Setup and Procedures

1. Sand ply-wood and apply an appropriate finish


2- Layout positions for circuit components
3- Position Main Switch and Distribution Panel
4- Secure them to the board with a drywall screw
5- Connect supply conductors to the main switch and then to the distribution panel.
Connect all conductors, (live, neutral, earth) to their respective terminals.
Use the 20 Amp breaker for the main switch
NB: DO NOT CONNECT TO THE POWER SOURCE AS YET
6- Position Switchbacks and the Socket Outlet on the circuit board and secure them
with drywall screws
7- Measure and cut trunking to the respective length according to the layout
8- Position and secure trunking at their respective position using dry-wall screw
9- Secure the socket and fluorescent lamp in the respective position on ply-wood using
dry-wall screw
10- Place conductors in the trunking and connect the neutral and earth to their
respective terminals in the distribution panel, lights and switch
11- Connect the live conductor to the circuit breakers, through the switches, light and
socket outlet.
- 10 Amp for lights
- 15 Amp for socket outlet
12- Test for continuity and assemble switches and socket-outlet covers
13- Power up the circuit and test to record observation