BILL OF QUANTITY
2 Sub Structure
2.1 Excavation for Foundation m3 540.00 20.00 10800.00
2.2 Filling below Foundation m3 540.00 15.00 8100.00
2.3 100mm thick P.C.C below foundation m2 180.00 50.00 9000.00
2.4 50mm thick P.C.C below Grade slab & tie beam m2 328.00 30.00 9840.00
2.5 R.C.C Isolated Footing m3 40.00 1300.00 52000.00
2.6 R.C.C Tie beam m3 20.00 1400.00 28000.00
2.7 R.C.C Neck Column m3 2.00 1450.00 2900.00
2.8 R.C.C Wall m3 1.00 1500.00 1500.00
2.9 R.C.C Lift wall m3 4.00 1600.00 6400.00
2.9 R.C.C Ground floor slab 100mm thick with
BRC Mesh A-142 & SRC 30 N/mm2 m3 30.00 650.00 19500.00
2.10 1000 Gauge polythene sheet m2 560.00 6.00 3360.00
2.11 Block work below tie beam m2 75.00 95.00 7125.00
2.12 Damp Proof Course Rmt 90.00 12.00 1080.00
2.13 Flexcel sheet around tie beam L.S 1500.00
2.14 Anti-termite treatment L.S 4000.00
2.15 Bitumenous paint m2 950.00 6.00 5700.00
170,805.00
3 Super Structure
3.1 R.C.C Column m3 19.00 1500.00 28500.00
3.2 R.C.C Wall m3 9.00 1550.00 13950.00
3.3 R.C.C Lift wall m3 15.00 1700.00 25500.00
3.4 R.C.C Beam m3 17.00 1450.00 24650.00
3.5 R.C.C Solid Slab m3 127.00 1350.00 171450.00
3.6 R.C.C Staircase m3 5.00 1500.00 7500.00
3.7 R.C.C lintels & Arches m3 8.00 1250.00 10000.00
3.8 R.C.C Parapet m3 45.00 1200.00 54000.00
3.9 R.C.C Misc. work & Décor m3 2.00 1250.00 2500.00
3.10 R.C.C for Water tank base m3 4.00 1200.00 4800.00
342,850.00
Project : (G+1 ) Villa + Service Block
Plot No : 615 - 4078
Location : Nad Al Shiba Second, Dubai
Owner : Engineering Office
Consultant : NEB Architectural & Engineering Consultants
5 Plastering
5.1 Internal Plaster
a Plaster for Ceiling (Spray Plaster) m2 20.00 25.00 500.00
b Ceiling cement Plaster m2 505.00 40.00 20200.00
c Plastering for Wall m2 1670.00 40.00 66800.00
5.2 External Plaster
a Plaster for wall m2 1078.00 45.00 48510.00
5.3 60mm Architectural groove Rmt 139.00 12.00 1668.00
5.4 Plaster Accessories 2500.00
140,178.00
8 External Finishes
8.1 Epoxy paint m2 1078.00 35.00 37730.00
8.2 GRC Moulding Rmt 113.00 125.00 14125.00
8.3 GRC Moulding Rmt 139.00 100.00 13900.00
65,755.00
11 Electrical work
11.1 Electrical work L.S 170000.00
11.2 Light Fittings L.S 78500.00 P.S
11.3 CCTV , Intercom & Dish Antenna system L.S By Owner
11.4 Builder work 10000.00
258,500.00
Project : (G+1 ) Villa + Service Block
Plot No : 615 - 4078
Location : Nad Al Shiba Second, Dubai
Owner : Engineering Office
Consultant : NEB Architectural & Engineering Consultants
14 External Works
14.1 Porcelain tile Dhs 60/-m2 m2 260.00 160.00 41600.00
14.2 Interlock paving Dhs 35/-m2 m2 130.00 100.00 13000.00
14.3 Heel Kerb Dhs 15/-Rmt Rmt 146.00 35.00 5110.00
14.4 Landscaping work L.S By owner
14.5 Wheel Stopper No 4.00 250.00 1000.00
60,710.00
15 Aircondition work
15.1 Aircondition & Mechanical Ventilation work L.S 250000.00 P.S
15.2 Civil work for Aircondition work L.S 10000.00
15.3 Builder work L.S 10000.00
270,000.00
Project : (G+1 ) Villa + Service Block
Plot No : 615 - 4078
Location : Nad Al Shiba Second, Dubai
Owner : Engineering Office
Consultant : NEB Architectural & Engineering Consultants
17 Lift Work
17.1 Supply, Installation & commissioning of
Passanger Lift L.S 150,000.00 P.S
17.2 Builder work 15,000.00
165,000.00
Project : (G+1 ) Villa + Service Block
Plot No : 615 - 4078
Location : Nad Al Shiba Second, Dubai
Owner : Engineering Office
Consultant : NEB Architectural & Engineering Consultants
BILL OF QUANTITY
SERVICE BLOCK
2 Sub Structure
2.1 Excavation for Foundation m3 155.00 20.00 3100.00
2.4 Filling around foundation & Plinth m3 155.00 15.00 2325.00
2.5 100mm thick P.C.C below foundation m2 42.00 50.00 2100.00
50mm thick P.C.C below Grade slab & tie beam m2 123.00 30.00 3690.00
2.6 R.C.C Footing m3 9.00 1000.00 9000.00
2.7 R.C.C Tie beam/Strip Beam m3 13.00 1400.00 18200.00
2.8 R.C.C Neck Column m3 1.00 1450.00 1450.00
2.9 R.C.C Ground floor slab 100mm thick with
BRC Mesh A-142 & SRC 30 N/mm2 m3 11.00 650.00 7150.00
2.10 1000 Gauge polythene sheet m2 185.00 6.00 1110.00
2.11 Block work below tie beam m2 36.00 95.00 3420.00
2.12 Damp Proof Course Rmt 66.00 12.00 792.00
2.13 Flexcel sheet around tie beam L.S 300.00
2.14 Anti-termite treatment L.S 1500.00
2.15 Bitumenous paint m2 285.00 6.00 1710.00
55,847.00
3 Super Structure
3.1 R.C.C Column m3 5.00 1500.00 7500.00
3.2 R.C.C Beam m3 8.00 1450.00 11600.00
3.3 R.C.C Solid Slab m3 13.00 1200.00 15600.00
3.4 R.C.C lintels & Arches m3 1.00 1250.00 1250.00
3.5 R.C.C Parapet m3 10.00 1200.00 12000.00
3.6 R.C.C for Water tank base m3 1.00 1200.00 1200.00
49,150.00
4 Block Work
4.1 Hollow Block for Super structure
a 250mm thk. Insulated Block wall m2 160.00 125.00 20000.00
b 200mm thk. Hollow Block Wall m2 45.00 90.00 4050.00
c 100mm thk. Hollow Block Wall m2 11.00 80.00 880.00
d 50mm Insulation on column & Beam L.S 2500.00
e G.I. Ties & mesh L.S 400.00
27,830.00
Remark
Project : (G+1 ) Villa + Service Block
Plot No : 615 - 4078
Location : Nad Al Shiba Second, Dubai
Owner : Engineering Office
Consultant : NEB Architectural & Engineering Consultants
SERVICE BLOCK
8 External Finishes
8.1 Epoxy paint m2 443.00 35.00 15505.00
8.2 GRC Moulding Rmt 33.00 100.00 3300.00
18,805.00
SERVICE BLOCK
11 Electrical work
11.1 Electrical work L.S 17000.00
11.2 Light Fittings L.S Incl.in Villa P.S
11.3 CCTV , Intercom & Dish Antenna system L.S By Owner
11.4 Builder work 500.00
17,500.00
14 Aircondition work
14.1 Aircondition & Mechanical Ventilation work L.S 25000.00
14.2 Civil work for Aircondition work L.S 1500.00
14.3 Builder work L.S 2500.00
29,000.00
Project : (G+1 ) Villa + Service Block
Plot No : 615 - 4078
Location : Nad Al Shiba Second, Dubai
Owner : Engineering Office
Consultant : NEB Architectural & Engineering Consultants
NOTE