2. Grumpy John Products makes pizza ovens for commercial use. CEO Grumpy John is contemplating
producing smaller ovens for high school and college kitchens. The activities necessary to build an
experimental model and related data are given in the following table: (5 items x 5 points)
CRASH
NORMAL CRASH TIME NORMAL IMMEDIATE
ACTIVITY COST
TIME (WEEKS) (WEEKS) COST (PHP) PREDECESSOR(S)
(PHP)
A 3 2 1,000 1,600 -
B 2 1 2,000 2,700 -
C 1 1 300 300 -
D 7 3 1,300 1,600 A
E 6 3 850 1,000 B
F 2 1 4,000 5,000 C
G 4 2 1,500 2,000 D, E
H 5 3 2,000 3,000 F, G
f. What activities should you crash if James Kimpel wants to reduce the project time to 15
weeks? -ACTIVITY C
3. A renovation of the gift shop at Orlando Amway Center has six (6) activities (in hours). For the
following estimates of a, m, and b, calculate the a) expected time and the b) standard deviation
for each activity: (2 items x 5 points)
CRITERIA POINTS
Complete solution with correct answer, layout/design, and proportion are correctly laid 5
out/sketched.
Last two (2) major steps of the solution and layout/design are incorrect. 4
Half of the solution and layout/design is correct. 3
First two (2) major steps of the solution and layout/design are correct. 2
First major step of the solution and layout/design are correct. 1
REFERENCES
Gupta, S., & Starr, M. (2014). Production and Operations Management Systems. CRC Press.
Heizer, J., Render, B., & Munson, C. (2020). Operations Management: Sustainability and Supply Chain
Management (13th ed.). Pearson Education Inc.
Krajewski, L. J., Malhotra, M. K., & Ritzman, L. P. (2018). Operations Management: Processes and Supply
Chains (12th ed.). Pearson Education Limited.
Schroeder, R., & Goldstein, S. M. (2020). Operations Management in the Supply Chain: Decisions and