JSA
NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: MASONARY WORK
Project Name:
Prepared By:
10
12
Getting down from working height/platform. Hit injury to head and body,
Fracture,
13
Removing of Residual Debris after work. Small Injury,
Brush Injury
14
Comments:
6. Erection crew must use safety helmet and chin strap must be properly tied.
7. Double hook safety belt must be used by the person whenever he is at a height of 6 feet or
more.
8. Safety harness
safety shoes, safety helmet
Reflective jacket
1. Person must use double hook safety belt while climbing at the working platform or height.
2. Person must wear safety helmet with chin strap properly tied
3. Suitable working platform must be provided at required working height.
4. Safety harness
safety shoes
safety helmet
1. Safety net must be fixed before working platform before commencing the work.
2. Working platform must be properly fixed to the scaffolding.
3. Double hook Safety belt must be used while working at height.
4. Safety Helmet must be used while working at height and chin strap must be properly tied. All
person working in area must wear safety helmet.
5. No unwanted people should be there in area while materials are lifted upward.
6. Safety harness,Safety helmet, Safety shoes, Hand gloves, Reflective jacket
1. Person must use double hook safety belt while getting down from working platform or height.
2. Person must wear safety helmet with chin strap properly tied
3. Safety harness, Safety helmet, Safety shoes,Hand gloves,Reflective jacket
1. Residual materials should be collect from working area and stacked properly.
2. It should not be spread here and there or pathway.
3. Safety helmet,Safety Shoe, Rubber ,Hand gloves.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
e:
e:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: CARPENTRY WORK
Project Name:
Prepared By:
Loading & Unloading of wood Material 1. Workers can be slipped during shifting materials
& Material Handling and get impact.
2. Materials can fall from head to floor or on person
and can be injured or damage of floor.
3. Wrong body posture while handling the Plywood.
4. Repetitive strain on body.
2
Removal of Residual materials from site. 1. Hand can be cut during collecting residual
materials.
2. Breathing problem during booming.
4 3. Repetitive strain on back
Comments:
1. Debris must be kept at a suitable place to avoid any disturbance in other site activities.
2. It must be cleared from site at the earliest.
3. Use Nose mask, Hand gloves, Safety shoes & helmet as Mandatory PPEs.
Reviewed & Approved By: Date:
Project Manager (Client): Date:
TE : 01/04/2021
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: CHASE CUTTING WORK
Project Name:
Prepared By:
Comments:
1. Have a look of the entire area for any protruded part or sharp edges to
avoid cut or brush injury.
2. Structure or ladder being used must be rigid enough for the job.
3. Safety belt must be used if height is more than 6 feet.
4. Dust mask, Goggle,Helmet, Safety shoes
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: CONCRETE WORK
Project Name:
Prepared By:
Comments:
1. Use helmet ,
2. Rubber hand gloves
3. Use gumboot.
4. Use nose musk,
5. Hand gloves for avoiding skin contact irritation.
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1. Use cotton hand gloves,
2. Safety shoes must be wearing.
3 .Competent person allowed only
Shifting material from outside to the 1. Fall of Material on leg or body of person
specific storage location nearby.
2. Fall of materials.
2 3. Repetitive strain on back
4. Back pain, Finger injury, leg injury.
Installing Conduit on Wall and Floor 1. Cut Injury on hands during cutting the PVC or
MS conduit,
2. Brush injury during Installing the Conduit on
6 wall
Installing Cable Tray 1. Cut Injury due to cutting the cable tray.
2. Physical injury due to fall from height
3.Fall of Material or person during cable tray
installations.
Switch Box Installing 1. Hand can be cut by Sharp edge, may result
cut injury, brush injury.
2. Hitting the material to the body
9
Comments:
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: FALSE CEILING WORK
Project Name:
Prepared By:
Comments:
Comments:
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: GYPSUM PARTITION WORK
Project Name:
Prepared By:
Comments:
4. Avoid wearing loose clothes and ornaments like chain, ring or watches.
4. Avoid wearing loose clothes and ornaments like chain, ring or watches.
1. All workers must wear all required ppe,
2. Use hand gloves during screwing,
3. Wear nose mask and goggle during drilling the stone,
4. If working at height must wear full body harness.
5. During height work must barricade the area
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: WORK AT HEIGHT
Project Name:
Prepared By:
Lifting tools, materials at the working 1. Fall of material on leg or someone else
height/ platform. working nearby, fall of person and get
injured.
3 2. Bellow materials can damage by fall of
materials from height.
Working at the platform/ working height. 1. Fall of material on leg or someone else
working nearby, fall of person and get
injured.
2. Bellow materials can damage by fall of
materials from height.
4
1. Person must use double hook safety belt while climbing at the working platform
or height.
2. Person must wear safety helmet with chin strap properly tied
3. Suitable working platform must be provided at required working height.
1. Safety net must be fixed before working platform before commencing the work.
2. Working platform must be properly fixed to the scaffolding.
3. Double hook Safety belt must be used while working at height.
4. Safety Helmet must be used while working at height and chin strap must be
properly tied. All people working in area must wear safety helmet.
5. No unwanted people should be there in area while materials are lifted upward.
1. Person must use double hook safety belt while getting down from working
platform or height.
2. Person must wear safety helmet with chin strap properly tied
3. Use full body harness, safety helmet safety shoes.
Reviewed & Approved By: Date:
Project Manager (Client): Date:
DATE : 01/04/2021
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: SCAFFOLDING WORK
Project Name:
Prepared By:
Lifting of material from the ground level 1. Hand, finger may crush.
and placing at desired location 2. Collapse of material on someone.
3. Repetitive strain on back
Collapse of structure due to loose soil at 1. Man can get serious injured due to fall of
the base of scaffolding scaffolding structure
2. Materials can be damage due to hit with
3 other structure.
Working on the scaffolding 1. Man can fall from height get serious
injury.
2. Fall of materials from height and can be
damage floor or other materials. Fracture /
5 material damage, cut injury, leg injury, brush
injury
Comments:
1. Check the joints in case of MS scaffolding and knots of the rope before use of
scaffolding.
2. Cup should be properly placed on the bottom MS pipe.
3. Educate the scaffolding erecting team about the same.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: STONE CUTTING & POLISHING
Project Name:
Prepared By:
4
Fixing of Stone to the Designated place Leg Injury,
Brush injury or finger injury,
Cut injury due to sharp edge of stone,
Comments:
1. All workers must be trained and having the adequate knowledge of stone cutting
2. Stone cutting area must be free from any obstacle or tripping hazard,
3. Take the power supply safely with double insulated cable, 4.
There should be no open electrical joint,
5. All workers must wear all mandatory PPE’s like Hand gloves, Safety shoes, helmet,
Safety goggle, nose mask.
6. Always use machine guard in Cutter machine,
7. Safety Shoes, Helmet, Hand Gloves, Nose Mask, Ear plug
1. All workers must wear all required PPE’s
2. Lift the stone according your capacity,
3. Use hand gloves and nose mask before applying adhesive on the stone,
4. Be careful during placing the stone on the wall or ground,
5. Wear nose mask and goggle during drilling the stone,
6. If working at height must wear safety harness,
7. During height work must barricade the area
8. Safety shoes, Helmet, Goggle, Nose mask, Hand gloves, Earplug
1. Debris must be kept at a suitable place to avoid any disturbance in other site activities.
2. It must be cleared from site at the earliest.
3. Safety shoes, Hand gloves, Nose mask, Helmet
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: WALL CLADING WORK
Project Name:
Prepared By:
4
Fixing of Stone to the Designated place Leg Injury,
Brush injury or finger injury,
Cut injury due to sharp edge of stone,
Comments:
1. All workers must be trained and having the adequate knowledge of stone cutting
2. Stone cutting area must be free from any obstacle or tripping hazard,
3. Take the power supply safely with double insulated cable, 4.
There should be no open electrical joint,
5. All workers must wear all mandatory ppes like Hand gloves, Safety shoes, helmet, Safety
goggle, nose mask.
6. Always use machine guard in Cutter machine,
7. Safety Shoes, Helmet, Hand Gloves, Nose Mask, Ear plug
1. All workers must wear all required ppe,
2. Lift the stone according your capacity,
3. Use hand gloves and nose mask before applying adhesive on the stone,
4. Be careful during placing the stone on the wall or ground,
5. Wear nose mask and goggle during drilling the stone,
6. If working at height must wear safety harness,
7. During height work must barricade the area
8. Safety shoes, Helmet, Goggle, Nose mask, Hand gloves, Earplug
1. Debris must be kept at a suitable place to avoid any disturbance in other site activities.
2. It must be cleared from site at the earliest.
3. Safety shoes, Hand gloves, Nose mask, Helmet
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: WELDING WORK
Project Name:
Prepared By:
Comments:
Safety Officer (ASSA CONSTRUCTION): Date:
Project Manager (ASSA CONSTRUCTION) Date:
EV. NO :00 DATE : 01/04/2021
1. Debris must be kept at a suitable place to avoid any disturbance in other 1.Site Engineer
site activities. 2.Site Supervisor
2. It must be cleared from site at the earliest. 3.Safety Officer
3. Nose mask , Hand gloves, Safety shoes, helmet
Reviewed & Approved By: Date:
Project Manager (Client): Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: GLASS FIXING WORK
Project Name:
Prepared By:
Comments:
1) Proper working platform must be provided before start of work. 1.Site Engineer
2) Hand railing must be provided. 2.Site Supervisor
3) Safety Belt must be used while working on the platform as well as climbing 3.Safety Officer
up & down to the platform.
4) No work and unwanted people to be allowed below the area where glass
work is under progress.
5) Using Proper PPE’s
2
Grinding 1)Cut injury
2)Burn injury or shock,
3) Breathing and hear related problem.
Comments:
1) Debris must be kept at a suitable place to avoid any disturbance in other 1.Site Engineer
site activities. 2.Site Supervisor
2) It must be cleared from site at the earliest. 3.Safety Officer
3) Using Proper PPE’s
Comments:
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: MATERIAL HANDLING WORK
Project Name:
Prepared By:
Comments:
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: PAINTING WORK
Project Name:
Prepared By:
Comments:
1) Paint drum should be properly stacked; clearance is must from all sides near wall.
2) Used paint drum must be properly evacuated and should be safely discharges to avoid
any fire hazard.
3) Fire extinguishers must be kept near paint storage.
4) Should have proper ventilation system.
5) Using Proper PPE’s
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: PANELLING WORK
Project Name:
Prepared By:
Comments:
1. All workers must be trained and having the adequate knowledge of Material cutting
2. Material area must be free from any obstacle or tripping hazard,
3. Take the power supply safely with double insulated cable, Site engineer/ Site supervisor /
safety officer
4. There should be no open electrical joint,
5. All workers must wear all mandatory PPE’s like Hand gloves, Safety shoes, helmet, Safety
goggle, nose mask.
6. Always use machine guard in Cutter machine,
1. Debris must be kept at a suitable place to avoid any disturbance in other site activities.
2. It must be cleared from site at the earliest.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: PLUMBING WORK
Project Name:
Prepared By:
Marking the Plumbing Pipe for cutting area.( Scratch, Small Injury.
4
Plumbing Pipe Cutting for fitting Scratch, Cut, Dust Allergy, Breathing
problem, Impact injury, respiratory problem,
Damage to ear and eye in long term.
Comments:
1. Backside guard must be there in the cutter to avoid backward through of the small
particles.
2. Goggles must be used to protect the eyes from small particle.
3. A firm grip on cutter machine must be maintained while cutting.
4.Powered hand tools shall be inspected by the Operator prior to use each day.
5. Tools that are not fully operational shall be tagged and labeled “Defective” &
removed from service
1. Have a look of the entire area for any protruded part or sharp edges to avoid cut or
brush injury.
1. Backside guard must be there in the cutter to avoid backward through of the small
particles.
2. Goggles must be used to protect the eyes from small particle.
3. A firm grip on cutter machine must be maintained while cutting.
4.Powered hand tools shall be inspected by the Operator prior to use each day.
5. Tools that are not fully operational shall be tagged and labeled “Defective” &
removed from service
1. All workers must wear all required PPE
2. Lift the Pipe according your capacity,
3. Be careful during placing the Pipe on the wall or ground,
5. Wear nose mask and goggle during drilling the Pipe,
6. If working at height must wear safety harness,
7. During height work must barricade the area
1. Debris must be kept at a suitable place to avoid any disturbance in other site
activities.
2. It must be cleared from site at the earliest.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: DEMOLITION WORK
Project Name:
Prepared By:
Providing scaffolding or working platform, as 1. Fall of tubes on leg or other body part,
applicable scratch or cut in hand
3 2. Person fall from height
Work In height with all types of materials 1. Materials fall from height. 2.
and Tools Person fall from height. 3.
Materials fall on leg
4. Electrical shock or fire
5
Comments:
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: HVAC WORK
Project Name:
Prepared By:
Cutting the sheet as per size and shape of 1. Cutting hand or leg cut by sharp
duct edge.
2. Sparking during cutting 3. Hit
4 during handling materials.
4. Heavy noise produce during
cutting.
Folding the sheet as per wings of the duct 1. Hand cutting during folding and
handling the ducting sheet.
2. Hamer can run out of hand
5 3. Exessive noise during folding the
sheet by hamer
Comments:
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: INSTALLATION OF MATERIAL HOIST
Project Name:
Prepared By:
Fixing of Trolley with clamp of Lower Pulley Fall of trolley due to clamping
failure
5
Comments:
Carrying with suitbae trolley or hydra, Chain must be fastened with the frame.
1. Place the hoist about 3 mtrs in straight line with the tower.
2. Now the free end of the wire rope from the hoist is pulled and placed around the
bottom pulley of the tower.
3. It is pulled up the top of the tower and placed around the top pulley .
4. The wire rope is moved around the pulley to come down to the pulley attached to the
trolley.
5. The wire rope is moved around this pulley and pulled up to a point where it is fixed to a
hook and clamped with staples.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: MATERIAL HOIST OPERATION
Project Name:
Prepared By:
Comments:
1. A scaffold has been errected surrounding the bucket movement to avoid close vicinity
with bucket.
2. Rope has been marked on suitable place to get the idea about pacement of bucket.
3. Signalman is in continuous communication with operator.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date:
Format. No : JSA-ASSA-CTC FORMAT REV. NO :00
Title : Job Safety Analysis / Job Hazard Analysis (Safe Work Method Statement)
Doc. No.: HIR-SAF-PM Department: OHSE Rev. No.: 00
Work/Activity: GRANITE MACHINE OPERATION
Project Name:
Prepared By:
Comments:
1. All workers must be trained and having the adequate knowledge of stone cutting
2. Stone cutting area must be free from any obstacle or tripping hazard,
3. Take the power supply safely with double insulated cable, 4.
There should be no open electrical joint,
5. All workers must wear all mandatory ppes like Hand gloves, Safety shoes, helmet,
Safety goggle, nose mask.
6. Always use machine guard in Cutter machine.
1. Debris must be kept at a suitable place to avoid any disturbance in other site activities.
2. It must be cleared from site at the earliest.
Responsibility
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
1.Site Engineer
2.Site Supervisor
3.Safety Officer
Date:
Date: