Professional Documents
Culture Documents
Final Project 1
Final Project 1
Final Project 1
Thank you
Project content:
Chapter1 (Project Scope)
1.1 Project Purpose ……………………………………………………………………………………………….…07
1.2 Project Location …………………………………………………………………………….............…….…07
1.3 Project Description …………………………………………………………………….…………..……….…09
1.4 Scope of work …………………………………..…………………………………………………..………..…10
IL CUORE VERDE INTRODUCTION
1.5 Project Layout
………………………………………………...………….........................................11
1.6 Project information’s ………………………………………….…………………………………..…………15
1.7 Project participants …………………………………………...………………………………………………16
3
IL CUORE VERDE INTRODUCTION
4.6 Activity coding
…………………………………………………………………………………………..………..79
4.7 Define Activities List………………………………………………………………………………………………79
4.8.1 Coding activities……………………………………………………………………………………….….80
4.8.2 Coding activities……………………………………………………………………………………………81
4.8.3 Coding activities……………………………………………………………………………………………81
CHAPTER 5 (RESOURCES)
5.1 INTRODUCTION…………………………………………………………………………………………………..113
5.2 CONSTRUCTION RESOURCES MIGHT INCLUDE…………………………………………………….113
5.3 The type of project resources………………………………………………………………………………114
5.4 Seven Category Types of Resources in Project Management……………………………….114
5.5 Project resources…………………………………………………………………………………………………119
5.6 Table of duration…………………………………………………………………………………………………121
5.7 Histogram ………………………………………………………………….……………………………………….140
4
IL CUORE VERDE INTRODUCTION
6.18 Hard Logic Vs Soft
Logic.…………………………………………………………………………...…..170
6.19 Project Evaluation.………………………………………………………………………………………….171
6.20 Project Brief.…………………………………………………………………………..………………….…..172
5
IL CUORE VERDE PROJECT SCOPE
Chapter 1
PROJECT SCOPE
6
IL CUORE VERDE PROJECT SCOPE
7
IL CUORE VERDE PROJECT SCOPE
8
IL CUORE VERDE PROJECT SCOPE
9
IL CUORE VERDE PROJECT SCOPE
Civil Works
Arch Works
Mep Works
Facade Works
Landscape Works
OUT OF SCOPE
Infrastructure Works
Final finishing and furnishing for units
10
IL CUORE VERDE PROJECT SCOPE
Fig1.7GROUND FLOOR
11
IL CUORE VERDE PROJECT SCOPE
12
IL CUORE VERDE PROJECT SCOPE
13
IL CUORE VERDE PROJECT SCOPE
14
IL CUORE VERDE PROJECT SCOPE
15
IL CUORE VERDE PROJECT SCOPE
Owner Archplan
Developments
Arch Archplan
Consultant
16
IL CUORE VERDE QUANTITY SURVEYING
Chapter 2
Quantity Surveying
17
IL CUORE VERDE QUANTITY SURVEYING
2.1 Introduction
2.1.1 Definition of Quantity Surveying :
Quantity survey is a schedule and take-off of quantities of all the items
of work in a building.
18
IL CUORE VERDE QUANTITY SURVEYING
19
IL CUORE VERDE QUANTITY SURVEYING
2.4 Excavation
Excavation
Object Units Area Hight Volume
Z1 m3 3670 11 40370
2.5 FOUNDATIONS
2.5.1 PC RAFT
FOUNDATIONS
PC RAFT
Object Units Level Area Thickness Volume
Z1 m3 -8.85 3025 0.2 605
2.5.2 RC RAFT
FOUNDATIONS
RC RAFT
Object Units Level Area Thickness Volume
Z1 m3 -9.85 2935 1 2935
20
IL CUORE VERDE QUANTITY SURVEYING
2.6 Columns
21
IL CUORE VERDE QUANTITY SURVEYING
22
IL CUORE VERDE QUANTITY SURVEYING
23
IL CUORE VERDE QUANTITY SURVEYING
24
IL CUORE VERDE QUANTITY SURVEYING
25
IL CUORE VERDE QUANTITY SURVEYING
26
IL CUORE VERDE QUANTITY SURVEYING
2.7 Cores
Cores
Concrete of Cores (B1&B2)
Object Units length Thickness hight Size
core 1 m3 29.5 0.3 4.5 39.825
core 2 m3 19.6 0.3 4.5 26.46
core 3 m3 12.9 0.3 4.5 17.415
total 83.7
Cores
Concrete of Cores (GF)
Object Units length Thickness hight Size
core 1 m3 29.5 0.3 4.7 41.595
core 2 m3 19.6 0.3 4.7 27.636
core 3 m3 12.9 0.3 4.7 18.189
total 87.42
Cores
Concrete of Cores (F1-F7)
Object Units length Thickness hight Size
core 1 m3 29.5 0.3 3.5 30.975
core 2 m3 19.6 0.3 3.5 20.58
core 3 m3 12.9 0.3 3.5 13.545
total 65.1
27
IL CUORE VERDE QUANTITY SURVEYING
Retaining walls
Concrete of Retaining walls
Object Units length Thickness hight Volume
W1 m3 213.7 0.4 12 1025.76
W2 m3 17.5 0.3 12 63
total 1088.76
Quantity of Concrete of Retaining walls = 1089 m^3
2.9 Slabs
28
IL CUORE VERDE QUANTITY SURVEYING
29
IL CUORE VERDE QUANTITY SURVEYING
2.10 Stairs
total 8.775525
30
IL CUORE VERDE QUANTITY SURVEYING
2.11 Beams
total 1.51884
total 1.51884
31
IL CUORE VERDE QUANTITY SURVEYING
total 1.51884
32
IL CUORE VERDE QUANTITY SURVEYING
2.12 Finishes
2.12.1 Bricks
33
IL CUORE VERDE QUANTITY SURVEYING
34
IL CUORE VERDE QUANTITY SURVEYING
2.12.2 Plaster
35
IL CUORE VERDE METHOD OF CONSTRUCTION
Chapter 3
METHOD OF CONSTRUCTION
36
IL CUORE VERDE METHOD OF CONSTRUCTION
Introduction
Method of construction refers to the method to construct the building’s
elements by surveying the available resource and project site conditions.
The following section illustrates examples of project works method of
construction. Plans should include construction methods to be adopted
for different construction activities and tools and planning for tools and
tackles for each activity so that they can be made available whenever
required.
Construction strategy:
1- Site Mobilization & Earth work
2- Surveying works
3- Excavation
4- Soil replacement
5- Retaining wall (Formwork, reinforcement, concrete pouring) then insolating
then backfilling
6- PC Foundation: it is 15 cm was done in 1 stage
7- Raft ( Formwork, reinforcement, concrete pouring)
8- Columns (formwork, reinforcement, concrete pouring)
9- First slab “Lower basement slab”
10- Columns of second slab (Formwork, reinforcement, and concrete pouring)
11- Second slab (Formwork, reinforcement, and concrete pouring)
12- Then typical floors.
37
IL CUORE VERDE METHOD OF CONSTRUCTION
38
IL CUORE VERDE METHOD OF CONSTRUCTION
39
IL CUORE VERDE METHOD OF CONSTRUCTION
3.3 Excavation:
The depth is 11 meters below ground level according to
recommendations of soil report, retaining walls were used to support
the sides of the excavation area, and the level of excavation is checked
using the total station
The fixed points of the building must be benchmarked in case there is a
conflict between it and the area of the excavation, and these points
usually resembles the vertices of the building, extra helping points are
taken on known distance from the building, after the excavation is done
we return to these helping points to allocate the fixed points of the
building on the level of construction one more time
Total excavation is 40370 m3
An Excavator was used and two Loader with 3 m2 per bucket were used
and the excavated soil was transported to public landfills using three 20
liter trucks.
40
IL CUORE VERDE METHOD OF CONSTRUCTION
41
IL CUORE VERDE METHOD OF CONSTRUCTION
Checking:
) زز
Check on the angles of the pig. (الخنيرة
Check the angels of the excavation according to soil type
Check the level of the excavation
Check the borders of the building
42
IL CUORE VERDE METHOD OF CONSTRUCTION
43
IL CUORE VERDE METHOD OF CONSTRUCTION
44
IL CUORE VERDE METHOD OF CONSTRUCTION
45
IL CUORE VERDE METHOD OF CONSTRUCTION
Checking:
1. To ensure the durability and quality of the wood
2. Ensure that sectors and inclinations (if any) match the drawings
3. Verify the dimensions and sizes of the walls according to the
drawings
4. Verify the verticality of the sides and binding using a thread
leveler
5. Ensure the durability of the mattresses under the posts and the
durability of the wooden structure
6. Ensure the presence of locks
7. Ensure that there are no gaps between the application panels of
the wall
46
IL CUORE VERDE METHOD OF CONSTRUCTION
3.5.3 Raft:
The form work was traditional in the raft, the thickness is 1 m of
concrete with compressive strength of 350 kg/M3
The raft is under the whole building’s area is reinforced .
pouring the concrete. 3 pumps were used on site
The raft was poured in one day.
Then we pour the concrete and the sides are de-shuttered after 24
hours
47
IL CUORE VERDE METHOD OF CONSTRUCTION
48
IL CUORE VERDE METHOD OF CONSTRUCTION
49
IL CUORE VERDE METHOD OF CONSTRUCTION
Formwork:
Fixing the plywood onto a backing framework. The framework
normally is made with timber or iron sections. The timber frame
members shall be joined end to end by butt joint or lap joint or
mitred joint. And the shuttering plywood shall be screwed or
nailed to the framework
separate panels that can be joined side by side by using suitable
nuts and bolts spaced at suitable distances
Steel frameworks may be of angled iron or channel section
suitably fabricated and braced to which shuttering plywood can
be fixed either by nuts and bolts or by screws
The plywood is so fixed on to the timber or steel framework that
it gives a flush surface on the inside. The four-side frames are
assembled into box form by use of nuts and bolts at appropriate
distances, where holes have been drilled earlier, 3 sides are
assembled and the fourth is installed after the reinforcement is
done.
Checking on formwork:
1. The dimensions of each column is checked, taking in
consideration the thickness of plywood
2. Measure the distance between each two successive columns
3. Matching the columns directions with drawings
50
IL CUORE VERDE METHOD OF CONSTRUCTION
Columns reinforcing:
Steel bars are prepared according to drawings
The neck of the column is measured from the surface of the
reinforced foundations till the level of the ceiling surface
The steel is cut and ready to be placed
The plastic biscuit are set for the concrete cover
Steel check:
1. check the number, diameter and the setting of steel bars for each
column
2. measure the column necks
3. checking the stirrups its diameter and it’s density in each meter in
the top and bottom of each column
4. checking the pacing of steel bars with stirrups
5. checking that the bars at 90 degrees
6. checking the thickness of concrete cover.
51
IL CUORE VERDE METHOD OF CONSTRUCTION
Pre-pouring:
after getting the pouring permit, the concrete station is
notified with date and time for pouring
clearing the positions of the concrete pumps, and concrete
trucks
a crew of form men is set at site to help fixing any defects in
the formwork during pouring
the formwork is sprayed well with water
Pouring concrete:
making sure the pump is on site in time, and ready.
making the required tests for concrete.
52
IL CUORE VERDE METHOD OF CONSTRUCTION
After pouring:
de-shutter after 24 hours.
cure with water for 7 days.
3.5.5 Slabs:
The formwork was fair face using plywood, and the reinforcement
wasn’t traditional, in all the slabs in the building we used the post
tension, we could have used only lower reinforcement with PT but due
to the Egyptian code we were obligated to use upper and lower
reinforcement.
Formwork:
The vertical posts are placed at the required distances (80 cm
between the post and the post).
Brands are made every 180 cm.
Strengthening is done with frogs.
The level of the beam bottoms is determined on the posts.
Beam strips are made.
The cameras application is installed.
Carpentry of the bottoms of the beams and installing them
above the application.
Make the sides of the internal and external beams, as the
internal is the height of the beam and the external is the height
of the ball and slab.
Making pallets.
53
IL CUORE VERDE METHOD OF CONSTRUCTION
Checking:
1. check that there is no slope in the slab
2. check the thickness of the slab
3. check the dimensions of the slab
4. check the depth of the beams
5. check the bracing of the formwork
6. check the drop of bathrooms areas in the slabs
Steel reinforcement:
Installing the reinforcement of the slabs and beams
set the lower steel reinforcement for the slab, set it on iron chairs
set the post tension
Install the upper reinforcement steel
Checking:
check the iron bars, that they clean and there is no Rust
check the number and dimensions of bars
check the connection between bars, and post tension wires
according to drawings
check the dimensions of the stirrups, and density in each meter
check the distance for the concrete cover
check the column necks, their length
54
IL CUORE VERDE METHOD OF CONSTRUCTION
55
IL CUORE VERDE METHOD OF CONSTRUCTION
Pre-pouring:
after getting the pouring permit, the concrete station is notified
with date and time for pouring
clearing the positions of the concrete pumps, and concrete
trucks
a crew of form men is set at site to help fixing any defects in the
formwork during pouring
the formwork is sprayed well with water
Pouring concrete:
making sure the pump is on site in time, and ready
making the required tests for concrete
After pouring:
cure with water for 7 days
56
IL CUORE VERDE METHOD OF CONSTRUCTION
57
IL CUORE VERDE METHOD OF CONSTRUCTION
58
IL CUORE VERDE METHOD OF CONSTRUCTION
59
IL CUORE VERDE METHOD OF CONSTRUCTION
60
IL CUORE VERDE METHOD OF CONSTRUCTION
61
IL CUORE VERDE METHOD OF CONSTRUCTION
62
IL CUORE VERDE METHOD OF CONSTRUCTION
63
IL CUORE VERDE METHOD OF CONSTRUCTION
3.7.2 Plasterwork:
Plasterwork: It is a layer of cement and sand mortar covering the
surfaces of buildings and concrete to obtain clean flat solid surfaces
that can be finished with paints such as oil or plastic or can be covered
with a kind of sucker. Whiteness controls the prominence of the throats
of doors and windows whiteness if its surface is strong and cohesive,
the strength and cohesion of paints on its surface increases.
3. Lining layer .
4. Epithelium layer.
350 kg cement + 1 cubic meter of sand is unique 200 square meters with
a thickness of 1/2 cm from the inside.
64
IL CUORE VERDE METHOD OF CONSTRUCTION
tendons: It works from the same color as the lining and its purpose is to
shield and settle the lining form.
5- Epithelium layer: It is the final layer, where it gives the shape, color
and final texture of whiteness, and often its thickness is 1/2 cm in the
case of Al-Masisi, 2 cm in the case of artificial stone and mosaic, and 2
mm for granite and gravito.
65
IL CUORE VERDE METHOD OF CONSTRUCTION
Width: The width of the aluminum layer ranges between 1220mm and
1250mm.
66
IL CUORE VERDE METHOD OF CONSTRUCTION
2-Curtain wall:
A curtain wall is an exterior covering of a building in which the outer
walls are non-structural, instead serving to protect the interior of the
building from the elements. Because the curtain wall facade carries no
structural load beyond its own dead load weight, it can be made of
lightweight materials. The wall transfers lateral wind loads upon it to
the main building structure through connections at floors or columns of
the building.
The curtain wall was made of glass and was executed from the inside.
67
IL CUORE VERDE WPS & ACTIVITY LIST
Chapter 4
WBS Introduction
& Activity List
68
IL CUORE VERDE WPS & ACTIVITY LIST
69
IL CUORE VERDE WPS & ACTIVITY LIST
Mobilization Works
Demobilization
Works
70
IL CUORE VERDE WPS & ACTIVITY LIST
71
IL CUORE VERDE WPS & ACTIVITY LIST
72
IL CUORE VERDE WPS & ACTIVITY LIST
73
IL CUORE VERDE WPS & ACTIVITY LIST
Arch
Puplic Toilets
74
IL CUORE VERDE WPS & ACTIVITY LIST
75
IL CUORE VERDE WPS & ACTIVITY LIST
76
IL CUORE VERDE WPS & ACTIVITY LIST
77
IL CUORE VERDE WPS & ACTIVITY LIST
78
IL CUORE VERDE WPS & ACTIVITY LIST
79
IL CUORE VERDE WPS & ACTIVITY LIST
Types Of Work
Code Description
M Milestone
GW General Work
E Engineering
P Procurement
C Construction
T&C Testing & Commissiong
CO Closeout
MO Mobilization
DM Demobilization
EA Earth Works
SH Shoring
FO Foundation Work
B Basement
80
IL CUORE VERDE WPS & ACTIVITY LIST
81
IL CUORE VERDE WPS & ACTIVITY LIST
Milestone
CC-01 Commencement Date CV-M-CC-01
General Work
MO Mobilization CV-GW-MO
DE Demobilization CV-GW-DE
Engineering
Receiving IFC drawings
RS-IFC-D Receive Structure IFC Drawing CV-E- RS-IFC-D
Shop Drawing
SDS Shop Drawing Submittals CV-E-SD-SDS
Material
MS Material Submittals CV-E-M-MS
82
IL CUORE VERDE WPS & ACTIVITY LIST
Construction
Site preparation
ST Set Boundaries CV-C-SP-ST
EX Excavation CV-C-SP-EX
Earth Work
EX Excavation CV-C-EW-EX
IB Internal Backfilling CV-C-EW-IB
EB External Backfilling CV-C-EW-EB
Sub structure
Retaining Wall
EX Excavation CV-C-SS-RW-EX
ST Steel fixing for RC Retaining CV-C-SS-RW-ST
Wall
PO Pouring concrete for Retaining CV-C-SS-RW-PO
Wall
RC Raft
SH Shuttering for RC raft CV-C-SS-RC-SH
ST Steel fixing for RC raft CV-C-SS-RC-ST
PO Pouring concrete for RC raft CV-C-SS-RC-PO
DSH DE shuttering for RC raft CV-C-SS-RC-DSH
CU Curing for RC raft CV-C-SS-RC-CU
83
IL CUORE VERDE WPS & ACTIVITY LIST
84
IL CUORE VERDE WPS & ACTIVITY LIST
85
IL CUORE VERDE WPS & ACTIVITY LIST
86
IL CUORE VERDE WPS & ACTIVITY LIST
87
IL CUORE VERDE WPS & ACTIVITY LIST
88
IL CUORE VERDE WPS & ACTIVITY LIST
89
IL CUORE VERDE WPS & ACTIVITY LIST
90
IL CUORE VERDE WPS & ACTIVITY LIST
91
IL CUORE VERDE WPS & ACTIVITY LIST
92
IL CUORE VERDE WPS & ACTIVITY LIST
93
IL CUORE VERDE WPS & ACTIVITY LIST
94
IL CUORE VERDE WPS & ACTIVITY LIST
95
IL CUORE VERDE WPS & ACTIVITY LIST
96
IL CUORE VERDE WPS & ACTIVITY LIST
97
IL CUORE VERDE WPS & ACTIVITY LIST
98
IL CUORE VERDE WPS & ACTIVITY LIST
99
IL CUORE VERDE WPS & ACTIVITY LIST
100
IL CUORE VERDE WPS & ACTIVITY LIST
101
IL CUORE VERDE WPS & ACTIVITY LIST
102
IL CUORE VERDE WPS & ACTIVITY LIST
103
IL CUORE VERDE WPS & ACTIVITY LIST
104
IL CUORE VERDE WPS & ACTIVITY LIST
105
IL CUORE VERDE WPS & ACTIVITY LIST
106
IL CUORE VERDE WPS & ACTIVITY LIST
107
IL CUORE VERDE WPS & ACTIVITY LIST
108
IL CUORE VERDE WPS & ACTIVITY LIST
109
IL CUORE VERDE WPS & ACTIVITY LIST
110
IL CUORE VERDE WPS & ACTIVITY LIST
Roof
Electrical works
SS Solar Station CV-C-M-R -E-SS
Landscape area
Irrigation Network
Lighting For Landscape
Duct Bank
Softscape
T Trees CV-C-LS-S-T
PT Palm trees CV-C-LS-S-PT
P Plants CV-C-LS-S-P
Hardscape
I Interlock CV-C-LS-H-I
SP Spotlights CV-C-LS-H-SP
SE Seating CV-C-LS-H-SE
111
IL CUORE VERDE RESOURCES
Chapter 5
Resources
112
IL CUORE VERDE RESOURCES
5.1 Introduction.
Resources are the means of production needed to complete a project.
Most project managers would consider the big three resources that will
require your attention to be: material, labor, and equipment. A key idea
when managing the overall capacity, availability, and allocation of
resources on large construction projects is that the project manager’s
perspective is from the level of completion of the project’s major
features of work.
Construction companies need the ability to have real-time visibility into
resources needed, what’s available, where their resources are located
and the ability to reschedule those resources accordingly. Ensuring the
highest utilization of resources across all projects in order to complete
on schedule is key to delivering on time and under budget. That's why a
program that provides visibility into early indicators where owned
resources are light to allow for rentals, subcontracts or purchases to be
secured, is so important.
113
IL CUORE VERDE RESOURCES
114
IL CUORE VERDE RESOURCES
5.4.1 Services
A project may benefit from, and often require, hiring third-parties for
certain tasks. Making the right choice requires careful consideration
from the project manager. Forbes explains:
One of the best ways to decide to outsource a task is to perform a
cost/time calculation. You may have tasks that you could conceivably do
in-house with the right amount of time and money – for example,
perhaps you eventually plan to hire in-house developers to increase your
software design flexibility. But in the website and your back-end systems.
In the short- term, you can outsource this work to a contractor, with the
long-term goal of recruiting in-house developers.
5.4.2Labors.
Workers: like masons, plasterers, steel fixer, carpenter, helpers and
plumbers who are hired to perform specific task or activity.Staff: include
project manager, engineers, safety officers, who are tied to the project.
5.4.3 Equipment.
The selection of the appropriate type and size of construction equipment
often affects the required amount of time and effort and thus the job-
site productivity of a project. It is therefore important for site managers
and construction planners to be familiar with the characteristics of the
major types of equipment most commonly used in construction.
Construction equipment: Which are used for the construction process
but not permanently installed in the project such as excavator, loaders
and trucks.
5.4.4 materials.
115
IL CUORE VERDE RESOURCES
116
IL CUORE VERDE RESOURCES
5.4.6 Time.
Software Project Management explains the time type of resource in
project management as follows: Time is the resource that is being offset
against the other primary resources – project timescales can be reduced
by increasing other resources and will almost certainly be extended if
they are unexpectedly reduced.
5.4.7 Resource productivity.
Productivity in construction is often broadly defined as output per labor
hour. it is important to note that labor productivity is a measure of the
overall effectiveness of an operating system in utilizing labor, equipment
and capital to convert labor efforts into useful output, and is not a
measure of the capabilities of labor alone. For example, by investing in a
piece of new equipment to perform certain tasks in construction, output
may be increased for the same number of labor hours, thus resulting in
higher labor productivity. Job-site productivity is influenced by many
factors which can be characterized either as labor characteristics, project
work conditions or as non-productive activities.
117
IL CUORE VERDE RESOURCES
118
IL CUORE VERDE RESOURCES
119
IL CUORE VERDE RESOURCES
5.5.2 Equipment.
NO Activity name Resource Name Resource Type
1 Excavation works Excavator + loader Equipment
+ truck
2 Backfilling works Loader compactor Equipment
+ trucks
3 Pouring concrete Pump + mixers + Equipment
vibrator
5.5.3 Materials.
NO Activity name Resource Name Resource Type
1 Raft Brich plywood material
2 Footing R.C Brich plywood + material
Reinforcement
steel
120
IL CUORE VERDE RESOURCES
121
IL CUORE VERDE RESOURCES
122
IL CUORE VERDE RESOURCES
123
IL CUORE VERDE RESOURCES
124
IL CUORE VERDE RESOURCES
125
IL CUORE VERDE RESOURCES
126
IL CUORE VERDE RESOURCES
127
IL CUORE VERDE RESOURCES
128
IL CUORE VERDE RESOURCES
129
IL CUORE VERDE RESOURCES
130
IL CUORE VERDE RESOURCES
131
IL CUORE VERDE RESOURCES
132
IL CUORE VERDE RESOURCES
133
IL CUORE VERDE RESOURCES
134
IL CUORE VERDE RESOURCES
135
IL CUORE VERDE RESOURCES
136
IL CUORE VERDE RESOURCES
137
IL CUORE VERDE RESOURCES
138
IL CUORE VERDE RESOURCES
139
IL CUORE VERDE RESOURCES
5.7 Histogram
5.7.1carpenter
140
IL CUORE VERDE RESOURCES
5.7.2plaster
141
IL CUORE VERDE RESOURCES
5.7.3plumber
142
IL CUORE VERDE TIME SCHEDULE
Chapter 6
Time Schedule
143
IL CUORE VERDE TIME SCHEDULE
144
IL CUORE VERDE TIME SCHEDULE
Define Activities
Sequence
Activities
Estimat Activity
Resources
Estimate
Activity
Durations
145
IL CUORE VERDE TIME SCHEDULE
Figure 6.5.1
146
IL CUORE VERDE TIME SCHEDULE
Figure 6.5.2
147
IL CUORE VERDE TIME SCHEDULE
6.7 Calendar
148
IL CUORE VERDE TIME SCHEDULE
149
IL CUORE VERDE TIME SCHEDULE
150
IL CUORE VERDE TIME SCHEDULE
151
IL CUORE VERDE TIME SCHEDULE
152
IL CUORE VERDE TIME SCHEDULE
6.9 WBS
153
IL CUORE VERDE TIME SCHEDULE
154
IL CUORE VERDE TIME SCHEDULE
155
IL CUORE VERDE TIME SCHEDULE
Refer To WPS
Chapter
156
IL CUORE VERDE TIME SCHEDULE
6.11 Duration
157
IL CUORE VERDE TIME SCHEDULE
158
IL CUORE VERDE TIME SCHEDULE
159
IL CUORE VERDE TIME SCHEDULE
160
IL CUORE VERDE TIME SCHEDULE
161
IL CUORE VERDE TIME SCHEDULE
162
IL CUORE VERDE TIME SCHEDULE
163
IL CUORE VERDE TIME SCHEDULE
164
IL CUORE VERDE TIME SCHEDULE
165
IL CUORE VERDE TIME SCHEDULE
6.14 Resources
166
IL CUORE VERDE TIME SCHEDULE
167
IL CUORE VERDE TIME SCHEDULE
168
IL CUORE VERDE TIME SCHEDULE
169
IL CUORE VERDE TIME SCHEDULE
Hard logic This means the whole project is critical Because if there is
one activity, the whole project will be delayed. He will be late but if
you are present, you will do it Villa project Concrete and finishes A
relationship will appear.
Soft logic
170
IL CUORE VERDE TIME SCHEDULE
1 2 3 4
Missing Missing Negative
Have Lags Relationship Types
Pred Succ Lag
SS,FS
Less than Less than Less than FS 90% or
0 Tasks Less than SF
5% 5% 5% greater
5%
0 0 0 1 344 34 0
0.00% 0.00% 0.00% 0.005 91.00% 8.99%
5 7 8 9
Hard High Negative High
Invalid Dates
Constraints Float Float Duration
Invalid Invalid
Less than Less than Less than Invalid Actual Actual Forecast
5% or Less
5% 5% 5% Start 0 tasks Finsh 0 Start 0
tasks tasks
0 12 0 4 0 0 0
0.00% 3.53% 0.00% 1.18% 0.00% 0.00% 100.00%
171
IL CUORE VERDE TIME SCHEDULE
BREIF
Total Activity (378) Critical Activty (105)
22%
78%
172
IL CUORE VERDE COST MANAGEMENT
Chapter 7
COST MANAGEMENT
173
IL CUORE VERDE COST MANAGEMENT
7. 1.1 Introduction
Admin Office Building Reliable cost estimates are necessary for all projects without
costing It would be impossible to conduct a financial assessment, prepare a business
plan, or draw up detailed budgets or controlling spending, assessing manpower
requirements, or implementing many other administrative procedures. This chapter
shows the cost estimate summary because it may be assigned to a typical project.
Costing: The process of developing a rough estimate of the monetary resources
needed to complete project activities Budgeting: The process of compiling the
estimated costs of individual activities to obtain a project budget.
7.2 Calculations:
The following paragraphs are samples to demonstrate the cost estimate for different
work Packages for the project. the prices used for cost estimate for material are
quoted from suppliers within the approved Contractor vendor list. Equipment rental
cost and labor daily cost are gathered during site visits.
174
IL CUORE VERDE COST MANAGEMENT
175
IL CUORE VERDE COST MANAGEMENT
7.4.2 Equipment
Equipment Cost
Excavator 5000
Concrete pump 2800
Vibrator 450
Loader 3000
Tipper truck 3500
Truck mixer 1500
Roller 2100
176
IL CUORE VERDE COST MANAGEMENT
7.4.3 Manpower
Manpower Cost
Crane labourer 350
Carpenter 350
Painter 300
Skilled labor 250
Concrete crew 1000
Epoxy worker 300
Helper 200
Mason 300
Civil supervisor 450
Operator 300
Painter 300
177
IL CUORE VERDE COST MANAGEMENT
First
Total Lab.& Eq. Cost (LE)/day = (Quantity/ Productivity rate) x
Cost/day + (Cost of Eq.
x no of Eq x Duration)
= (40370/400) x2000 + (5000+10500 + 6000) x 21) =653350 LE.
Second
Material
There is no material
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost = 653350 + 0 =
653350 LE.
Quantity = 2350m³
Productivity rate/day = 250m³
Duration:5 days
178
IL CUORE VERDE COST MANAGEMENT
First
Total Lab.& Eq. Cost (LE)/day = (Quantity/ Productivity rate) x
Cost/day + (Cost of Eq.
x no of Eq x Duration)
= (2350/250) x1350 + (7000+ 2100 + 3000) x 5) = 73190 LE.
Second
Material:
Sand 1m³= 150 LE
=150*2350=352500LE
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost = 352500 +
73190
=425690 LE.
Quantity = 800m³
Productivity rate/day = 250 m³
Duration:2 days
179
IL CUORE VERDE COST MANAGEMENT
First
Total Lab.& Eq. Cost (LE)/day = (Quantity/ Productivity rate) x Cost/day + (Cost
of Eq.
x no of Eq x Duration)
= (800/250) x 1350 + (3500+ 2100 + 3000) x 2) = 21520 (LE).
Second
Material:
Sand 1m³= 150 LE
=150*800=120000 LE
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost = 120000+ 21520
= 141520 LE.
180
IL CUORE VERDE COST MANAGEMENT
Crew No. Cost Equipment Cost/ Material Material Total Lab. &
of / day day cost Eq.&Material
crew Cost (LE)
1Concrete 1Vibrator 450
1000
crews 3Truck mixer 1500 1070470.313
3 350
1Concrete 2800 Concrete 1750
2Carpenter 200
2Helper pump
Total Lab.& Eq. Cost (LE)/day = (Quantity/ Productivity rate) x Cost/day + (Cost
of Eq.
x no of Eq x Duration)
( 605/320)*2100+(450+4500+2800)*1+(1750*605) = 1070470 lE
Deshuttering for PC
Quantity = 605m³
Productivity rate/day = 300m³
Duration:2 days
181
IL CUORE VERDE COST MANAGEMENT
Curing for PC
Quantity =605 m³
Duration:2 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
1Skilled
250 900
labor .. 200 .. ..
1helper
Table 7.11 (Curing for PC cost)
Insulation for PC
Quantity = 491.344 m³
Productivity rate/day = 152m³
Duration:2 days
Total Lab.
No. of Material
Crew Cost/day Material &Material
crew cost
Cost (LE)
1Skilled 250
labor 3 200 Insulation 70 70242
1helper
Table 7.12(Insulation for PC cost)
First
Labor:
Total Lab (LE)/day = (Quantity/ Productivity rate) x Cost/day
Total Lab for PC =16305 LE
Second
Material:
Concrete 1 m³=1750 LE
=1750*605= 1058750 LE
Insulation 1m³= 70 LE
=70*491.344=34394 LE
Third
Equipment:
1Vibrator / 3Truck mixer / 1Concrete pump=23250 LE
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost = 11084+
1093144+23250= 1127478 LE
182
IL CUORE VERDE COST MANAGEMENT
Deshuttering for RC
Quantity = 2935 m³
Productivity rate/day = 300m³
Duration:4 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
1Carpenter 350
3 .. .. 7337.5
2Helper 200
183
IL CUORE VERDE COST MANAGEMENT
Curing for RC
Quantity = 2935m³
Duration:4 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
1Skilled 250
labor .. .. .. 2700
200
1helper
Table 7.16 (Curing for RC cost)
Insulation for RC
Quantity = 5506m³
Productivity rate/day = 152m³
Duration:3 days
Total Lab.
Material
Crew No. of crew Cost/day Material &Material
cost
Cost (LE)
1Skilled 250
labor 15 Insulation 70 401720.65
200
1helper
Steel fixing
For Rc Raft
Quantity = 239.5 m³
Productivity rate/day = 2m³
Duration:8days
Total Lab.
No. of Material
Crew Cost/day Material &Material Cost
crew cost
(LE)
4 steel fixer 300
25 steel 40000 9747650
1helper 200
184
IL CUORE VERDE COST MANAGEMENT
First
Labor:
Total Lab (LE)/day = (Quantity/ Productivity rate) x Cost/day
Total Lab for RC =233508 LE
Second
Material:
Concrete 1 m³=1750 LE
=1750*2935= 5136250 LE
Insulation 1m³= 70 LE
=70*5506=385420 LE
Steel = 239.5*40000=9580000
Third
Equipment:
1Vibrator/ 3Truck mixer /1Concrete pump=23250 LE
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost = 233508 +
15101670+23250= 15358428 LE
185
IL CUORE VERDE COST MANAGEMENT
Steel fixing
Quantity = 37.6 m³
Productivity rate/day = 2 Ton
Duration:7 days
Total Lab.
No. of Material
Crew Cost/day Material &Material
crew cost
Cost (LE)
5 Steel
300
Fixer 3 200
steel 40000 1530320
2Helper
Table 7.20 (Steel fixing for Walls & columns cost)
Pouring concrete
Quantity = 183 m³
Productivity rate/day = 81m³
Duration:1 day
No. Total Lab. &
Cost/ Cost/ Material
Crew of Equipment Material Eq.&Material
day day cost
crew Cost (LE)
Concrete 1Vibrator
1000 1Truck 450
crews 329744.4
3 350 mixer 1500 Concrete 1750
2Carpenter 200 2800
1Concrete
2 Helper pump
Table 7.22 (Pouring concrete for Walls & columns cost)
186
IL CUORE VERDE COST MANAGEMENT
Deshuttering
Quantity =183 m³
Productivity rate/day = 28m³
Duration:4 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
2Carpenter 350
2 200
.. .. 7190
2Helper
Curing
Quantity = 183m³
Duration:4 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
1Skilled
250
labor .. 200
.. .. 1350
1helper
First
Labor:
Total Lab (LE)/day = (Quantity/ Productivity rate) x Cost/day
Total Lab for Walls & columns for second floor =76671 LE
Second
Material:
Concrete 1m³= 1750 LE
Steel 1Ton= 40000 LE
Total material = 1824250 LE
Third
Equipment:
1Vibrator/ 1Truck mixer /1concrete pump=14250 LE
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost = 1915170 LE
187
IL CUORE VERDE COST MANAGEMENT
Steel fixing
Quantity = 47m³
Productivity rate/day = 2 m³
Duration:8 days
Total Lab.
No. of Material
Crew Cost/day Material &Material
crew cost
Cost (LE)
4 Steel
300
Fixer 3 200
steel 40000 1912900
1Helper
Table 7.26 (Steel fixing for Slabs & stairs cost
Pouring concrete
Quantity = 521.5 m³
Productivity rate/day = 320m³
Duration:1day
188
IL CUORE VERDE COST MANAGEMENT
Deshuttering
Quantity =521.5 m³
Productivity rate/day = 32m³
Duration:4 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
1Carpenter 350
6 .. .. 12222.6
2Helper 150
Table 7.28 (Deshuttering for Slabs & stairs cost)
Curing
Quantity = 521.5 m³
Duration:4 days
No. of Total Lab
Crew Cost/day Equipment Cost/day
crew Cost (LE)
1Skilled
250
labor .. .. .. 900
200
1helper
First
Labor;
Total Lab (LE)/day = (Quantity/ Productivity rate) x Cost/day
Total Lab for Slabs & stairs for second floor
=78620 LE
Second
Material:
Concrete 1m³= 1750 LE
Steel 1Ton= 40000 LE
Total material = 2792625 LE
Third
Equipment;
1Vibrator/ 3Truck mixer /1concrete pump=23250 LE
Total Activity Cost = Total Lab.& Eq. Cost + Material Cost =2894495 LE
189
IL CUORE VERDE COST MANAGEMENT
Total Lab.
No. of
Crew Cost/day Material cost &Material
crew
Cost (LE)
Bricks
484137.5
1 Mason 1 300 Cement
8 54743 1112632
Helper 200 Sand
10264
water
First
Labor;
Total Lab (LE)/day = (Quantity/ Productivity rate) x Cost/day
Total Lab for Masonry Works in services rooms for lower basement
=9600 LE
Second
Material:
• Dimension of one Brick= 25×12×6
• Volume of one Brick= 0.26× 0.07 ×0.12= 0.002184
• Number of Bricks in 1m³=1/0.002184= 457 Bricks
• Price of 1m³=2500 (LE)
• Price of 1m³= (2500/2) =1250 (LE)
Total Activity Cost = Total Lab Cost + Material Cost = 828076 LE
190
IL CUORE VERDE COST MANAGEMENT
191
IL CUORE VERDE COST MANAGEMENT
Bid price
Total Direct
Total Direct Activity total price
cost Price factor
Cost
439962276 622738731.5
Site Overhead 45777000
Office
overhead=2% 8799245.5
DC
Total Direct &
494538521.5
In-Direct cost
Risk & Profit =20% 98907704.3 Price factor =
Total cost after Total project Bid / Total
1.41543
adding Risk & 593446225.8 direct cost.
Profit =622738731.5/439962276=
Bond=0.9% 5341016.1
Total cost after
598787241.8
adding Bond
Tax=4% 23951489.67
Total project Bid
622738731.5
192
IL CUORE VERDE COST MANAGEMENT
Total
Total cost Total cost
cost
Civil work
Excavation and backfilling
Excavation 210000 2257500 / 40370 2467500 3492573.5 86.514
Backfilling 18900 155400 472500 3150 646800 915500.12 290.634
Foundation
PC 16305 23250 1093144 605 1132699 1603256.14 2650.01
RC Raft 233508 62000 15101670 2935 15397178 21793627.66 7425.4
B02
Retaining
walls 220704 62000 4426816 538 4709520 6665995.89 12390.32
&columns
Slabs &
stairs & 106641 46500 5440625 1017.5 5593766 7917584.2 7781.40
ramps
B01
Retaining
walls 215846 47500 4426816 538 4690162 6638596 12339.39
&columns
Slabs &
stairs & 120640 23250 4660250 871 4804140 6799923.88 7807.030
ramps
Ground floor
Walls &
74804 14250 1824250 183 1913304 2708147.88 14798.622
Columns
Slabs &
103215 23250 2792625 521.5 2919090 4131767 7922.851
Stairs
First floor
Walls &
50610 14250 1059274 136.728 1124134 1591132.98 11637.21
Columns
Slabs &
89131 23250 2383275 445.3 2495656 3532426.372 7932.68
Stairs
193
IL CUORE VERDE COST MANAGEMENT
Second floor
Walls &
41240 14250 1059274 136.728 1114764 1577870.409 11540.214
Columns
Slabs &
67340 23250 2383275 445.3 2473865 3501582.73 7863.42
Stairs
Third floor
Walls &
57653 14250 1059274 136.728 1131177 1601101.86 11710.124
Columns
Slabs &
67340 23250 2383275 445.3 2473865 3501582.73 7863.424
Stairs
Fourth floor
Walls &
57653 14250 1059274 136.728 1131177 1601101.86 11710.12
Columns
Slabs &
64885 23250 2291275 429.3 2379410 3361888.29 7845.069
Stairs
5th floor
Walls &
47625 9500 921250 115 978375 1384821.3 12041.92
Columns
Slabs &
63322 23250 2222525 424.3 2309097 3268365.16 7702.958
Stairs
6th floor
Walls &
42490 9500 826777 106.73 878767 1243833.17 11654.016
Columns
Slabs &
60440 23250 2136850 398.2 2220540 3143018.93 7893.066
Stairs
7th floor
Walls &
39540 9500 697500 90 746540 1056675.11 11740.83
Columns
Slabs &
52820 23250 1889892.5 348.51 1965962 2782681.59 7984.51
Stairs
194
IL CUORE VERDE COST MANAGEMENT
ArchWorks
Floor
concert …. …. …. 6200 3110000 4401987.3 709.997
Works
Isulation
…. …. …. 3850 1949000 2758673 716.538
Works
Conch /
white …. …. …. 20278 5779116 8179934.16 403.389
Works
Cladding
and stairs …. …. …. …. 2751000 3893847.9 ….
works
Floor
ceramic …. …. …. …. 5999500 8491872.28 ….
works
Paint
…. …. …. 29517 8675821 12280017.32 416.032
Works
carpentery
…. …. …. 302 3296000 4665257.28 15447.8
Works
Metal
…. …. …. …. 1665000 2356690.95 ….
Works
Gypsum
Board and
…. …. …. …. 4924700 6970568 ….
various
Works
Façade
The
…. …. …. 8 176000 249115.68 31139.46
doorway
Cladding
…. …. …. 5000 40000000 56617200 11323.44
destination
Glass
…. …. …. 3000 15000000 21231450 7077.15
curtains
Cladding
destination …. …. …. 328 4104000 5808924.72 17710.13
window
Coupler …. …. …. 235 352574 499043.81 2123.59
195
IL CUORE VERDE COST MANAGEMENT
MEP
Electricity 22925195 22925195 22925195 … 68775585 97347026.28 …
Plumbing 3213601.7 3213601.7 3213601.7 … 9640805 13645884.62 …
HVAC 23032787 23032787 23032787 … 69098362 97803894.53 …
Firefighting 7472050.3 7472050.3 7472050.3 … 22416151 31728492.61 …
Table 7.33 (Recap Sheet)
Summary
196