Professional Documents
Culture Documents
ITP - Erection
ITP - Erection
2.5 NDT - CJP Groove Weld Ultrasonic Testing 100% Approved NDT Procedure AWS D 1.1 NDT Report S P R R
Magnetic Particle
2.6 NDT - PJP Groove Inspection / Dye 100% Approved NDT Procedure AWS D 1.1 NDT Report S P R R
Penetrant Testing
Magnetic Particle
2.7 NDT - Fillet Weld Inspection / Dye 25% Approved NDT Procedure AWS D 1.1 NDT Report S P R R
Penetrant Testing
3 Painting
Painting Procedure guideline to
3.1 Paint Touch-up Visual Inspection 100% painting procedure Project Specification Painting Reports P1 H R R
be followed
4 Decking Work
4.1 Decking Visual Examination Random Decking Layout Structural Inputs Inspection Report P1 P2 R R As per decking layout
Visual & Quality
Follow AWS D 1.1 requirement &
4.2 Verification (WPS / PQR 100% Decking Layout AWS D 1.1 / Structural Inputs Inspection Report P W&A R R
acceptance
Shear Stud Welding / WPQ)
Follow AWS D 1.1 requirement &
4.3 Bend Test Random Stud welding procedure AWS D1.1 Inspection Report P W&A R R
acceptance
5 Final Area Handing Over
Erection methodology / Erection methodology / follow Erection methodology /
5.1 Visual Examination 100% Inspection Report P1 P2 R R
project specification project specification project specification
Final Area Handing Over
Phase / Floor Final Inspection
5.2 Final Documentation Inspection Report Project Specification P H A A Final Quality Dossier
wise report
6 Final Documentation
Preparation of quality
6.1 Quality Dossier One Time NA NA NA S P R&A R&A Final Quality Dossier
dossier
Legends:
S - Submission / offer 1 - 100% / Full Scope TPI - Third Party Inspection VT - Visual Inspection
P - Perform 2 - Random / Sample MTC - Material Test Certificate UT - Ultrasonic Test
R - Review QAP - Quality Assurance Plan RT - Radiography Test
H - Hold ITP - Inspection Test Plan PT - Dye Penetrant Test
W - Witness IRN - Inspection Release note MT - Magnetic Particle test
A - Approve