Professional Documents
Culture Documents
Site Visit Report: Kryfs
Site Visit Report: Kryfs
Based on a request for Inspecting Column welding a site visit was carried out at KRYPS, Building Unit 5. In
Kherdi Village, UT of Dadra Nagar Haveli
Reference Doc.
Proposed ITP - KRYFS/FAB/ITP/2024-25/01
Drawing- SMK-DCPL-KPL-AMPL-MCPL-FB-Unit-5-FAB-002
IS 7215-Tolerances for Fabrication of Steel Structures
IS 12843-Tolerances for Erection of Steel Structures
AWS D1.1 (Structural Welding Code)
Review Documents:
Observation:
1. Column No C-21: Both side welding done but as per drawing its required only 300 mm Stitch weld.
2. Fillet Leg measure and leg size found 8 mm, but throat Thickness is not found as per requirement need
to be rectify.
3. Both side concave weld profile observed, rectification required.
4. Fit up Inspection for C-1, C-13, C-33, C-41, and C-21 Found satisfactory.
5. In fit-up of column to base plate, root face and root gap in two plate found more than 3 mm.
6. Bevel angle not found satisfactory.
7. Approximate 10 mm distortion found in full length of column.
8. Gas cutting is not been done properly.
9. After gas cutting straightening check and found approximate 10 to 20 mm out of the line, need to be
rectify.
Recommendation:
Throat size not match, Concave weld found Throat size not match, Concave weld found
Gas cutting not doing proper Root face & Grinding not proper
Date: 27/02/2024
Mr. Sydney Rozario
ASTSPL Rep. Client Rep. Fabricator Rep.