WTPS Daily Generation Report 13.03.2024

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Wanakbori Daily Generation Report Date: 13.03.

2024

Genration SOC
Unit No. PLF (%) PAF (%) Remarks
(MWH) (ml/KWH)
Unit No.1 put under RSD at 05:00 hrs on 13.03.2024 as per SLDC instruction. Unit was
1 2781 55.18 0.00 tripped on loss of all fuel at 16:57 hrs dtd 12.03.2024 due to PA fan 1A tripped on
electrical fault.

2 3728 73.97 4.60 Frequent feeders tripped due to stone.

Unit no. 3 stopped under FSD from 20:53 hrs 05.03.2024 for condenser low vacuum
problem (HP water jetting will be carried out), Moreover, HPH 7 coil leakage
3 0 0.00 0.00 attending work with various other defects attending work will be carried out. Unit Lit
72.09 up at 23:10 hrs dtd 12.03.2024 & Syn at 03:47 hrs dtd 13.03.2024, Turbine tripped on
IP stress high at 04:00 hrs and again syn at 05:37 hrs dtd 13.03.2024.

4 0 0.00 0.00 Unit No.4 stopped under RSD at 20:04 hrs on 26.02.2024 as per SLDC instruction.

5 0 0.00 0.00 Unit No.5 stopped under RSD at 08:18 hrs on 27.02.2024 as per SLDC instruction.

6 0 0.00 0.00 Unit No. 6 kept under RSD from 17:00 hrs 29.02.2024 as per SLDC instruction.

1-6 6509 21.52 3.29

7 4692 93.10 85.22 0.00

Unit no. 8 stopped at 05:40 hrs on dtd 10.03.2024 under forced outage as Boiler tube
8 0 0.00 0.00 0.00
leakage observed at 68 mtr LHS in FSH area in consultation with SLDC.

Station 11201 20.56 47.19 1.91