FREESIA 23/03/2024
Approval shall not relieve Contractor of any of his obligations under the Contract or constitute authorization of any change to Contract Documents or
variation to the works. Contractor is responsible for dimensions, quantities and coordination with other trades.
A - 06c- Riviera Phase-4 - WIR - Mechanical
Document No. Title Type Revision Status Received Date FILE REPLACED
Mechanical
Clearance for
Toilet ceiling
1084P4-GBC-RV6-MEC- board closure in Work Inspection
00 Approved 22/03/2024
WIR-0417 flats 301 to 318 Request
(Exclude
306,307,317) in
CP04-016
Comments:
Document No. Title Type Revision Status Received Date FILE REPLACED
Mechanical
Clearance for
Toilet ceiling
1084P4-GBC-RV6-MEC- board closure in Work Inspection Checked and
00 23/03/2024
WIR-0417 flats 301 to 318 Request Verified
(Exclude
306,307,317) in
CP04-016
Comments: Documents are Checked and Found Acceptable.
Document No. Title Type Revision Status Received Date FILE REPLACED
Mechanical
Clearance for
Toilet ceiling
1084P4-GBC-RV6-MEC- board closure in Work Inspection Revise and
00 23/03/2024
WIR-0417 flats 301 to 318 Request Resubmit
(Exclude
306,307,317) in
CP04-016
-Incomplete Slab Pipe Sealant penetration with collar and sticker
Comments: - Ceiling not done as per RCP, Contractor to attached latest Approved RCP with Confirmation where
flat ceiling is done on site inside toilet areas.
Approval shall not relieve Contractor of any of his obligations under the Contract or constitute authorization of any change to Contract Documents or
variation to the works. Contractor is responsible for dimensions, quantities and coordination with other trades.