Professional Documents
Culture Documents
Using ETAP Load Flow Analysis of 132 11kv Kohat Substation A Case Study
Using ETAP Load Flow Analysis of 132 11kv Kohat Substation A Case Study
ISSN 2320-9186
1040
KeyWords
ETAP, Power flow analysis, under voltages etc.
GSJ© 2019
www.globalscientificjournal.com
GSJ: Volume 7, Issue 11, November 2019
ISSN 2320-9186
1041
Abstract – Using ETAP software load flow analysis owner-operator. ETAP offers a suite of fully integrated
is accurate and gives high reliable result. This Electrical Engineering software solutions including arc
research makes effective use of ETAP (Electrical flash, load flow, short circuit, transient stability, relay
Transient Analyzer Program) to carry out load flow coordination, cable capacity, optimal power flow, and
analysis of 132 kV substation. The actual rating of more. Its modular functionality can be customized to fit
transformer, circuit breakers, current transformer, the needs of any company, from small to large power
potential transformer and isolating switch are taken systems [2].
and modelled in ETAP in the form of single line
diagram. This 132 kV grid station located in KPK Figure 1: Load Flow Diagram
Kohat Pakistan which is come under NTDCL
(National Transmission and Dispatch Company
limited).
In the operation and design planning for the power
system, the most significant and beneficial approach
for the investigation of problems relating to power
systems can be done by means of load flow analysis
or design power flow. In light of a predefined
structured power system and transmission system,
the load flow analysis provides steady state
As the electric power demand increasing day by day so
characteristic data for voltage phase angles and its for that demand more generating station buit but also to
magnitude, the flow of reactive power in the
redesign the current power grid. For this reason, load
transmission lines, losses in the system, generation
flow analysis can play vital role. Load flow or power
and consumption of reactive power in the bus bar flow analysis can be performed by using Electrical
load. In this, an effort has been made to explore
Transient Analyzer Program (ETAP)
power flow in the 132/11kV grid by utilizing ETAP
which gives accurate, precise and reliable
[1]. The data will be collect from Kohat 132/11KV outcomes[3][4].ETAP provides a package of complete
substation over a period of one year, specifically in
set of Electrical Design programming tools which
summer and winter peak loads.
consists of transient steadiness, transfer coordination,
burden stream, transfer coordination, link capacity, and
I. INTRODUCTION numerous more ETAP [5].
ETAP is Electrical Transient Analyzer Program. This It is predicted that consumption of energy will rise as
software provides Engineers, operators, and manager the population raises by which urbanization increases
platform for continuous functionality from modeling to and financial system will raise too [6].In third world
operation. ETAP’s model driven architecture enable county or developing countries like Pakistan, where
“Faster than Real-Time” operations - where Data and the generation capacity of electricity is not increasing in
analytics meet to provide predictive behaviour, pre- the same proportion as the demand of the country,
emptive action, and situational intelligence to the which in term leads to deficit of electric power. In spite
GSJ© 2019
www.globalscientificjournal.com
GSJ: Volume 7, Issue 11, November 2019
ISSN 2320-9186
1042
of the deficiency of electric power, the main reason for Equipment Type Primary/ Secondary
the energy deficit is the deficiency in the field of Current Transformers 1200/5A
analysis [7].Due to under voltage problem in power CT 1-3
system causes disturbance in power system so in case Current Transformers 1600/5A
of heavy load the reactive power cannot be send to long CT 4
separation so reactive power can be generated near the Current Transformers 300/5A
load. This is because the difference in voltage causes CT 5-11
reactive power (VARs) to flow and voltages on a Current Transformers 600/5A
power system are only ±5 percent of nominal and this Remaining 41 CTs
small voltage difference does not cause considerable
reactive power (VARs) to flow over long distances. So
if that reactive power (VARs) is not available at the Table 2: Potential Transformer Rating
load centre, the voltage level goes down. Lasting under
voltages can cause excess wear and tear on certain Equipment Type Primary/ Secondary
devices like motor as they will tend to run overly hot Potential Transformers 132KV/120 KV
if the voltage is low [8]. Power system studies are done PT- 5
by electrical engineers from many years for utilizing Potential Transformers 66 KV/120 KV
distinctive programming tools. The recently powerful PT- 6
Computer-based software is emerged as a cause of
important research in the field of electrical engineering. Table 3: Power Transformer Rating
For the analysis and examination of mighty electrical
power systems, which comprises of power distribution Power TF Rating Primary/
flowing from the 132kV grid, this project features the secondary
viable utilization of Electrical Transient Analyzer TF-1 40MVA 132/11 KV
Program (ETAP).[9][10][11].For modelling and TF-2 40MVA 132/66 KV
simulation in ETAP, the single line diagram and real TF-3 37MVA 132/11 KV
ratings of power transformers, current
TF-4 26MVA 132/11 KV
transformers(CT), circuit breakers, potential
transformers(PT) and isolators are taken from 132kV
kohat grid situated in kohat Pakistan. Table 4: Current Transformer Rating
GSJ© 2019
www.globalscientificjournal.com
GSJ: Volume 7, Issue 11, November 2019
ISSN 2320-9186
1043
Table 5: 11KV Feeder Summer & Winter Load 132KV single line diagram are modelled in ETAP
which are given above. The two bus bar of 132 KV
11kv Feeder Winter Load Summer load rated having four incoming supplies. These 132KV bus
(Places) (A) (A) bars are further connected to feeders through power
Old City 1 200 160 transformers which stepped down to 11KV. Already to
New City 2 250 190 capacitor bank are installed of rating of 7.2 MVAR
New City 3 260 290 each.
Lachi Express 370 380
Figure 3: Simulation of 132KV grid in ETAP Before adding
Jarma 450 250
capacitor
K.T.M 5 7
B.C.M 50 90
Gumbat 370 400
Kohat Express 410 390
Barh 290 250
Alizai-1 220 150
OTS 140 370
Kharmaton 420 390
College town 160 230
Cadet college 120 120
Kohat tunnel 22 25
GSJ© 2019
www.globalscientificjournal.com
GSJ: Volume 7, Issue 11, November 2019
ISSN 2320-9186
1044
Figure 3: Simulation of 132KV grid in ETAP before after Type MW MVAR MVA %P.F
adding capacitor Swing 173.9 93.45 205.5 87.9
Total 173.9 93.45 205.5 87.9
Demand
Appearent 0.31 8.21 --- ---
Losses
Grid MV KV MW MVA Am % While the bus 9 is in under voltage and two power
Type R p P.F transformer TF-2 & TF-4 are overloaded which are
Daud 27.43 132 40.96 23.04 206 87.2 marginal alert condition which is shown in below table.
Khel 1
Daud 27.43 132 40.96 23.04 206 87.2 Table 8: Marginal alert of bus 9 which is in under voltage
Khel 2 &power transformer tf-2&tf-4 are overloaded.
Pesha 37.27 132 45.90 27.70 235 85.6
war 1 Equipment Conditio Ratin Operatin %Operati
Pesha 45.72 132 45.90 27.70 235 85.6 Type n g g ng
war 2 Bus 9 Under 11 10.62 96.5
Voltage KV
TF-2 Overloa 40 38.9 97.1
V. LOAD FLOW ANALYSIS Transform d MVA
Swing capacity, demand and losses summary report er
without capacitor bank are in below table.
TF-4 Overloa 26 25.90 99.6
Transform d MVA
Table 7: summary Report of swing, total demand and losses
er
before adding capacitor bank.
GSJ© 2019
www.globalscientificjournal.com
GSJ: Volume 7, Issue 11, November 2019
ISSN 2320-9186
1045
GSJ© 2019
www.globalscientificjournal.com
GSJ: Volume 7, Issue 11, November 2019
ISSN 2320-9186
1046
GSJ© 2019
www.globalscientificjournal.com