Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Preliminary Project Schedule for:

Flare System Upgrade (Procurement and Installation of Ultrasonic Flare Meter)


Client: Pillar Oil Limited
Contractor: J&G Engineering and Construction Services Limited

ID Task Name Duration Start Finish Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24 Jun 2, '24 Jun 9, '24 Jun 16, '24
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
0 Flare System Upgrade (Procurement and 7.18 wks Mon 4/15/24 Thu 6/13/24
Installation of Ultrasonic flare meter)

1 1 Project Kick-off 0.34 wks Mon 4/15/24 Wed 4/17/24

2 1.1 Project Kick-off meeting 0.17 wks Mon 4/15/24 Tue 4/16/24

3 1.2 Community Engagement and settlement0.17 wks Tue 4/16/24 Wed 4/17/24

4 1.3 Project Kick-off Concluded 0 wks Wed 4/17/24 Wed 4/17/24 4/17

5 2 Engineering Design 0.5 wks Tue 4/16/24 Fri 4/19/24

6 2.1 Engineering Design Review & Approval 0.5 wks Tue 4/16/24 Fri 4/19/24
cycle

7 2.2 End of Engineering Design 0 wks Fri 4/19/24 Fri 4/19/24 4/19

8 3 Procurement 2.34 wks Fri 4/19/24 Thu 5/9/24

9 3.1 Procurement and Delivery of meter 2.34 wks Fri 4/19/24 Thu 5/9/24
and accessories

10 3.2 Procurement concluded 0 wks Thu 5/9/24 Thu 5/9/24 5/9

11 4 Mobilization & Preconstruction Survey 0.51 wks Fri 4/19/24 Wed 4/24/24

12 4.1 Mobilize Personnel to site 0.17 wks Fri 4/19/24 Mon 4/22/24

13 4.2 Mobilize Equipment to site 0.17 wks Mon 4/22/24 Tue 4/23/24

14 4.3 Preconstruction Survey and ROW access0.17 wks Tue 4/23/24 Wed 4/24/24

15 4.4 Mobilization & Preconstruction Survey 0 wks Wed 4/24/24 Wed 4/24/24 4/24
concluded

16 5 Fabrication and Civil works 1 wk Thu 5/9/24 Fri 5/17/24

17 5.1 Fabrication and Civil works 1 wk Thu 5/9/24 Fri 5/17/24

18 5.2 Fabrication and Civil works concluded 0 wks Fri 5/17/24 Fri 5/17/24 5/17

19 6 Hot Tapping and Mechanical works 2 wks Fri 5/17/24 Tue 6/4/24

20 6.1 Hot Tapping and Mechanical works 2 wks Fri 5/17/24 Tue 6/4/24

21 7 Installation and Commissioning 1.17 wks Tue 6/4/24 Thu 6/13/24

22 7.1 Installation and Commissioning 1 wk Tue 6/4/24 Wed 6/12/24

23 7.2 Demobilize Personnel and Equipment 0.17 wks Wed 6/12/24 Thu 6/13/24

24 7.3 Project Closeout 0 wks Thu 6/13/24 Thu 6/13/24 6/13

Task Project Summary Manual Task Start-only Deadline

Project: Flare System Upgrade ( Split Inactive Task Duration-only Finish-only Progress
Date: Fri 3/15/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1

You might also like