OVERALL PROGRESS CALIBRATION CV / XV

No Valve Type Area BOQ Tested Remaining

1 Control Valve Globe BTX 185 135 50

2 Control Valve Globe BD 130 110 20

3 Butterfly BD/BTX 29 29 0

4 On Off Ball Valve BD/BTX 91 78 13

TOTAL 435 352 83

DAILY PROGRESS CALIBRATION CV / XV


No Day Date Result Remarks
1 Tuesday 27-Feb 23
2 Wednesday 28-Feb 38
3 Thursday 29-Feb 35
4 Friday 1-Mar 13
5 Saturday 2-Mar 16
6 Sunday 3-Mar 0 Holiday
7 Monday 4-Mar 28
8 Tuesday 5-Mar 11
9 Wednesday 6-Mar 17
10 Thursday 7-Mar 4
11 Friday 8-Mar 7
12 Saturday 9-Mar 0 Rain all day
13 Sunday 10-Mar 0 Holiday
14 Monday 11-Mar 0 Holiday
15 Tuesday 12-Mar 25
16 Wednesday 13-Mar 22
17 Thursday 14-Mar 20
18 Friday 15-Mar 8
19 Saturday 16-Mar 11
20 Sunday 17-Mar 0 Holiday
21 Monday 18-Mar 13
22 Tuesday 19-Mar 9
23 Wednesday 20-Mar 8
24 Thursday 21-Mar 10
25 Friday 22-Mar 13
26 Saturday 23-Mar 8
27 Sunday 24-Mar 0 Holiday
28 Monday 25-Mar 7
29 Tuesday 26-Mar 6
30 Wednesday 27-Mar 0
31 Thursday 28-Mar 0
32 Friday 29-Mar 0
33 Saturday 30-Mar 0
Progress

73%

85%

100%

86%

81%