TF-Chimney & VFD-16.04.15
TF-Chimney & VFD-16.04.15
TF-Chimney & VFD-16.04.15
15
Coordinator:- RC Rao (Engr. Safety)
2 16.04.15 Chimney IVRCL Improper routing of electrical cables Proper routing of electrical cables 20.04.15
found in (Chimney area) should be done as soon as possible
3 16.04.15 Chimney IVRCL Plug tops not found for electrical cable Plug tops should be provided as soon 20.04.15
in (Chimney area) as possible for elecrical cables
4 16.04.15 Chimney IVRCL Halogen mounted at metal rod in Halogen should be fixed at wooden 20.04.15
(Chimney area) bamboos supplied with 3 core for
extending the earth connectivity
5 16.04.15 Chimney IVRCL Improper housekeeping found in Housekeeping should be done at daily 20.04.15
( Chimney area) basis
6 16.04.15 Chimney/ IVRCL Barrication not found for excavation pit Hard barrication should be done for 20.04.15
VFD (Chimney & VFD area) excavation pit deeper than 1.5 mtrs
7 16.04.15 VFD IVRCL Access not found for height work Access should be made with proper 20.04.15
(VFD area) sloping/handrails etc
K.M.Solanki (Mgr RC Rao
Safety)
(Engr. Safety)