TRADE/ACTIVITY CONTROL SHEET - PILING (Bored)

Project Contract No
Contractor
Area/Location of works
Date Sheet Number

Yes/ Date Sign Off


NoN/a Completed

General

Bored Pile No: ……………...................................................

Work Methodology Reviewed and Approved

Hazard and Risk Assessment (Form HS09) completed?

Environmental mitigation measures in place?

Drawing number and revision for task:


……………………………………...........................................

Drilling

Confirm set out/location prior to drilling

Drilling Log completed (documentation attached)

Pile Drilling total depth:

● design ………............................................................

● actual …………..........................................................

Bell Diameter:

● design ……………………….…….................................

● actual …………….......................................................

Bell height:

● design …………....................................................

● actual ……………......................................................

FORM IPI 22.06 – TRADE ACTIVITY CONTROL SHEET PILLING BORED


1
Casing Used

Dewatering, clean out and spoiling

Levels

RL Ground Level: ………………...................................................

RL Founding Depth: …………......................................................

Actual RL Founding Depth:..........................................................

Difference: ………………..............................................................

Finished Pile Reduced Level (RL):.............................................

Hold Point for Inspection prior to reinforcement:

Reinforcing to Pile

Drawing/Detail reference for reinforcing (including Revision):

………………………………………………………………………..
Confirm main bar diameter and grade correct

Confirm spiral bar diameter, grade and pitch correct

Confirm stirrup bar diameter, grade and spacing

Confirm lap lengths correct

All spaces, ties and spreaders correct to achieve spacing and


cover

Placement of reinforcing correct and aligned

Hold Point for Inspection prior to concrete:

Concrete to Pile

Placing equipment on site and operational

Concrete placement method: …………........................................

Concrete Sump test taken and recorded at:................................

Concrete samples taken for strength testing (results to be


attached)

Casing removed

Pile cap/joint prepared correctly

(Results documentation attached)

FORM IPI 22.06 – TRADE ACTIVITY CONTROL SHEET PILLING BORED


2
FORM IPI 22.06 – TRADE ACTIVITY CONTROL SHEET PILLING BORED
3
Time period

Backfill
commenced : ...............................................................................
(date & time)

Backfill
completed: ...............................................................................
(date & time)

Sign off Activity Complete:

The signing of this Control Sheet and Inspection by UNOPS does not relieve the Contractor from any contractual
obligations detailed within the Contract Documents

UNOPS Representative: Contractors Representative:

Date: ………………………....... Date: ………………………..........

FORM IPI 22.06 – TRADE ACTIVITY CONTROL SHEET PILLING BORED