Professional Documents
Culture Documents
CMPM
CMPM
C. DETAILED ESTIMATE
A. MATERIALS
a. Aluminum Glass w/ screen 17
b. Flush Hollow Core Door 5
c. Flush SolidCore Door 13
B. LABOR
a. Foreman 10 1
b. Skilled 10 2
c. Unskilled Worker 10 3
C. EQUIPMENT
E. OCM 8% OF D
F. CONTRACTOR'S PROFIT 8% OF D
G. VAT 5% OF (D+E+F)
H. TOTAL COST OF WORK ITEM (D+E+F+G)
I. UNIT COST
B. LABOR
a. Foreman 14 1
b. Skilled 14 2
c. Unskilled Worker 14 2
C. EQUIPMENT
E. OCM 8% OF D
F. CONTRACTOR'S PROFIT 8% OF D
G. VAT 5% OF (D+E+F)
H. TOTAL COST OF WORK ITEM (D+E+F+G)
I. UNIT COST
A. MATERIALS
a. Patching Compound 90
b. Primer 70
c. Semi Gloss (2Coat) 130
d. Neutralizer 40
B. LABOR
a. Foreman 21 1
b. Skilled 21 3
c. Unskilled Worker 21 3
C. EQUIPMENT
E. OCM 8% OF D
F. CONTRACTOR'S PROFIT 8% OF D
G. VAT 5% OF (D+E+F)
H. TOTAL COST OF WORK ITEM (D+E+F+G)
I. UNIT COST
A. MATERIALS
a. Tiles unglazed 500
b. Cement 110
c. Sand 20
d. Tile Grout 60
B. LABOR
a. Foreman 20 1
b. Skilled 20 3
c. Unskilled Worker 20 3
C. EQUIPMENT
E. OCM 8% OF D
F. CONTRACTOR'S PROFIT 8% OF D
G. VAT 5% OF (D+E+F)
H. TOTAL COST OF WORK ITEM (D+E+F+G)
I. UNIT COST
A. MATERIALS
a. CHB #5 230
b. 3/4 Gravel 5
c. 40kg Cement 25
d. Sand 5
e. 10 mm Steel Bar 6m 30
f. #16 GI Wire 6
B. LABOR
a. Foreman 3 1
b. Skilled 3 2
b. Operator 3 1
d. Unskilled Worker 3 4
C. EQUIPMENT
a. BAGGER MIXER 2 1
D. TOTAL DIRECT COST
E. OCM 8% OF D
F. CONTRACTOR'S PROFIT 8% OF D
G. VAT 5% OF (D+E+F)
H. TOTAL COST OF WORK ITEM (D+E+F+G)
I. UNIT COST
A. MATERIALS
a. ACU Split Type 4
b. Water Closet set 2
c. Lavatory set 2
d. Shower Set 2
e. Kitchen Cabinet/Bar 1
f. Cabinet 5
g. Led Bulb 20
B. LABOR
a. Foreman 8 1
b. Skilled 8 2
d. Unskilled Worker 8 2
C. EQUIPMENT
a.
E. OCM 8% OF D
F. CONTRACTOR'S PROFIT 8% OF D
G. VAT 5% OF (D+E+F)
H. TOTAL COST OF WORK ITEM (D+E+F+G)
I. UNIT COST
UNIT UNIT COST TOTAL COST
Lot ₱ 269,871.00 ₱ 269,871.00
Lot ₱ 1,340,287.20 ₱ 1,340,287.20
Lot ₱ 3,735,880.05 ₱ 3,735,880.05
Lot ₱ 6,499,248.00 ₱ 6,499,248.00
Lot ₱ 2,407,943.37 ₱ 2,407,943.37
Lot ₱ 266,400.96 ₱ 266,400.96
Lot ₱ 290,931.48 ₱ 290,931.48
lot ₱ 157,365.60 ₱ 157,365.60
₱ 16,327,209.57
SUB-TOTAL C = -
(A+B+C)= ₱ 129,200.00
= ₱ 10,336.00
= ₱ 10,336.00
= ₱ 7,493.60
= ₱ 157,365.60
= ₱ 157,365.60
SUB-TOTAL C = -
(A+B+C)= ₱ 126,820.00
= ₱ 10,145.60
= ₱ 10,145.60
= ₱ 7,355.56
= ₱ 154,466.76
= ₱ 154,466.76
SUB-TOTAL C = -
(A+B+C)= ₱ 288,900.00
= ₱ 23,112.00
= ₱ 23,112.00
= ₱ 16,756.20
= ₱ 351,880.20
= ₱ 351,880.20
SUB-TOTAL C = -
(A+B+C)= ₱ 316,000.00
= ₱ 25,280.00
= ₱ 25,280.00
= ₱ 18,328.00
= ₱ 384,888.00
= ₱ 384,888.00
pcs 15 3,450.00
pcs 1500 7,500.00
bags 225 5,625.00
cu.m 1100 5,500.00
pcs 190 5,700.00
kgs 75 450.00
SUB-TOTAL A = ₱ 28,225.00
(A+B+C)= ₱ 42,875.00
= ₱ 3,430.00
= ₱ 3,430.00
= ₱ 2,486.75
= ₱ 52,221.75
= ₱ 52,221.75
SUB-TOTAL C = -
(A+B+C)= ₱ 341,400.00
= ₱ 27,312.00
= ₱ 27,312.00
= ₱ 19,801.20
= ₱ 415,825.20
= ₱ 415,825.20
LENGTH WIDTH HEIGHT QTY VOLUME cement gravel sand
FOOTING 1.5 1.5 0.5 27 30.375 273.375 30.375 15.1875
MCOLUMN 4.5 0.5 0.5 27 30.38 273.375 30.375 15.1875
COLUMN 3.5 0.5 0.5 27 23.63 212.625 23.625 11.8125
WF/GB 200 0.4 0.4 1 32 288 32 16
BEAM 200 0.6 0.4 1 48 432 48 24
RB 200 0.6 0.4 1 48 432 48 24
Slab 22 19 0.2 1 83.6 752.4 83.6 41.8
295.975 2663.775 295.975 147.9875
AREA 575
B
rsb 12 rsb 16 lateral 10 tie wire
126 20
108 85 11
216 144 19
200 425 34
252 422 41
95 85 14
300 30
300 997 1161 169
20077.36
EQUIPMENT RENTAL RATES & CAPABILITIES, ACEL RATES January 2003 Ed.
Wekding Machine Electric Driven/ DC output Weilding / Cutting 500 APMS Capacity
Oxy-Acetylene/Cutting outfit Cutting
Chainsaw w/out blade Cutting
Generator Set Power Generation 64-125 KVA 51-100 HP
Dumpt truck (12-15 cu.Yds) Hauling / Transporting 9.17-11.46 Cu.M. Capacity
Water Truck ( 5000-6000 Gals) Water Supply 5000-6000 Gals. Capacity
Trailer 60 Ton PhP4.25/HR./Km Transporting 15 TONS Capacity
( PhP 4.25 X Wt. (Min.=15T) X No. of KM. +
50% Surcharge, Return trip Example (100KM)
= (4.25 X 15 X 100) X 1.5 = PhP 16,576 per
Day
Cargot Truck ( 9-10 Tons) Hauling / Transporting 9-10 TONS Capacity
EQUIPMENT CAPABILITIES
Type of Equipment Average Capabilities
FACTORS TO BE MULTIPLIED TO
DETERMINE THE REQUIRED QUANTITY
OF EACH MATERIAL CONCRETE
I. MECHANIZED ASPECT
B.2 DOZER
Horse Production ( cu.m./hr. ) Bank Volume
Power Canal Structure
120 30 15
140 35 20
160 40 25
180 45 30
200 50 35
B.3 BACKHOE
Bucket ( cu.m.) Production ( cu.m./hr.) Bank Volume
Canal Structure Creek
0.5 20 15 15
0.75 30 20 20
1 40 30 30
1.25 50 40 40
1.5 60 45 45
C. QUARRYING
Dozer ( H.P.) Production ( cu.m./hr.) Bank Volume
Common Aggregate Cobbles/Boulders
140 55 60 27
160 60 65 29
180 65 70 31
200 70 75 33
D. LOADING
Bucket (cu.m.) Production ( cu.m./hr.) Bank Volume
Common Aggregate Cobbles/Boulders
1 50 55 35
1.5 75 80 55
2 100 110 75
2.5 125 135 90
3 150 165 110
E. SPREADING
Grader ( H.P.) Road ( cu.m./hr. ) cmp.
Common Aggregate
80-100 60 70
100-125 70 80
125-150 90 100
150-175 100 110
H. EMBANKMENT COMPACTION
Capacity ( cu.m./hr.) Compacted Volume
Tons Self- Propelled
Tam. Foot drum Vib. Drum
10 80 60
12 90 70
15 120 90
K. DEMOLITION OF CONCRETE
L. DRIVING OF PILES
Steel Pipes : Crane 25 tons with 2-tons drop
hammer, Capacity= 8 L.M./Hr.
Concrete Piles : Crane 25 tons with 2500
kgs.m. Pile hammer, Capacity= 2.00 L.M. per
Hr.,
4.00 L.M./Hr. for thick & thin concrete piles.
M. MANUAL ASPECT
A. EXCAVATION
A.1. Common Materials
Capacity (cu.m./day) Bank Volume & Depth of Excavation
Type of Work ( meter )
Farmditchs 3.00 2.50 2.00
Canal 2.50 2.00 1.75
Structure 2.00 1.75 1.50
E. QUARRYING
Capability cu.m./day/man
Sand & Gravel Cobbles Boulder
3.5 2.5 2
F. DEMOLITION OF CONCRETE
Slab & Wall 0.50 cu.m./man-day
Massive Concrete 0.20 cu.m./man-day
G. SCREENING OF AGGREGATES
Gravel 4.00 cu.m./day/man
Sand 6.00 cu.m./day/man
H. MANUAL BACKFILL
Capacity : 3.00 cu.m./day/man
L. GROUTED RIPRAP
Crew : 1- Foreman, 2- Mason, 10- Laborers,
& 1- L.E. Operator
Capacity : 7.50 cu.m./day
N. CONCRETE LINING
Crew : 1- Foreman, 2- Mason, 1- L.E.
Operator, 10- Laborers with one (1) bagger
mixer
Capacity : 4.50 cu.m./day
P. CONCRETE WORKS
P.1. Fabrication, Placing & Dismantling of
Forms
Crew : 2- Carpenters & 4- Laborers;
Capacity : 3.50 cu.m./day for 3000 psi
Crew : 1- Carpenter & 1- Laborer; Capacity :
4.50 cu.m./day Canal Lining
G. I. LAYING OF C.H.B.
Size Cement Sand
Bag/sq.m. Cu.m./sq.m.
4" 0.55 0.046
6" 1.07 0.089
Lumpsum
Installation:
Timber:
Paintings:
Paint Rollers 125 sq.m./man-days
Paint Brush 50 sq.m./man-days
Neutralizer 100 sq.m./man-days
Truss Fabrication 0.25 truss/man-days
Purlins Installation 60 L.M./man-days
Fascia Boards 0.05 cu.m./man-days
Roof Coverings ( G.I. sheets ) 35 pcs./man-days
Concrete Works:
Concrete Pouring 0.30 cu.m./man-days
Rebars 20 - 30 kgs.man-days
Finishing:
Rough Finish 10 sq.m./man-days
Plain/Fine Finish 8 sq.m./man-days
CHB Filling/Laying 6 - 8 sq.m./man-days
A. CEMENT MORTAR
MAINTENANCE BY CONTRACT
( MBC )
METHODS OF CONSTRUCTION