Pillar Schedule
ID Task Name Duration Start Finish Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24 Jun 2, '24 Jun 9, '24 Jun 16, '24
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
0 Flare System Upgrade (Procurement and 7.18 wks Mon 4/15/24 Thu 6/13/24
Installation of Ultrasonic flare meter)
2 1.1 Project Kick-off meeting 0.17 wks Mon 4/15/24 Tue 4/16/24
3 1.2 Community Engagement and settlement0.17 wks Tue 4/16/24 Wed 4/17/24
4 1.3 Project Kick-off Concluded 0 wks Wed 4/17/24 Wed 4/17/24 4/17
6 2.1 Engineering Design Review & Approval 0.5 wks Tue 4/16/24 Fri 4/19/24
cycle
7 2.2 End of Engineering Design 0 wks Fri 4/19/24 Fri 4/19/24 4/19
9 3.1 Procurement and Delivery of meter 2.34 wks Fri 4/19/24 Thu 5/9/24
and accessories
11 4 Mobilization & Preconstruction Survey 0.51 wks Fri 4/19/24 Wed 4/24/24
12 4.1 Mobilize Personnel to site 0.17 wks Fri 4/19/24 Mon 4/22/24
13 4.2 Mobilize Equipment to site 0.17 wks Mon 4/22/24 Tue 4/23/24
14 4.3 Preconstruction Survey and ROW access0.17 wks Tue 4/23/24 Wed 4/24/24
15 4.4 Mobilization & Preconstruction Survey 0 wks Wed 4/24/24 Wed 4/24/24 4/24
concluded
18 5.2 Fabrication and Civil works concluded 0 wks Fri 5/17/24 Fri 5/17/24 5/17
19 6 Hot Tapping and Mechanical works 2 wks Fri 5/17/24 Tue 6/4/24
20 6.1 Hot Tapping and Mechanical works 2 wks Fri 5/17/24 Tue 6/4/24
23 7.2 Demobilize Personnel and Equipment 0.17 wks Wed 6/12/24 Thu 6/13/24
Project: Flare System Upgrade ( Split Inactive Task Duration-only Finish-only Progress
Date: Fri 3/15/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress