Professional Documents
Culture Documents
VKP - Apartment Schedule 09.01.2024
VKP - Apartment Schedule 09.01.2024
1 7 W3 Yars WP AN Sanitation C C C C C C C C C C C C C C C C
2 8 W3 Yars WP AN Sanitation C C C C C C C C C C C C C C C
Cluster -12
3 9 W3 MT WP AN Sanitation C C C C C C C C C C C C C C
4 10 W3 MT WP AN Sanitation C C C C C C C C C WIP WIP WIP WIP
5 104 E14 RG Entrp Namashivay C C C C C C C C C C C C C C C WIP WIP WIP WIP C
Cluster -1
6 105 E21 RG Entrp Namashivay C C C C C C C C C C C C C C C WIP WIP WIP C C
7 106 W2 Superior Namashivay C C C C C C C C C C C C C C C WIP C
8 107 W2 Cluster -2 Superior Namashivay C C C C C C C C C C C C C C C C C C C C C
9 108 W2 Superior Namashivay C C C C C C C C C C C C C C C C C C C C C
10 121 W1 Superior Namashivay C C C WIP WIP WIP
11 122 W1 Superior Namashivay C C C WIP WIP WIP C UPTO PL
12 123 W1 Superior Namashivay C C C WIP WIP WIP C
13 124 W2 Superior Namashivay C C C C C C C C C C C C C C C C
14 125 W2 Superior Namashivay C C C C C C C C C C C C C C C C
15 126 W2 Superior Namashivay C C C C C C C C C C C C C C C C
Cluster -3
16 132 E2 Superior Namashivay C
17 133 E2 Superior Namashivay C C C C C C C C C C
18 134 E1 Superior Namashivay C C C WIP C C WIP WIP C
19 135 E1 Superior Namashivay C C C WIP C C WIP WIP C UPTO PL
20 136 E1 Superior Namashivay WIP WIP WIP C UPTO PL
21 137 E1 Superior Namashivay
22 179 E1 RG Entrp SB ENG C C C C C C C C C C
Cluster -7
23 180 E1 RG Entrp SB ENG C C C C C C C C C C
24 186 W2 Yars SSG Infra C WIP WIP C
25 187 W2 Superior SSG Infra C C C C C C C C C C C
26 188 W2 Superior BD Panda C C C C C C C C C C C C C C C C C C C
27 189 W2 Superior BD Panda C C C C C C C C C C C C C C C C C C C C
28 190 W2 Superior SSG Infra C C C C C C C C C C C C C C C C C
29 191 W2 Cluster -8 Superior SSG Infra C C C C C C C C C C C C
30 192 W2 Superior SSG Infra C C C WIP C C WIP
31 193 E2 VL Enterprices SSG Infra C C C C C C C C C C C C C C C C C C
32 194 E2 VL Enterprices SSG Infra C C C C C C C C C C C C C C C C C C
33 195 E2 VL Enterprices SSG Infra C C C C C C C C C C C C C C C C C C
34 196 E2 VL Enterprices SSG Infra WIP C C
0 0 0 0 0 0
VERTEX KINGSTON PARK
43 VILLA'S THIRD PRIORITY (15-05-2023)
WP Base Coat PVC WP Top Coat CPVC Flush Tank & Ledge Wall Villa Flooring
Water Diverters Electrical Toilet Door&V Toilet Villa
Sr.No Villa No Model Cluster No Proofing Plumbing Patch Putty Tile ent Marble External Compound
Contractor GF FF SF GF FF SF GF FF SF GF FF SF GF FF SF GF FF SF TILE MARBLE Wall
Contractor Work Dado Jambs Fooring Cladding
1 30 E2 Premiere AN Sanitation C UPTO PL
2 31 E2 Premiere AN Sanitation C
3 32 E2 Premiere AN Sanitation WIP WIP WIP C
4 33 E2 Premiere AN Sanitation WIP WIP WIP C
Cluster -14
5 34 W2 Premiere AN Sanitation C C C C C C C
6 35 W2 Yars WP AN Sanitation C C C C C C C
7 36 W2 Yars WP AN Sanitation C
8 37 W2 Yars WP AN Sanitation C UPTO PL
9 127 W4
10 128 W4
Cluster -3A
11 129 E4
12 130 E4 Namashivay
13 148 E2 Superior BD Panda WIP WIP WIP
14 149 E2 Superior BD Panda WIP WIP WIP
15 150 E2 Superior BD Panda WIP WIP WIP
16 151 E5 Superior BD Panda WIP WIP WIP
17 152 W5 Superior BD Panda C C C
18 153 W1 Superior BD Panda C C C C C C C C C C C C C C C
19 154 W2 Superior BD Panda C C C C C C C C C
20 155 W2 Superior BD Panda C C C C C C C C C
Cluster -05
21 159 E2 Superior BD Panda C C C C C C C C C C C C C C C
22 160 E2 Superior BD Panda WIP WIP WIP
23 161 E1 Superior BD Panda C C C
24 162 E5 Superior BD Panda C C C
25 183 W2 Yars WP SSG Infra C C C
26 184 W2 Yars WP SSG Infra C C WIP C
27 185 W2 Yars WP SSG Infra C WIP WIP C
28 197 E2 VL Enterp SSG Infra WIP C C
29 198 E2 Cluster -08 SSG Infra
30 199 E2 SSG Infra
31 200 E2 SSG Infra
32 201 E2 SSG Infra
33 202 E2 SSG Infra
34 210 W3 Safex Plumbing WIP WIP WIP
35 211 W3 Safex Plumbing
36 212 W3 Safex Plumbing WIP WIP WIP
37 215 E3 Safex Plumbing
38 216 E3 Safex Plumbing
Cluster -09
39 217 E3 Safex Plumbing
40 219 E3 Safex Plumbing
41 220 E3 Safex Plumbing
42 221 E3 Safex Plumbing
43 224 E9 Safex Plumbing
Completed 12 12 11 6 6 6 4 4 4 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 0 8
WIP 10 10 11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
External
Villa Setback Compound Plumbing Ground Earth Pits Feature Wall Shaft
Leveling Wall Fencing Shafts Sanitary Louvers
Pipe Line
C
C
2 0 0 0 0 0 0
0 0 0 0 0 0 0
VKP_ NALLAGANDLA APARTMENT G + 4 RESIDENTIAL BUILDING CONSTRUCTION SCHEDULE
Duration in Baseline Baseline Actual
Sl no. Task Name Actual Finish
days Start Finish start
FOUNDATIONS
EXCAVATION 20 18/12/2023 07/01/2024
BACK FILLING UPTO OUTER PLINTH BEAM BOTTOM LEVEL(IN LAYERS) 7 21/01/2024 28/01/2024
II Structure Work
6 of 14
VKP_ NALLAGANDLA APARTMENT G + 4 RESIDENTIAL BUILDING CONSTRUCTION SCHEDULE
Duration in Baseline Baseline
Sl no. Task Name days Start Finish Actual start Actual Finish
VI Waterproofing work
7 of 14
VKP_ NALLAGANDLA APARTMENT G + 4 RESIDENTIAL BUILDING CONSTRUCTION SCHED
Duration in
Sl no. Task Name
days
Project Schedule
I Excavation 90
II Structure Work
Foundation works 40
Septic Tank 20
Lift Pit 15
Plinth Beam 20
Grade Slab 20
Underground Sump 10
Ground Floor 20
First Floor 20
Second Floor 20
Third Floor 20
Fourth Floor 20
Terrace Floor 20
Cellar-01 10
Ground Floor 20
First Floor 20
Second Floor 20
Third Floor 20
Fourth Floor 20
Terrace Floor 10
Cellar-02 10
Cellar-01 10
Ground Floor 20
First Floor 20
Second Floor 20
Third Floor 20
Fourth Floor 20
Terrace Floor 10
East Side 30
West side 30
south side 30
North side 30
VI Waterproofing work
Retaining wall 60
Lift Pit 20
Underground Sumps 30
Toilet Waterproofing works 207
Super Finishes (Flooring , dado , Granite, Doors & Windows and Cp &
X 200
Sanitary etc.)
XI External Painitng works 60
10/10/2023 08/10/2025
10/10/2023 08/01/2024
16/02/2024 02/03/2024
03/03/2024 18/03/2024
23/03/2024 02/05/2024
19/03/2024 29/03/2024
08/04/2024 23/04/2024
24/04/2024 09/05/2024
29/05/2024 18/06/2024
08/07/2024 28/07/2024
17/08/2024 06/09/2024
26/09/2024 16/10/2024
05/11/2024 25/11/2024
15/12/2024 04/01/2025
19/06/2024 29/06/2024
11/07/2024 21/07/2024
02/08/2024 22/08/2024
17/09/2024 07/10/2024
27/10/2024 16/11/2024
06/12/2024 26/12/2024
15/01/2025 04/02/2025
15/02/2025 25/02/2025
30/06/2024 10/07/2024
22/07/2024 01/08/2024
01/09/2024 21/09/2024
17/10/2024 06/11/2024
26/11/2024 16/12/2024
05/01/2025 25/01/2025
14/02/2025 06/03/2025
07/03/2025 17/03/2025
17/03/2025 16/04/2025
17/03/2025 16/04/2025
16/04/2025 16/05/2025
16/04/2025 16/05/2025
28/07/2024 26/09/2024
28/07/2024 17/08/2024
12/08/2024 11/09/2024
01/09/2024 27/03/2025
16/12/2024 30/06/2025
16/12/2024 16/05/2025
16/12/2024 10/06/2025
10/01/2025 29/07/2025
15/06/2025 14/08/2025
11/03/2025 08/09/2025
08/09/2025 08/10/2025
VERTEX KINGSTON PARK
50 VILLA'S SECOND PRIORITY (11-04-2023)
WP Base Coat PVC WP Top Coat CPVC Flush Tank & Ledge Wall Villa Flooring
Water Diverters Electrical Toilet Door&V Toilet
Plumbing Compound Villa Setback
Sr.No Villa No Model Cluster No Proofing Patch Putty Tile ent Marble
Contractor GF FF SF GF FF SF GF FF SF GF FF SF GF FF SF GF FF SF TILE MARBLE Wall Leveling
Contractor Work Dado Jambs Fooring
1 13 E7 MT WP AN Sanitation
2 14 E3 MT WP AN Sanitation WIP WIP WIP C UPTO PL
3 20 W3 Cluster -13 MT WP AN Sanitation WIP WIP WIP C
4 21 W3 MT WP AN Sanitation WIP WIP WIP C
5 22 W3 MT WP AN Sanitation WIP WIP WIP C UPTO PL
6 23 W3 MT WP AN Sanitation
7 30 E2 Premiere AN Sanitation C UPTO PL
8 31 E2 Premiere AN Sanitation C
9 32 E2 Premiere AN Sanitation WIP WIP WIP C
10 33 E2 Premiere AN Sanitation WIP WIP WIP C
11 34 W2 Premiere AN Sanitation C C C C
12 35 W2 Cluster -14 Yars WP AN Sanitation C C WIP C
13 36 W2 Yars WP AN Sanitation C
14 37 W2 Yars WP AN Sanitation C UPTO PL
15 38 W1 Yars WP AN Sanitation C UPTO PL
16 39 W1 Yars WP AN Sanitation C UPTO PL
17 40 W1
18 48 E2 SLV WP MACT ENG WIP WIP
Cluster -15
19 49 E2 SLV WP MACT ENG WIP WIP
20 67 E1 MACT ENG
21 68 E2 Cluster -16 MACT ENG
22 70 E2 MACT ENG
23 127 W4
24 128 W4
Cluster -3A
25 129 E4
26 130 E4 Namashivay
27 141 W5 Superior BD Panda
28 148 E2 Superior BD Panda
29 149 E2 Cluster -4 Superior BD Panda
30 150 E2 Superior BD Panda
31 151 E5 Superior BD Panda
32 152 W5 Superior BD Panda WIP WIP WIP
33 153 W1 Superior BD Panda C C C C C C C C WIP
34 154 W2 Superior BD Panda C C C C C C
35 155 W2 Superior BD Panda C C C WIP WIP WIP
Cluster -05
36 159 E2 Superior BD Panda C C C C C C C WIP WIP
37 160 E2 Superior BD Panda
38 161 E1 Superior BD Panda WIP WIP WIP
39 162 E5 Superior BD Panda WIP WIP WIP
40 183 W2 Yars WP SAFEX C WIP WIP
41 184 W2 Cluster -8 Yars WP SAFEX C WIP WIP
42 185 W2 Yars WP SAFEX C WIP WIP
43 197 E2 VL Entrp SSG Infra WIP WIP WIP C
Completed 9 6 5 3 3 3 2 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 9 0