Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

CONFORMED

TABLE OF CONTENTS (con’t)

DIVISION 6 - WOOD AND PLASTICS (NOT USED)

DIVISION 7 - THERMAL AND MOISTURE PROTECTION (NOT USED)

DIVISION 8 - DOORS AND WINDOWS (NOT USED)

DIVISION 9 - FINISHES
09800 Protective Coating............................................................................... 09800-1
09905 Abrasive Blasting ................................................................................ 09905-1
09930 Concrete Surface Rehabilitation and Protective Lining ........................ 09930-1

DIVISION 10 - SPECIALTIES (NOT USED)

DIVISION 11 - EQUIPMENT
11000 Equipment General Provisions ............................................................ 11000-1
11204 Weir Plates, Scum Baffles and Supports............................................. 11204-1
11232 Gravity Thickeners .............................................................................. 11232-1

DIVISION 12 - FURNISHINGS (NOT USED)

DIVISION 13 - SPECIAL CONSTRUCTION


13122 Aluminum Flat Cover System Work..................................................... 13122-1

DIVISION 14 - CONVEYING SYSTEMS (NOT USED)

DIVISION 15 - MECHANICAL
15025 Steel Pipe ........................................................................................... 15025-1
15209 Knife Gate Valves ............................................................................... 15209-1
15254 Slide Gates ......................................................................................... 15254-1

DIVISION 16 - ELECTRICAL
16010 General Electric Information ................................................................ 16010-1
16015 Short-Circuit Coord. Study and Arc Flash Hazard Analysis ................. 16015-1
16070 Hangers and Supports for Electrical Systems ..................................... 16070-1
16075 Electrical Identification ........................................................................ 16075-1
16120 Wire and Cable ................................................................................... 16120-1
16130 Boxes and Fittings .............................................................................. 16130-1
16133 Raceway and Fittings .......................................................................... 16133-1
16140 Wiring Devices .................................................................................... 16140-1
16150 Termination and Splicing..................................................................... 16150-1
16225 Motor Control Centers (MCC) ............................................................. 16225-1
16414 Disconnect Switches ........................................................................... 16414-1
16420 Temporary Starters and Controllers .................................................... 16420-1
16500 Lighting ............................................................................................... 16500-1
16990 Testing and Commissioning ................................................................ 16990-1

DIVISION 17 - INSTRUMENTATION
17100 Supervisory Control & Data Acquisition (SCADA) Integration ............. 17100-1

R3M - 6/3/2022 TABLE OF CONTENTS


MCUA-Contract 19-4-8(CTP)(REBID) Gravity Thickener Equipment Rehab.-Phase II PAGE 2
SECTION 17100

SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA) INTEGRATION

PART 1 -- GENERAL

1.1 SCOPE OF WORK

A. Design, supply and install all hardware and software products required to provide a fully
integrated SCADA subsystem as shown on the Contract Drawings and/or herein specified. The
subsystem shall allow for monitoring of statuses of all Gravity Thickener motors and pumps on
local HMIs via local PLCs, and enable the viewing of statuses on the plant’s remote SCADA
system, without the ability to control motors or pumps remotely.

1. Two (2) SCADA cabinets, one located in the top floor of each Stair Building, composed of
but not limited to:

a. 24V DC Power Supply

b. Programmable Logic Controller (PLC)

c. Human-Machine Interface (HMI)

d. Network Switch

e. NEMA 12 Enclosure

B. Design the panels and field wiring interfaces required

1. All panels shall be designed and manufactured in accordance with UL 508A, Standard for
Industrial Control Panels, and National Electrical Code.

2. All components shall be UL recognized.

C. Provide network connection between new panels and existing plant SCADA infrastructure

1. Fiberoptic cables and terminations between ANC-5 cabinet and the new SCADA cabinets,
as shown on the Contract Drawings.

D. Furnish, Install and Test

1. Control panels, programmable logic controllers, enclosures, and appurtenant equipment

2. Software products, interface cables and related products

3. Relays, resistors, signal splitters or other devices required to condition input and output field
signals for the control equipment.

4. Connect and test all input and output field wiring to and from the control equipment.

a. Provide any manufacturer's services required for installation, startup, calibration,


inspection, and training.

1.2 SPECIFICATION REFERENCES

A. Section 16225 - Motor Control Centers

B. Attachment 1 - Basic Network Diagram

C. Attachment 2 - Existing Fiber Network

D. Attachment 3 - I/O List

R3M - 6/3/2022 SCADA


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.- Phase II PAGE 17100-1
E. Attachment 4 - MCUA Programming Guidelines

1.3 SUBMITTALS

A. Furnish submittals in accordance with Section 01300 – Contractor Submittals.

B. Product data shall include catalog cuts and product specifications for all product components.

C. Submit complete detailed shop drawings, working drawings and descriptive literature for control
panel equipment, components. As a minimum the shop drawings and working drawings shall
include the following:

1. Bill of Materials

2. Power load calculations verifying capacity of power supplies to carry panel load

a. Provide a minimum of 20% spare capacity on DC power supplies.

b. Provide 10 minutes of no power operation on UPS units.

3. Front panel, back panel and panel schematic wiring diagrams

a. Submit detailed drawings showing proposed arrangement of equipment within each


enclosure, proposed locations of all equipment and enclosures, and proposed
arrangement of all conduits and conductors that will enter each enclosure.

b. Provide a minimum of 20%, but no less than two (2), installed spare I/O for each type of
I/O present in the panel. All I/O are to be factory wired out to field terminal strips in the
panel. These spare I/O are to be in addition to the material to be supplied under the
Spare Parts section of this specification.

c. Provide a minimum of 20%, but no less than two (2), spare (open) module slots on the
controller I/O back plane.

4. Interconnection wiring diagrams showing all component and panel terminal board
identification numbers and external wire numbers, including existing equipment and
equipment furnished by others.

5. Screenshots of proposed HMI graphics.

6. Complete I/O list.

D. Certificates

1. Manufacturer’s Certificate of Proper Installation

1.4 QUALIFICATIONS

A. Consideration will be given only to products of manufacturers who can demonstrate successful
experience in the manufacture, operation, and servicing of equipment of a type, size, quality,
performance, and reliability equal to that specified.

B. Qualified Instrumentation Suppliers shall have a minimum ten (10) years demonstrated
experience in the design, fabrication, programming, installation, testing, and maintenance of
process control and instrumentation systems successfully utilized for applications in industrial
process plant control systems or wastewater treatment plant control systems. The Systems
Integrator shall be a Rockwell Automation Recognized System Integrator and shall have a Cisco
Certified Network Associate (CCNA) on staff.

R3M - 6/3/2022 SCADA


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.- Phase II PAGE 17100-2
1.5 WARRANTY

A. Provide a manufacturer’s warranty on all products and equipment to remain in effect for not less
than two (2) years after the successful completion of the Site Acceptance Test.

PART 2 -- PRODUCTS

2.1 PLC, HMI AND NETWORK SWITCH

A. To minimize training requirements, provide a uniform look and feel, and provide better support
and administration, the OWNER has standardized on a single Control System software package,
and specific PLC, HMI, and Network Switch manufacturers. Or-equal substitutions are acceptable
pending ENGINEER review; however, these may require at minimum additional spare parts,
training, and software license requirements.

1. Programmable Logic Controller (PLC)

a. PLC shall be Allen-Bradley ControlLogix 1756-L82E, or equal. Provide all power supplies,
I/O modules, removable terminal blocks (RTB), backplanes, end caps, and other
communication adapters as required for a complete system.

1) PLC shall be programmable using ladder logic, structured text, and function blocks

2) PLC shall be compatible with Tenable OT cybersecurity software and part of their
standard OT device database

3) PLC be capable of providing general alarms to SCADA and HMI such as major faults,
minor faults, run status, etc.

2. Human-Machine Interface (HMI)

a. HMI shall be Allen-Bradley Panelview Plus 7, 19”, Color with Ethernet port, or equal.

3. Network Switch (Switch)

a. Switch shall communicate Ethernet/IP

b. Switch shall have Fiberoptic capability

c. Switch shall be Cisco IE-3300, or equal.

2.2 PROGRAMMING SOFTWARE

A. The Contractor's System Integrator shall be responsible for maintaining their own version of the
programming software for their own purposes.

2.3 MISCELLANEOUS EQUIPMENT

A. DC Power Supply

1. Provide power supply housed in rugged narrow metal case with large, rugged accessible,
multiple connection screw terminations

a. Power supply shall be enclosed and completely finger-safe. Open power supplies shall
not be acceptable.

b. Auto select 115/230V AC, 50/60 Hz single phase input

c. Powers high inrush loads without shutdown or foldback, meets SEMI F47 Sag Immunity

d. Power Factor Correction per IEC 61000-3-2

R3M - 6/3/2022 SCADA


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.- Phase II PAGE 17100-3
e. Adjustable voltage

f. Industrial grade design

g. Operates between -10/60 DegC without derating

h. Indefinite short circuit, overvoltage and overtemperature protection

i. High MTBF and reliability

j. Highly efficient greater than 90% switching technology

2. Manufacturer shall be SOLA, or equal

B. Communication Adapters

1. Provide communications adapters only as required to convert signals to Ethernet/IP protocol.

2. Manufactures, or equal:

a. Moxa

b. Prosoft

3. Signal Isolators, Relays and Terminal Blocks

4. Provide signal isolators, relays, and terminal blocks as required.

5. Relays shall be plug-in type, with lockable test button, and LED light.

6. Manufacturers, or equal:

a. Phoenix Contact

b. Allen-Bradley

c. Schneider Electric

C. Wiring

1. Wiring shall be installed and labeled utilizing best practices, ran in a neatly organized
fashion, and in accordance with the National Electrical Code (NEC) and UL 508A.

D. Network Integration

1. The CONTRACTOR shall run 12-fiber single-mode fiberoptic cable (Corning 012EUC-
T4101D2(or equal) from each Stair Building PLC to the ANC-5 network cabinet located in
the East-West Gallery.

2. The MCCs within each Stair Building shall be connected to each other via their respective
Switches via 1Gb CAT-6 cable. Ethernet cable shall be ran in 316SS conduit.

3. The MCCs shall each individually be connected to their respective Stair Building’s SCADA
panel via 1Gb CAT-6 cable. Ethernet cable shall be ran in 316SS conduit.

4. Fiberoptic cable shall be ran in 316SS conduit from each SCADA panel to the ANC-5
cabinet. Hardware modifications to ANC-5 for acceptance of each fiberoptic cable are:

a. Fiber patch panel 1U with two cassettes, one for each PLC connection

1) Fiber patch panel: Corning CCH-01U, or equal

2) Cassette: Corning CCH-CS12-A9-P00RE, or equal

R3M - 6/3/2022 SCADA


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.- Phase II PAGE 17100-4
5. The CONTRACTOR shall coordinate network integration activities with the OWNER. The
OWNER shall have final selection and approval of IP addresses.

2.4 PROGRAMMING

A. PLCs shall be programmed using RSLogix 5000, Version 31 or higher, to be compatible with the
specified PLC/HMI hardware.

B. Final .ACD files shall be turned over to the OWNER for both units.

C. OITs shall be programmed using Factory Talk View Studio, to be compatible with the specified
PLC/OIT hardware.

D. Final .APA and .MER files shall be turned over to the OWNER for both units.

E. Or-equal substitutions which require their own programming software suites shall be programmed
in the latest stable release. Equivalent final program files are to be turned over to the OWNER.

F. All switches on the Operations network will require programming with the new MCC VLAN and
new trunk connection from each PLC switch.

G. Functionality shall be verified with the System Integrator.

H. SCADA should not be allowed to be accessed from a web browser.

2.5 SPARE PARTS

A. The follow spare parts shall be provided:

1. PLC:

a. One (1) PLC with one of every type of PLC part used (I/O cards, backplane, power
supply, end cap, removable terminal blocks, etc.)

b. One (1) PLC programming software license

2. HMI:

a. One (1) HMI touchscreen complete with required cables

b. One (1) HMI programming software license

3. One (1) Network Switch

B. Or-equal substitutions shall require the following spare parts and training to be provided IN
ADDITION to the quantities specified under Paragraph A of this section, as applicable:

1. PLC:

a. One (1) PLC with one of every type of PLC part used (I/O cards, backplane, power
supply, end cap, removable terminal blocks, etc.)

b. Two (2) PLC programming software licenses

c. A total of eight (8) hours of training by Manufacturer’s representative

2. HMI:

a. One (1) HMI complete with required cables

b. Two (2) HMI programming software licenses

c. A total of eight (8) hours of training by Manufacturer’s representative

R3M - 6/3/2022 SCADA


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.- Phase II PAGE 17100-5
3. One (1) Network Switch

4. Two (2) sets of workstation communication cables

PART 3 -- EXECUTION

3.1 INSTALLATION

A. The CONTRACTOR shall furnish and install all required conduit, wiring and electrical
appurtenances for a complete and operable system.

B. The CONTRACTOR shall return any SCADA components scheduled for replacement or
demolition to the OWNER, as applicable.

3.2 TESTING

A. Site Acceptance Testing (SAT) shall be conducted to prove a complete and functional system
without errors. SAT shall include individual verification of loops, signals, faults, HMI functionality,
and witnessed operation of the SCADA system.

B. Where an error is detected because of either a software or wiring fault this shall be reported to
the ENGINEER and the OWNER. After any correction by the CONTRACTOR the loop shall be
retested.

1. The CONTRACTOR shall provide technicians as required to enable effective testing

3.3 TRAINING

A. The System Integrator shall provide two (2) 2-hour training sessions with the OWNER’s
operations staff.

3.4 ACCEPTANCE

A. For the purpose of this section, the following conditions shall be fulfilled before the WORK is
considered substantially complete:

1. All submittals have been completed and approved.

2. The Control System has been tested.

3. All required spare parts and expendable supplies and test equipment have been delivered to
the OWNER.

4. The performance test has been successfully completed.

5. All punch-list items have been corrected.

6. All record drawings in both hard copy and electronic format have been submitted.

7. Revisions to the OWNER’s Manuals that may have resulted from the field tests have been
made and reviewed.

8. All debris associated with installation of instrumentation has been removed.

9. All specified software has been turned over to the OWNER.

- END OF SECTION -

R3M - 6/3/2022 SCADA


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.- Phase II PAGE 17100-6
STAIR BUILDING A Attachment 1 STAIR BUILDING B
MCC 1005.2 MCC 1006.2

COLLECTOR COLLECTOR COLLECTOR COLLECTOR


DRIVE A-2 DRIVE A-4 DRIVE B-4 DRIVE B-2

TSP TSP
A-2 B-2

TSP STRATIX STRATIX TSP


A-4 5700 5700 B-4

TSSP PANEL A PANEL B TSSP


A-2 & A-4 B-2 & B-4
PLC PLC

SCUM PUMP SCUM MIXER SCUM MIXER SCUM PUMP


A-2 & A-4 A-2 & A-4 ANC-5 B-2 & B-4 B-2 & B-4
SCADA SWITCH
STRATIX STRATIX
OPS OPS
SWITCH SWITCH
MCC 1005.1 FIBER/ETH
VLAN VLAN
FIBER/ETH MCC 1006.1

COLLECTOR COLLECTOR COLLECTOR COLLECTOR


DRIVE A-1 DRIVE A-3 DRIVE B-3 DRIVE B-1
17" 17"
TOUCHSCREEN TOUCHSCREN
TSP TSP
A-1 B-1

TSP STRATIX STRATIX TSP


A-3 5700 5700 B-3

LEGEND
TSSP TSSP
= ETHERNET
A-1 & A-3 B-1 & B-3
= FIBER OPTIC

SCUM PUMP SCUM MIXER TSSP = THICKENED SLUDGE SCUM MIXER SCUM PUMP
A-1 & A-3 A-1 & A-3 AND SCUM PUMP B-1 & B-3 B-1 & B-3
TSP = THICKENED SLUDGE
PUMP

NOTE: SWITCHES HAVE MULTIPLE VLANS 19-4-8 NETWORK DIAGRAM


R3M ENGINEERING, INC.
Attachment 2

POWER, SCADA SYSTEM & VoIP NETWORK MEDIA DIAGRAM

Client Title
Designed STV Eng check BO
111 Wood Avenue South FRANCIS J. MESCALL PRIMARY INFLUENT SCREEN & THICKENER
Iselin NJ 08830-4112
MIDDLESEX COUNTY UTILITIES AUTHORITY NJ PROFESSIONAL ENGINEER LIC. No. 24GE039336 Drawn STV Coordination BO
TANK OVERFLOW FORCE MAIN EXTENSION
United States of America MIDDLESEX COUNTY, NEW JERSEY
Certificate No. 24GA28016600 Dwg check TK Approved AB INSTRUMENTATION
2571 MAIN STREET
www.mottmacamericas.com
Date 10/4/2019 Scale at ANSI D Status Rev Security NETWORK MEDIA DIAGRAM
© Mott MacDonald SAYREVILLE, NJ 08872 NTS BID REV 0 STD
This document is issued for the party which commissioned it and for specific purposes connected with the
captioned project only. It should not be relied upon by any other party or used for any other purpose. We Project Number B/O Total Drawing Number
accept no responsibility for the consequences of this document being relied upon by any other party, or
being used for any other purpose, or containing any error or omission which is due to an error or omission in
data supplied to us by other parties. Rev Date Drawn Description Ch’k’d App’d 343502 50 58 I-501
pw:\\mott-use-pw.bentley.com:mott-use-pw-14\Documents\343502-MCUA-THICKENER TANK OVERFLOW SCREENING FACILITY\343502-MCUA-Primary Influent Screen\Drawings_Models\05_I_Process Instrumentation\I-502.dwg
MIDDLESEX COUNTY UTILITES AUTHORITY
Contract 19-4-8 (CTP)(REBID)-Gravity Thickner Equipment Rehabilitation - Phase II
I/O List - Attachment 3

Stair
Equipment Name Signal Type Duty Function
Building
Thickened Sludge Pump A-1 A Discrete Input Running Status
Thickened Sludge Pump A-2 A Discrete Input Running Status
Thickened Sludge Pump A-3 A Discrete Input Running Status
Thickened Sludge Pump A-4 A Discrete Input Running Status
Thickened Sludge & Scum Pump No. 1 A Discrete Input Running Status
Thickened Sludge & Scum Pump No. 2 A Discrete Input Running Status
Mixer Tank A-1, A-3 A Discrete Input Running Status
Mixer Tank A-2, A-4 A Discrete Input Running Status
Collector Drive A-1 A Discrete Input Running Status
Collector Drive A-2 A Discrete Input Running Status
Collector Drive A-3 A Discrete Input Running Status
Collector Drive A-4 A Discrete Input Running Status
Exhaust Fan A-1 A Discrete Input In Local Status
Exhaust Fan A-1 A Discrete Input In Remote Status
Exhaust Fan A-1 A Discrete Input Running Status
Exhaust Fan A-2 A Discrete Input In Local Status
Exhaust Fan A-2 A Discrete Input In Remote Status
Exhaust Fan A-2 A Discrete Input Running Status
Exhaust Fan A-3 A Discrete Input In Local Status
Exhaust Fan A-3 A Discrete Input In Remote Status
Exhaust Fan A-3 A Discrete Input Running Status
Exhaust Fan A-4 A Discrete Input In Local Status
Exhaust Fan A-4 A Discrete Input In Remote Status
Exhaust Fan A-4 A Discrete Input Running Status
Exhaust Fan EF-8 Thickener Stair Bldg A A Discrete Input Running Status
Sump Pump E-35 A Discrete Input Running Status
Sump Pump E-36 A Discrete Input Running Status
Thickened Sludge Pump B-1 B Discrete Input Running Status
Thickened Sludge Pump B-2 B Discrete Input Running Status
Thickened Sludge Pump B-3 B Discrete Input Running Status
Thickened Sludge Pump B-4 B Discrete Input Running Status
Thickened Sludge & Scum Pump No. 1 B Discrete Input Running Status
Thickened Sludge & Scum Pump No. 2 B Discrete Input Running Status
Mixer Tank B-1, B-3 B Discrete Input Running Status
Mixer Tank B-2, B-4 B Discrete Input Running Status
Collector Drive B-1 B Discrete Input Running Status
Collector Drive B-2 B Discrete Input Running Status
Collector Drive B-3 B Discrete Input Running Status
Collector Drive B-4 B Discrete Input Running Status
Exhaust Fan B-1 B Discrete Input In Local Status
Exhaust Fan B-1 B Discrete Input In Remote Status
Exhaust Fan B-1 B Discrete Input Running Status

I/O List - Attachment 3 Page 1


MIDDLESEX COUNTY UTILITES AUTHORITY
Contract 19-4-8 (CTP)(REBID)-Gravity Thickner Equipment Rehabilitation - Phase II
I/O List - Attachment 3

Exhaust Fan B-2 B Discrete Input In Local Status


Exhaust Fan B-2 B Discrete Input In Remote Status
Exhaust Fan B-2 B Discrete Input Running Status
Exhaust Fan B-3 B Discrete Input In Local Status
Exhaust Fan B-3 B Discrete Input In Remote Status
Exhaust Fan B-3 B Discrete Input Running Status
Exhaust Fan B-4 B Discrete Input In Local Status
Exhaust Fan B-4 B Discrete Input In Remote Status
Exhaust Fan B-4 B Discrete Input Running Status
Exhaust Fan EF-9 Thickener Stair Bldg B B Discrete Input Running Status
Sump Pump E-37 B Discrete Input Running Status
Sump Pump E-38 B Discrete Input Running Status
Inline Exhaust Fan (Splitter Box No.2) B Discrete Input Running Status

I/O List - Attachment 3 Page 1


SECTION 17100 - ATTACHMENT 4

PROCESS CONTROL AND INSTRUMENTATION SYSTEMS

PROGRAMMING GUIDELINES

1. Every line in the program should have a comment.


2. Every data point in every data file that is used should have a description.
3. All programming should be down in Ladder Logic.
4. The PLC program shall be broken up into the following Program Files:
A. Main
i. Used to call subprograms
B. MapInput
i. Used to map all Inputs
1. Discrete Inputs
a. Should be “XOR”ed with a dedicated Array Data File. The destination should be
another Array Data File. Array name should correspond to the card slot.
b. Example:

2. Analog Inputs
a. All analog inputs should be scaled in the Module Properties of the corresponding
I/O Card.
b. Example:

R3M - 6/3/2022 PROGRAMMING GUIDELINES - ATTACHMENT 4


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.-Phase II PAGE 1 OF 4
C. MapOutput
i. Used to map all Outputs
1. Discrete Outputs
a. Should be “XOR”ed with a dedicated Array Data File. The destination should
be another Array Data File. Array name should correspond to the card slot.
b. Example:

2. Analog outputs
a. All Analog Outputs should be scaled in the Module Properties of the
corresponding I/O Card.
b. Example:

R3M - 6/3/2022 PROGRAMMING GUIDELINES - ATTACHMENT 4


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.-Phase II PAGE 2 OF 4
D. GenAlarms
i. General Alarm
1. PLC A Fault Alarm
2. PLC B Fault Alarm
3. RACK 1 Fault Alarm
4. RACK 2 Fault Alarm
5. RACK 3 Fault Alarm
6. RACK 4 Fault Alarm
7. RACK 5 Fault Alarm
8. RACK 6 Fault Alarm
9. UPS Fault Alarm
E. System
i. Overhead Logic
F. SysComm
i. Used for system communication logic
G. Equipment (In the following order)
i. Alarms
ii. Control
iii. Math
1. Totalizers

R3M - 6/3/2022 PROGRAMMING GUIDELINES - ATTACHMENT 4


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.-Phase II PAGE 3 OF 4
2. PID, if applicable
5. The PLC program shall be broken up into the following Arrays:
A. Array Files
i. HMIBIT; All Discrete Values that go to the HMI
ii. HMIINT; All Integer Values that go to the HMI
iii. HMIFLOAT; All Float Values that go to the HMI
iv. PLCBIT; All Discrete Values that are internet PLC logic only
v. PLCINT; All Integer Values that are internet PLC logic only
vi. PLCFLOAT; All Float Values that are internet PLC logic only
vii. PIDMEMORY; PID Memory
viii. ALARMS; Alarm Memory
B. Every Data Point (Bit, Integer, Float) should be linked to an about Array File with a
description. Inputs and outputs from I/O cards should be linked to their “Card Slot
Array.”(Under section 3-B and 3-C)
6. All PLCs, PCs, and OITs (Touch Screens) shall be time synched once a day.
7. Do create alarms using the analog cards Module Properties. All alarms should be created using
in the ladder logic.
8. DO NOT have any setpoints for the pump station write to an I/O Card register.

R3M - 6/3/2022 PROGRAMMING GUIDELINES - ATTACHMENT 4


MCUA-Contract 19-4-8(CTP)(REBID)-Gravity Thickener Equipment Rehab.-Phase II PAGE 4 OF 4

You might also like