard guide for specification, design, and verification of
pharmaceutical and biopharmaceutical manufacturing systems and equipment. West
Conshohocken, PA: ASTM International.
USFDA. (2011). Guidance for Industry. Process Validation: General Principles and Practices.
Rockville, MD, USA: Government Printing Office.
PREVIOUS NEXT
CONTACT US