INSTRUCTION: Select the correct answer for 7. A spherical triangle has a radius of 6 m. each of the following questions. Mark only Compute the area of a bi-rectangular one answer for each item by shading the box spherical triangle having an angle of 80°. corresponding to the letter of your choice A. 46.18 m2 C. 50.27 m2 on the answer sheet provided. STRICTLY NO B. 48.36 m 2 D. 52.72 m2 ERASURES ALLOWED. GOOD LUCK. 8. A spherical triangle ABC has an angle C = NOTE: A times B is represented by A×B or 90° and sides a = 50° and c = 80°. Find the A*B. A raised to the power n is value of side b. expressed as A^n. All problems are 1 A. 73.34° C. 74.33° point each. B. 74.44° D. 73.43°
9. Determine the length of the chord common
1. A cylindrical tank, 4m in diameter and 6m to the circles x2 + y2 = 64 and x2 + y2 – 16x high is full of water. It is then tilted to = 0. a position enough for the water surface to A. 8.94 C. 6.93 cut the diameter of the base. How much water B. 27.71 D. 13.86 is retained? A. 12 m3 C. 16 m3 10. A small circle is inscribed in a circular B. 14 m3 D. 18 m3 sector of radius 12cm and a central angle of 600. Compute the area of the small circle if 2. A concrete pavement 8 m wide and 150 mm it is tangent internally to the radius and thick is to be provided with a center the arc of the sector. longitudinal joint using 12 mm bars. The unit A. 50.27 cm2 C. 25.13 cm2 weight of concrete is 2400 kg/m3. Coefficient B. 75.40 cm2 D. 12.57 cm2 of friction of the slab on the subgrade is 2.0. Assuming an allowable stress in tension 11. The sides of an equilateral triangle are for steel at 138 MPa, determine the spacing increasing at rate of 27 in/sec. How fast is of bars in mm. the triangle’s area increasing when the A. 610.20 C. 552.42 sides of triangle are each 18 inches long? B. 305.10 D. 276.21 A. 420.89 C. 400.89 3. A piece of wire 10 m long is cut into two B. 402.89 D. 422.89 pieces. One piece is bent into a square and the other is bent into equilateral triangle. Situation 1: What is the perimeter of the square so that A grade of -5% is followed by a grade of the total area enclosed is minimum? +1%, the grades intersecting at the vertex A. 4.35 m C. 7.53 m (Sta.10+060). The change of grade is B. 6.98 m D. 5.65 m restricted to 0.40% in 20m. 12. Compute the length of the vertical 4. Find the equation of the line bisecting parabolic sag curve in meters. the acute angle between the lines x + y = 3 A. 200 m C. 300 m and 7x – y + 4 = 0. B. 250 m D. 350 m A. 12x + 4y = 11 C. 11x + 3y = 17 13. Find the value of K (length of curve for B. 2x – 6y = 16 D. 3x + 11y = 17 every 1% of change in slope/grade). A. 25 m C. 75 m 5. A satellite camera takes a rectangular B. 50 m D. 100 m shaped picture. The smallest region that can be photographed is a 5 km x 7 km rectangle. Situation 2: As the camera zooms out, the length L and An area bounded by the curve y = x^2 and the width W of the rectangle increase at a rate lines y = 0 and x = 2. of 3 km/sec. How long does it take for the area A to be at least 7 times its original size? 14. Find the volume generated if the area is A. 3.63 s C. 3.66 s revolved about the x – axis. B. 3.23 s D. 3.33 s A. 23.75 C. 20.11 B. 25.13 D. 24.47 6. The maximum allowable rate of crashes at 15. Find the volume generated if the area is intersections is 9 per million entering revolved about the y – axis. vehicles. At an intersection of 2 roadways, A. 23.75 C. 20.11 average daily traffic (ADT) values are B. 25.13 D. 24.47 10,000 and 8,265. Determine the maximum 16. Find the volume generated if the area is number of crashes per year before corrective revolved about the y = 4. action is needed. A. 44.28 C. 42.17 A. 30 crashes C. 60 crashes B. 48.36 D. 46.91 B. 40 crashes D. 80 crashes APRIL 2024 CE BOARD EXAM REFRESHER MSTE - 14 17. It is the process where a load is prepared for lifting using a lifting machine. The main part of this process is the tying up of the load with sling and other connecting devices so that the load could be hooked onto a crane. A. Lifting C. Loading B. Rigging D. Handling
18. Complete or partial dismantling of a
building or structure by pre-planned and controlled methods or procedures. A. Demolition C. Breaking B. Clearing D. Grubbing
19. It is capable of spreading,
consolidating, and finishing a concrete slab without the use of conventional forms. A. dust palliative C. tack coat B. fog seal D. slipform paver
20. It is a very versatile machine that has
the longest reach for digging and dumping of any member of the crane shovel family. A. dragline C. backhoe B. crane D. excavator
21. The bucket volume contained within the
bucket when following the outline of the bucket sides is called: A. Struck capacity B. Bucket capacity C. Plate line capacity D. Waterline capacity
22. Assumes a level of material flush with
the lowest edge of the bucket. A. Struck capacity B. Bucket capacity C. Plate line capacity D. Water line capacity
23. The bucket capacity when the load is
struck off flush with the bucket sides. A. Struck capacity B. Bucket capacity C. Plate line capacity D. Waterline capacity
24. It represents those components of cycle
time other than travel time. A. Time C. Waiting time B. Stop time D. Fixed time
25. This represents the travel time required
for a unit to haul material to the unloading site and return A. Different time C. Variable time B. Travel time D. Changing time