Rabigh4 - 0 2IWP - 0 2daily - 0 2 - 0 2report 14-11-2023

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 21

Date:

NO Area

Intake water pump


1
house

2 Workshop

3 Electric building
4 Marine works

5 IWP Water tank area

WTTCO Water tank


6
area

7 PV

8 Others
9 Others

Total
Activities performed today

1.Intake punp house excavation


2.Intake dewatering pump installation

1.construction wast removal work


1.Marine excavation
2.Marine site leveling for Pond discharge
line
3.The GRP pipeline from Settlement
pond to marine
4.GRP pipe butt entanglement
5.Marine cause way backfilling started
1.3#tank Soil loading
2.4#Tank Excavation

1.WTTCO Water tank 6 excavation


2. WTTCO tank 8 soil remove

PV area leveling work ongoing

1.all site road leveling and compaction


work
2.Rabigh 3 main road kerbstone end
termination work
Camp and office Temporary facilities
work, HSE team
inspection,Security,watchmen, Site
housekeeping etc

Total
Rabigh4 I

Activities tomorrow plan

1.Intake punp house excavation


2.Intake dewatering pump installation

1. Column base waterproofing work


1.Marine excavation
2.Marine site leveling for Pond discharge
line
3.The GRP pipeline from Settlement
pond to marine
4.GRP pipe butt entanglement
5.Marine cause way backfilling work
1.3#tank Soil loading
2.4#Tank Excavation

1.WTTCO Water tank 6 excavation


2WTTCO tank 7 PLT
3 WTTCO tank 7 soil remove.

PV area leveling work ongoing


Camp and office Temporary facilities
work, HSE team
inspection,Security,watchmen, Site
housekeeping etc
Rabigh4 IWP- Daily report

11/14/2023

Manpower
Dump Excavato
Trailer
Truck r

18 2 3

0
20 2 4

58 1 2 1

13 4 2

3 1

3
74

197 9 12 1
Machinery
Quantity

Loader Forklift Crane


1 1

1
1 1

3 1 2
Machinery
Quantity
Fire fighting
Roller Grader
truck
1

1 1
1

1 1 2
Water
JCB Bobcat
Tanker
1

1 1
1 1

1 2 2