Under Construction Phases that is Phase 1: Mobilization and Site Preparation include the

following and adjust accordingly:Providing Services such as; Lighting, Electrics, Gas & phones
Portakabins 10m × 3m Offices & welfare facilities Shower & Toilet rooms Office with 3 desks,
chairs & windows Other office furniture and first aid boxes Meeting room Rest area with tables
and benches, fridge, microwave, kettle etc. Changing/drying room 3 no. laptops, phones and
printer/scanner Consumables (tea/coffee, cleaning etc.) Secure storage Dry materials store
Manual equipment/plant store Unisex portable cabin with chemical toilet and cold-water
sink/tank Signage Traffic Management signs – Temporary Site specific & Traffic Management –
Permanent - Total provisional sum 3200 Site CCTV Camera linked to local police Security 1
person security 24hrs. Also provide the numbers of the tangible services as you see
relevant ,typical for this construction and considering the number of workers and users of the
site.Use the following information below to make an informed decision on the above
instruction.Below is what the project team will/would typically compose of.The decision of what
personnel should match the activities you will develop/or have developed.Here's what the team
could/should comprise:(Remember the decision of what personnel to include should match the
activities you will develop/or have developed so do not include irrelevant human resource.
Operative (varies by skill level) Plant Operator / craftsman (varies by skill level) Supervisor /
Banksman Foreman / Site Agent Trainee Engineer / Apprentice Graduate Engineer Senior
Engineer Principal Engineer For Earthworks: Excavation 1 plant operator, 1 banksman Filling 1
plant operator, 2 operatives Compaction 1 plant operator Geotextiles 1 supervisor (20% of time),
2 operatives Horticultural 2 operatives Reinforced concrete works if any; Formwork 1 joiner, 1
operative Reinforcement 1 steel fixer, 1 operative Placing 2 operators Striking 2 operators
Pavement works: Asphalt 1 plant operator, 3 operatives Edging/divider 2 operators Lining 1
operative Milling/scarifying 1 plant operator, 2 operatives.These new instructions should
consider earlier given instructions for example since the pavement is to be Cellular grid pavers
50 mm Grid ForceTM cellular paver installed on 150 mm thick compacted type 3 sub-base in
accordance with manufacturer’s instructions for gravel installation and If no existing pavement,
there'll be No divider,No edging, Unsegregated thus typically divider operators, and asphalt
operatives here would typically not be needed.These are the kind of logic decisions I need you
to follow in this new script. AdditionaIly,I also need you to develop a logical construction
sequence with estimated durations, plant resource requirements, and identification of critical
path is optimized to minimise the construction duration.Use all the above information provided
to make this decision(of Optimization)and Activity & material costs and duration rates, plant and
equipment hire rates,Personnel and gang rates,Materials and associated activity rates as
attached below(The number values after the hyphen i'm using represent the cost in £/week):
Activity & material costs and duration rates(£/week). Site Clearance-1000 Services Lighting,
Electrics, Gas & phones-500 Portakabins 10m × 3m,Offices & welfare facilities which may
include: Shower & Toilet rooms -300 Office with 3 desks, chairs & windows -120 Other office
furniture and first aid boxes one-off cost -200 Meeting room -120 Rest area with tables and
benches, fridge, microwave, kettle etc-150 Changing/drying room -120 3 no. laptops, phones
and printer/scanner - 60 Consumables (tea/coffee, cleaning etc.)-20 Secure storage Dry
materials store -260 Manual equipment/plant store -400 Unisex portable cabin with chemical
toilet and cold-water sink/tank -160 Signage Traffic Management signs(Temporary) Total
provisional sum-1700 Site specific & Traffic Management – Permanent - Total provisional sum-
3200 Site CCTV Camera linked to local police -135 Security 1 person security 24hrs @ £25/hr-
4200 Plant and equipment hire rates(£/week) Fencing: Heras site boundary fencing panel system
3.5m×1.8m-5 Vehicle/Pedestrian gate panel 3.5m×1.8m-10 Chapter 8 fencing system 2m
length-5 Surveying: Laser level & staff -95 Cable detector-70 Street works: Road crossing plates
(pedestrian, fibreglass 1.2m×1.4m)- 20 Road crossing plates ,steel 1.2m×2.4m-30 Pumps Petrol
powered pump and hoses-55 Groundcare Chipper,petrol-175 Hedge trimmer-60 Turf cutter -
190 Fuel storage: 105L fuel caddy-55 250 gal water bowser & pressure washer system-135
Cutting: Floor saw, petrol -110 Angle grinder-90 Concrete Vibrating poker,petrol-90
Compactors: Compactor plate 450mm petrol-120 Access/support: Trench sheets 2m×2.5m-10
Trench struts -5 Extension ladder-35 Loaders: JCB skid steer loader with standard bucket-320
Pallet forks -20 Sweeper collector-95 Muck grab-45 Rollers: 70cm pedestrian single drum
vibrating roller-75 100cm ride on twin drum vibrating roller-135 Telehandler 18T 4WD Rotating
telescopic handler,18m reach, 5T capacity-600 Crane jib-80 2-person work platform-90
Rehandling bucket 2m³ capacity-40 Excavators: 5T back-hoe excavator 2m width 4m dig depth-
400 Hydraulic breaker attachment-450 Dumper: 2T straight tip-110 Generator: Diesel electric
generator 110V-300 Compressor: Silenced compressor c/w generator (all petrol equipment can
be electric)-100 Heavy breaker -25 Air pick -25 Cranes: Mobile crane 30T capacity, reach 20m
inc. operator (day rate £750)-3500 Tower crane 10T capacity, reach 30m inc. operator (day rate
£750)-4200 Include only relevant for this work as per the step by step activities you will produce.
Personnel and gang rates(£/hr).(Note that the numbers after the hyphen in this section are now
representing cost in £/hr.) Operative (varies by skill level)-18 Plant Operator / craftsman (varies
by skill level)- 25 to 30 Supervisor / Banksman-35 Foreman / Site Agent-50 Trainee Engineer /
Apprentice-30 Graduate Engineer-40 Senior Engineer-60 Principal Engineer-120 Earthworks:
Excavation: 1 plant operator, 1 banksman-60 Filling: 1 plant operator, 2 operatives-60
Compaction: 1 plant operator 30 Geotextiles: 1 supervisor (20% of time), 2 operatives-40
Horticultural: 2 operatives-35 RC(Reinforced Concrete) Formwork:1 joiner, 1 operative-45
Reinforcement:1 steel fixer, 1 operative-40 Placing: 2 operators-35 Striking: 2 operators-35
Pavement: Asphalt: 1 plant operator, 3 operatives-80 Edging/divider: 2 operators -35 Lining: 1
operative -20 Milling/scarifying: 1 plant operator, 2 operatives-60 Materials and associated
activity rates(Rate/hr)unless specified otherwise.(Material costs is provided as a total in each
description).Also use the units as provided by the rates after the hyphen.Material costs are the
direct materials cost to manufacture a given product or provide a certain service.This cost is
provided as a total in each description in(£).The arrangement is as follows,Material costs in (£)
followed by the respective associated activity rates with the appropriate units of
measurement(for example (m²) shortform of square metre. I hope the numbers don't confuse
you. Earthworks: Description: Excavate topsoil up to 0.25m thick, disposal on site - 0£, 30 m²
Excavate small pit for foundation up to 1.0 m deep - 0£, 5 m³ Disposal/storage of excavated
material on site - 0£, 20 m³ Filling using excavated topsoil from site per m³ - 0£, 15 m³ Filling
using imported topsoil per m³ - 30£, 15 m³ Macadam: Surface dressing inc. gravel topping, per
m²-20£, 20 m² Asphalt concrete base course per tonne-40£, 2 m³ Asphalt concrete surface
course per tonne 55£, 1 m³ Asphalt concrete surface course (coloured) per tonne 60£, 1 m³
Pavement removal: Milling and disposal on site or used as fill, 75mm thick- 90£, 25 m² Scarifying
per m² (inc. specialist plant and operator)- 75£, 25 m² Whiteline painting: Continuous 60mm
reflective whiteline marking, inc. allowance for periodic arrows and shapes- 2£, 30 m Aggregate:
Type 1/3 crushed concrete per tonne, compacted-25, 5 m³ Type 1/3 crushed limestone/granite
per tonne, compacted- 30, 5 m³ 2-6mm limestone gravel per tonne- 160, 5 m³ 10m crushed
limestone gravel per tonne- 130, 5 m³ Geotextile: Woven fabric, per 4.5m×100m roll- 160£, 30
m² Non-woven fabric, per 4.5m×100m roll- 310£, 30 m² Geogrid, 20/20 biaxial, per 4m×75m
roll- 420£, 30 m² Bespoke: Self-binding gravel per tonne-120£, 5 m³ Gridforce GF50, per m² -
22£, 20 m² RC: Ready mix concrete per m³ -120£, 5 m³ Shaped rebar per tonne- 1500£, 0.1 T
Formwork & falsework per m²- 150£, 2 m² Rubble drain 20 mm stone aggregate fill per m³ -75£,
3 m³ Edging Timber, each 25mm×100mm×3m pressure treated softwood-6£ , 20 m Precast
concrete, each 25mm×100mm×0.5m- 1£, 15 m Culvert: Precast concrete culvert 1m² per m
length- 200 Bench seat: 2.0 m long bench seat, each depending on material pre-cast
concrete ,timber, painted steel-1100£,850£, 800£ respectively, 1 Number Guard rails: 1.0m
galvanized steel tube fencing in concrete footing, per m- 250£, 6 m Horticultural: Cut-back scrub
bushes and feed through chipper - 0£, 10 m² Wastage: Removal from site & landfill tax per m³,
5m³ per lorry- 150£, 5 m³.You also need to consider the notes below in developing the output I
require.(Apply the notes where relevant.i.e to match the step by step activities.These activities
need to be adjusted to be more technically detailed as outlined in the Materials and associated
activity rates provided above so adjust the earlier activities to match these descriptions as
provided by the Principal Engineer to be used in the tendering process.Remember you are a
Contractor responding to a client's brief. Notes: 1. Compacted layers up to 225 mm thick shall
be laid as one. Typical compaction rates can be assumed to be 30% for Type 1/3 aggregates (i.e.
a 100 mm thick compacted Type 1/3 layer should start 130 mm thick) and require 10 passes of
vibrating rollers/plates. This is included in the /hr activity durations. The effectiveness of the
compaction process should be trialled and assessed on site as it is highly variable depending on
machine type, number of passes and moisture content of gravel at installation. 2. Compacted
density of Type 1/3 road base can be assumed to be 2.0 tonne/m³. 3. Asphalt compaction rate
can be assumed to be 20% and a compacted density of 1.7 tonne/m³. 4. Breedon gravel
compaction rate can be assumed to be 50% and a compacted density of 2.0 tonne/m³. 5.
Bulkage of excavated material may be assumed to be 20%, i.e. 1m³ of excavated soil will have a
bulk volume of 1.2 m³. Also I'd like an additional section of Cost estimation using standard rates
for tender(Provided in the sections above) and estimate the cost of the construction of the
proposed development and optimise it in conjunction with the construction programme to
produce a budget.The information I'm referring to is the Activity & material costs and duration
rates, Plant and equipment hire rates,Personnel and gang rates, and Materials and associated
activity rates provided above.Use this informati