MATERIAL COST
1.00 Post Installation Application Coverage SQM.
MATERIALS DESCRIPTION QTY UNIT UNIT COST COST
Ordinary Plywood 1/2 inch thk x 4 x 8ft wide 1 pcs ₱1,200.00 ₱1,200.00
Common Wire Nail 3 inch long 1 kg ₱100.00 ₱100.00
Common Wire Nail 2 inch long 2 kg ₱80.00 ₱160.00
Concrete Nail 3 inch long 1 kg ₱100.00 ₱100.00
Coco Lumber 2 x 2 x 10 ft long 6 pcs ₱120.00 ₱720.00
Cement 40-kg 1 pcs ₱280.00 ₱280.00
Crushed Gravel 3/4 inch 0.2 cu ₱2,000.00 ₱400.00
Fined Sand Vibro 0.1 cu ₱2,000.00 ₱200.00
Steel Bars 10 mm x 21 ft long 2 pcs ₱280.00 ₱560.00
Steel Bars 10 mm x 21 ft long 1 pcs ₱280.00 ₱280.00
G.I Tie Wire Gauge 16 1 kg ₱100.00 ₱100.00
Tubular Bar 2 mm thk 2 x 3 x 21ft long 2 pcs ₱1,900.00 ₱3,800.00
Metal Primer 1 gal ₱850.00 ₱850.00
Welding Rod 1 box ₱370.00 ₱370.00
TOTAL COST ₱9,120.00
2.00 Roofing Works Application Coverage SQM.
MATERIALS DESCRIPTION QTY UNIT UNIT COST COST
G.I Long Span 1 lot ₱9,000.00 ₱9,000.00
Tubular Bar 2 mm thk 2 x 3 x 21ft long 3 pcs ₱1,900.00 ₱5,700.00
C Pulins 2 mm thk 2 x 2 x 21ft long 10 pcs ₱650.00 ₱6,500.00
Tex Screw 1 lot ₱350.00 ₱350.00
Sealant 1 lot ₱400.00 ₱400.00
TOTAL COST ₱21,950.00
COST SUMMARY
SCOPE OF WORKS
1.00 Post Installation ₱9,120.00
2.00 Roofing Works ₱21,950.00
3.00 Bar Counter ₱6,020.00
4.00 Kitchen Counter ₱4,230.00
5.00 Partition Works ₱2,360.00
6.00 Miscellaneous ₱5,000.00
7.00 Labor Cost ₱17,472.00
8.00 Contingency(10%) ₱26,460.80
Overall Total Cost ₱92,612.80