Professional Documents
Culture Documents
Risk Based Management of Corrosion Under Insulation
Risk Based Management of Corrosion Under Insulation
The electronic PDF version of this document, available at the DNV GL website dnvgl.com, is the official, binding version.
DNV GL AS
FOREWORD
This service document has been prepared based on available knowledge, technology and/or information at the time of issuance of this
document. The use of this document by others than DNV GL is at the user's sole risk. DNV GL does not accept any liability or responsibility
for loss or damages resulting from any use of this document.
CHANGES – CURRENT
Changes current
This is a new document.
DNV GL AS
CONTENTS
Contents
Changes – current.................................................................................................. 3
Section 1 General.................................................................................................... 7
1.1 Introduction......................................................................................7
1.2 Objective...........................................................................................7
1.3 Scope................................................................................................ 8
1.4 Application and limitations............................................................... 8
1.5 References........................................................................................ 8
1.6 Definitions and abbreviations........................................................... 9
DNV GL AS
6.3 New knowledge and technology..................................................... 26
Contents
6.4 Experience transfer, and lessons learned across assets..................26
6.5 Roles and responsibilities............................................................... 27
6.6 Organisational competence, data management and information
and communication technology systems.............................................. 27
6.7 Effectiveness of the corrosion under insulation management......... 27
Section 7 Bibliography.......................................................................................... 28
7.1 Bibliography.................................................................................... 28
DNV GL AS
Contents
Appendix E Probability of failure guidance on input data................................... 47
Changes – historic................................................................................................ 51
DNV GL AS
SECTION 1 GENERAL
1.1 Introduction
This recommended practice (RP) is a response to the major safety threat and the challenge of a multi-
billion-dollar cost faced by the industry as a consequence of corrosion under insulation (CUI). This document
describes a comprehensive methodology for managing CUI in a risk based, safe and cost-efficient manner.
The methodology was developed by a joint industry project in 2017-2018, led by DNV GL with participating
operators from the oil and gas industry.
CUI is defined as the external corrosion of piping and vessels that occurs when water becomes trapped
beneath insulation. CUI damage takes the form of localized external corrosion in carbon and low alloy
steels, /2/, and as external stress corrosion cracking (ESCC) and pitting in austenitic and duplex stainless
steel.
1.2 Objective
The objective of this document is to provide a practical, cost effective recipe for how to manage risk related
to CUI. The work process is built around a plan, do, check, act (PDCA) process aligned with ISO 9000
requirements of continuous improvement, see Figure 11. The target is to mitigate unacceptable risk in the
most effective way by giving priority to high risk.
This recommended practice aim to support efficient the CUI risk management in terms of timely response
based on risk assessment, but also with respect to acting on an identified degraded barrier as a part of
normal operating procedures. Adequate corrective response to degraded barriers is a key to improved CUI
risk management.
DNV GL AS
1.3 Scope
This document addresses the threat of corrosion under insulation in process plants.
Degradation mechanisms not involving CUI are not addressed by this document.
The document describes how to assess the probability of failure (PoF) due to CUI and how the different
mitigation activities alter the probability. In this document, existing data should be used to assign a
consequence of failure (CoF) to obtain the CUI risk.
The model combines individual probability assessments of the four CUI barriers, material barrier, coating
barrier, water wetting barrier and design barrier, into a total probability of failure category, and combines this
with the consequence of failure into a risk (CUI) category.
Guidance note:
To be further detailed in Sec.3.
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
Risks due to other degradation mechanisms, i.e. other than CUI, are not addressed in this document.
The document is based upon known technology and methodologies publicly available at the end of 2018.
The logic described in this document for assessing the probability of failure related to CUI should be adhered
to as a whole. The process of calculation of individual probability factors and aggregation into an overall PoF
may be accomplished by available software solutions.
1.5 References
This document may be used as a stand-alone document. Informative references to other standards and
specifications are listed in Sec.7.
Table 1-1 lists DNV GL references used in this document.
DNV GL AS
Table 11 DNV GL documents
Term Description
shall verbal form used to indicate requirements strictly to be followed in order to conform to the
document
should verbal form used to indicate that among several possibilities one is recommended as
particularly suitable, without mentioning or excluding others
may verbal form used to indicate a course of action permissible within the limits of the document
Term Definition
box solution easily removable jacketing insulation on equipment, flanges and valves
cladding external cover of insulation to protect against water or damage to insulation. Can be both metallic or
polymer based. Also referred to as 'jacketing', 'metal sheeting' and/or 'insulation protection' in other
literature
coating layer of material applied to the surface of another material with the intent of inhibiting or preventing
corrosion
coating operation in which different types and layers of paint or other coating materials are applied in a certain
system sequence
contaminants chemical compositions that influence the corrosion rate or coating breakdown
hot-spot location on a pipe or equipment where the condition being discussed is expected to be most severe, see
DNVGL-RP-G101, see API 583:2016, susceptible locations for CUI
insulation layer of material applied to the surface of another material with the intent to insulate an equipment, fire
protect the equipment or protect human health
insulation integrated solution in which different types and layers of insulation materials are applied in a certain
system sequence
object relevant physical item that might suffer from CUI. Examples are pipe systems, vessels and/or valves
PoFcoating probability of failure for the coating barrier, i.e. degraded coating to reveal bare steel
PoFCUI probability of failure for CUI including assessment of all relevant barriers
DNV GL AS
Term Definition
PoFdesign probability of failure for the design barrier, i.e. the design or layout will strengthen or weaken the
potential for CUI degradation
PoFmaterial probability of failure for the material barrier, i.e. breach of containment
PoFwater wetting probability of failure for the water wetting barrier, i.e. water in contact with pipe/vessel surface
PREN value PREN value is calculated based on the following formula: PREN = Cr + 3.3 Mo + 16 N, whereas Cr, Mo
and N represent the % of Chromium, Molybdenum and Nitrogen respectively
qualitative risk analysis using primarily subject matter expertise and experience to assign broad categorizations for
risk model POF and COF (ref API 580)
quantitative risk analysis that uses primarily model-based approaches where numerical values are calculated and
risk model more discreet input data used (ref API 580)
risk combination of the incident probability and its consequences, see also DNVGL-RP-G101
water insulation that will retain water and allow for water exposure on steel surface
retaining
wet condition wet condition is used in the context of describing the exposure of coating and insulation to water. Wet
condition shall mean a situation where moisture and/or water is present all or part of the time
1.6.3 Abbreviations
Table 14 Abbreviations
Abbreviation Description
DNV GL AS
Abbreviation Description
RT radiographic testing
DNV GL AS
SECTION 2 RISK BASED APPROACH
In addition to the above listed elements, the strategy should include elements such as roles &
responsibilities, change management, reporting requirements and reference to best industry technical
solutions, including coating, insulation, inspection, and monitoring methods.
The CUI strategy shall differentiate between different risk levels and be applicable for both short-time and
long-term periods, as CUI as a degradation mechanism will develop over time. The strategy shall be aligned
to the relevant asset to reflect material selection, coating condition, insulation selection, cladding, process
condition temperature, maintenance strategies and age.
The strategy shall consider the development of the barriers over time and hence increase activities when the
barriers are degrading. It is recommended that the CUI management strategy state that identified defects in
any of the barriers leading to unacceptable risk shall be repaired within a relatively short period of time.
DNV GL AS
The approach taken in this document uses a 5x5 risk matrix as shown in Figure 22, where the risk
acceptance limit is at the borderline between medium and high risk.
Figure 22 5x5 risk matrix with example values for safety and financial loss
DNV GL AS
4) Design barrier: CUI challenges may be reduced or increased based on the design of the system.
Parameters such as wall thickness and pipe diameters will influence the probability of failure due to CUI.
Results of NDT inspections are also included in this barrier.
Figure 23 Material barrier, coating barrier or water barrier is assessed to be intact (PoF assessed
to VL or L)
If either the material barrier, coating barrier or water wetting barrier is assessed to be intact (PoF assessed to
VL or L), it may be assumed that the CUI probability will not exceed M until the relevant barrier is assessed
to M or higher.
Each of the four barriers is assessed based on a subset of factors. These are:
— Material barrier:
— material type
— material surface temperature
— temperature fluctuations
— contaminants:
— the composition of the electrolyte is important for the possibility of corrosion.
— Coating barrier:
— coating age
— coating type
— quality control and workmanship
— wetting conditions:
— the composition of the electrolyte may be important for the coating breakdown.
— temperature:
— surface temperature vs recommended temperature, reference made to coating specification and
glass transition temperature.
DNV GL AS
— Water wetting barrier:
— location
— dew-point temperature
— insulation system
— workmanship
— maintenance routines.
— Design barrier:
— wall thickness
— pipe dimensions
— inspection method, extent, timing and results.
DNV GL AS
SECTION 3 QUALITATIVE CORROSION UNDER INSULATION RISK
ASSESSMENT
DNV GL AS
Table 32 Total CUI probability categories based on point model in table 31
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
DNV GL AS
3.3 Mitigation of risk
The risk development should be monitored to ensure that unacceptable risk is mitigated and controlled.
Risk mitigation in this context may be maintenance activities such as the permanent removal or upgrade of
insulation, refurbishment of coating or close visual inspection. The effect of mitigation shall be incorporated
into the PoF assessment as part of the risk assessment, see Sec.2 to Sec.5. The effect of risk mitigation is
described in detail in Sec.4.
DNV GL AS
SECTION 4 RISK MITIGATION
DNV GL AS
— experience from other assets and lessons learned
— installation of monitoring systems that will give better CUI information (modifications that affect the
increased knowledge part).
4.2.3 Modification
In this context, typical modifications that will mitigate the risk are:
— permanent removal of insulation
— replace one insulation system with a better design solution
— new coating - for example, full refurbishment or just spot repair of degraded coating - the different
coating repair activities will have different mitigating effects
— re-design of pipe-routing, new material selection, alteration in pipe or vessel wall thickness
— alteration of temperature variations
— permanent or temporary repair of degraded parts.
4.3.1 General
Modification and repair will have a direct impact on the object and the parameters that are changed will be
changed in the PoF assessment. Likewise, new information on any of the four barrier elements coming from
studies or inspections will be used as new knowledge and update the PoF assessment.
For mitigation by increased knowledge, a combination of NDT and close visual inspection of the coating might
be cost effective and provide the necessary risk reduction. Such a combination might have a positive effect
on three out of four barriers provided there is an adequate extent and no identified degradation.
DNV GL AS
4.3.2.4 Close visual inspection after removal of insulation
o
Close visual inspection shall be performed with access to the object from 360 , within arm's length distance
and performed under good lighting conditions and set requirements to reporting. It is expected that all
coating degradation and ongoing corrosion will be revealed. Based on results from the CVI of piping or
vessels, the coating conditions should be reassessed and given a new lifetime estimate. Furthermore, the
CVI should also inspect both the humidity and quality of the insulation removed from the system as well as
confirming that the new insulation work on the new insulation solution is of good quality.
Based on the results from the CVI, the status of both the coating and water wetting barriers should be
updated. The design barrier should also be updated in the same way as for NDT as CVI is a better inspection
method than any NDT for external corrosion under insulation.
The results of the CVI inspection (e.g. coating in good condition or no water ingress into the insulation) may
be applied to other objects that have not been inspected under certain conditions.
To apply the results of one inspection to other objects, the following criteria should be met:
— The basic parameters shall be similar:
— Coating degradation: same coating system, similar temperature, same age, same expected quality,
similar water exposure, similar geometry/layout.
— Water wetting: similar design, similar exposure, within same area, expected same workmanship,
similar temperature, similar layout.
— The performed inspection shall include a variety of hot-spots and represent all potential hot-spots in the
noninspected parts.
— There should be an external close visual inspection in place to confirm that the external cladding holds a
similar quality and is not damaged.
— The effect on non-inspected objects in terms of reduced PoF shall be less than for the inspected objects
(see also [4.3.3] for the effect of NDT inspection).
DNV GL AS
Table 41 Mitigating effect on PoFdesign based on NDT with no findings
In Table 4-1 , it is assumed that the selected NDT method will have a probability of detection (PoD) of
minimum 0.8. The PoD value shall relate to a circular defect of 1.5 mm depth with a diameter of 50 mm on a
10" line with a wall thickness of 10 mm, and 100 mm mineral wool insulation and stainless steel cladding.
To use the NDT information on non-inspected objects in the same CUI environment, it is required that
minimum 50% of the hotspots are inspected and that the rules for grouping items stated in [F.5] are
adhered to. The inspection extent may be considered for a 3-year period to determine the percentage of hot-
spots inspected, i.e. the inspections may be performed over a duration of 3 years.
Guidance note:
If NDT is selected as a main mitigation method, it is recommended to inspect 100% of hot-spots over a 6-year period. This
will also give more effective mitigation. Furthermore, the combination of CVI after removal and NDT will enable evaluation of
the coating system and make the assessment more reliable to the assessment. In general removal of insulation and CVI is
recommended for very high risk (VH). For high risk (H) a combination of insulation removal and NDT may give required risk
reduction.
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
DNV GL AS
4.4 Relevant nondestructive testing methods for corrosion under
insulation
Conventional radiography using isotope sources and film or, increasingly, digital detectors are used for
sampling the inspection of areas that are most likely to have CUI, particularly in small-bore pipework.
Other promising methods based on the pulsed eddy current (PEC) and guided wave technique (GWT) still
shall improve and demonstrate sufficient ability to detect relevant sized flaws. A qualification programme
performed in 2019 indicates that most NDT methods for CUI will have increased PoD value with increasing
wall thickness and decreasing insulation thickness.
Ongoing developments in the industry complemented by qualification programmes by HOIS /12/ will
probably qualify more CUI-detection methods in the near future.
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
DNV GL AS
4.5 Effect of modifications
Modifications or changes to the asset will have a direct impact on the assessment of the relevant barrier.
Whenever a piping, coating or insulation modification and/or upgrade is performed, the new values shall be
assessed and the risk should be updated. The positive and/or negative impact on the CUI threat should be
considered when selecting a new solution.
For material selection, more corrosion resistant materials will often be a positive element. It is recommended
to always apply protective coating on insulated pipes and vessels also including for corrosion resistant alloys
like 316, duplex and 6 Mo. When using stainless-steel type 316 material, it is recommended to verify that
316 material with high PREN value is used. For re-routing without a change in material, it is wise to design
such that the number of CUI hotspots is limited, see App.F.
When repairing or refurbishing coating, a good coating system should be selected, see App.B, and apply this
under controlled conditions with the necessary quality assurance. The difference in the increased lifetime
of the coating might differ as much as 20 years between good workmanship and poor workmanship for the
coating application work.
When repairing or upgrading the insulation solution, systems that either avoid/limit water ingress or ensure
that water will be drained out of the system in an efficient way, should be selected. Water repellent insulation
material and a good cladding solution with sealer when relevant should be used. Spacers between the
insulation and pipe to enable good drainage have been successfully used by several companies.
DNV GL AS
SECTION 5 CORROSION UNDER INSULATION RISK MANAGEMENT
DNV GL AS
SECTION 6 CONTINUOUS IMPROVEMENT
DNV GL AS
6.5 Roles and responsibilities
CUI management is a challenge that involves many stakeholders and is vulnerable to lack of ownership and
overview of the full risk.
This document has been developed with the intention to take the full CUI challenge into consideration and
will be most effective if a more integrated scheme for roles and responsibilities is implemented.
This RP represents a lifecycle approach seeking to minimize cost while ensuring safety and continuous
operation over the assets lifetime.
It is a challenge to have CUI management running over a assets lifetime from design to decommissioning.
The transfer from project to operations might suffered from a lack of CUI data transfer. The ability to provide
detailed knowledge of the CUI barrier status for a facility going through different phases has proven difficult
and an awareness of roles, responsibilities and good data management is important.
Operators should prioritise the use of integrated team to enable a common continuous understanding of the
CUI risk.
DNV GL AS
SECTION 7 BIBLIOGRAPHY
7.1 Bibliography
/1/ API 583,Corrosion Under Insulation and Fireproofing. Recommended Practice. Washington DC:
American Petroleum Institute, 2014.
/2/ EFC no. 55, CorrosionUnderInsulation. Woodhead Publishing Limited, 2016. European
Federation of Corrosion.
/3/ NORSOK M501, Surface preparation and protective coating. Edition 6, 2012.
/4/ NACE SP0198, Control of Corrosion Under Thermal Insulation and Fireproofing MaterialsA
Systems Approach. NACE 2017.
/5/ ISO 12944, Paints and varnishes Corrosion protection of steel structures by protective paint
systems Part 1: General introduction (ISO 129441:2017).
/6/ ISO 46283, Paints and varnishes Evaluation of degradation of coatings Designation of
quantity and size of defects, and of intensity of uniform changes in appearance Part 3:
Assessment of degree of rusting :2016.
/7/ NORSOK R004, Piping and equipment insulation. Edition 1, 2009.
/8/ EN1609, Thermal insulating products for building applications. Determination of short term
water absorption by partial immersion 2013.
/9/ EN14303, Thermal insulation products for building equipment and industrial installations.
Factory made mineral wool (MW) products. Specification 2015.
/10/ EN14305, Thermal insulation products for building equipment and industrial installations.
Factory made cellular glass (CG) products. Specification 2015.
/11/ HOIS Guidance for insitu inspection of corrosion under insulation (CUI). Oxford: ESR
Technology 2016.
/12/ https://www.esrtechnology.com/index.php/centres-of-excellence/hois.
DNV GL AS
APPENDIX A PROBABILITY OF FAILURE ASSESSMENT MATERIAL
BARRIER
CUI is defined as the external corrosion of piping and vessels that occurs when water gets trapped beneath
insulation. CUI damage takes the form of localized external corrosion in carbon and low alloy steels, /1/, and
as external stress corrosion cracking (ESCC) and pitting in austenitic and duplex stainless steel.
Provided water is present on the metal surface, the temperature on the metal surface is the dominant factor
for the extent of CUI. Contamination from salts and other corrosive chemicals might also affect the corrosion
rates. However, in this context, the temperature in combination with the type of material should be the
factors affecting the probability of CUI for the material barrier.
A guideline for PoFmaterial assessment of carbon steel, austenitic and duplex steels is given below.
The different steps of PoFmaterial are based on a compilation of information from acknowledged technical
documents, see DNVGL-RP-G101, /1/, /2/ and industry experience.
When assigning a PoF category, account shall be taken of fluctuations in the temperature, not only as a
function of process changes but also as a function of geometrical layout, including stagnant conditions or
partial insulation. To ensure conservatism when there is fluctuation between two different PoF categories, the
higher category should be used.
DNV GL AS
A.3 Probability of failure for external stress corrosion cracking in
austenitic and duplex steel
The probability of ESCC of austenitic and duplex stainless steel under insulation is considered low if the
operational temperature is in accordance with NORSOK M-001 or ISO 21457 for this type of material. If the
temperature is above these temperature limits, a more thorough evaluation should be performed.
1
The PREN value is calculated based on the following formula: PREN = Cr + 3.3 Mo + 16 N, where Cr, Mo
and N represent the % of Chromium, Molybdenum and Nitrogen respectively.
DNV GL AS
Figure A2 CUI in hot environment /2/
As temperatures rise above 110°C, the probability of failure for the material barrier will decrease due to
vaporisation. However, due to the piping layout, with branched piping experiencing lower temperatures,
and the potential trapping of vapour inside the cladding, the PoFmaterial will never be less than medium at
elevated temperatures, see Figure A1.
DNV GL AS
APPENDIX B PROBABILITY OF FAILURE ASSESSMENT COATING
BARRIER
DNV GL AS
— film thickness (maximum, minimum and specified)
— maximum and minimum recoating intervals at relevant temperatures
— final curing time at relevant temperatures
— thinners used
— coating repair system, if relevant.
More details on requirements for coating application requirements are found in the NORSOK standard M501.
If the coating is not applied under controlled and correct conditions, it can be fully degraded after just a few
years. It is recommended to have a good quality assurance system in place to ensure the proper quality of
the coating work.
DNV GL AS
Table B1 Probability of coating breakdown as a function of coating type and age
Recommended practice — DNVGL-RP-G109. Edition December 2019 Page 34
Risk based management of corrosion under insulation
DNV GL AS
Regarding Table B-1 it should be noted that:
— 3-layer on epoxy primer (zinc free) applied on CS, assessed to be as good as a phenolic epoxy system for
SS under insulation given temp. below 80°C.
— Inorganinc copolymer and/or coatings with an inert multipolymeric matrix has so far proven most capable
in the temperature range above 100°C with only short periods below that temperature.
---e-n-d---o-f---n-o-t-e---
DNV GL AS
as good as, or better than, quality coatings than arc spray but are more expensive and have lower efficiency
and mobility.
TSA is considered a very good protection for CUI but has certain limitations:
— It is recommended to only use TSA in environments where the pH is in the range 4.5 to 8.5.
— The application of TSA at field joints might be of poor quality or other coating systems might have been
used at field joints, i.e. field joints may be considered hot-spots on TSA coated objects.
— TSA application during the in-service phase is challenging and under some legislations or safety regimes
not possible.
— It is imortant that the applied TSA has a sealer and thickness above 200 microns in order to be able to
use the suggested coating brakedown data in Table B-1.
— Any areas with overlap of a polymer coating (not zinc based) to TSA will reduce the life time expectancy
to 0-5 years. There shall be no addtional organic coating on the TSA in order to be able to use the
suggested coating brakedown data in Table B-1.
DNV GL AS
APPENDIX C PROBABILITY OF FAILURE ASSESSMENT WATER
WETTING BARRIER
DNV GL AS
Figure C1 Decision logic for probability of water exposure
C.3.1 Location
This criterion is divided into two categories:
1) Exposed to water:
a) outdoor in geographic area subjected to rain, sea spray or regular deluge testing
b) indoor or outdoor subjected to regular deluge testing, mist or other sources of water
c) process system with temperature below dewpoint.
2) Not exposed to water:
a) this is a dry area with no probable water sources and above dewpoint temperature.
DNV GL AS
Poor design of cladding:
— Cladding solutions that are not referenced in applicable standards and have proven to have low capacity
for water proofing in practical use.
DNV GL AS
Cladding solution Waterproofing Comment
Note:
1) GRE cladding is recommended to be coated to prevent the breakdown of GRE caused by UV exposure.
2) SS 316 (301/302) cladding without sealing will have poor waterproofing properties.
3) Single cladding with PVC tape less than 10 years old can have normal waterproofing properties.
Insulation cladding is multifunctional where mechanical protection and weatherproofing are as important
as the improved waterproofing. Weatherproofing reduces exposure to water, and also protects organic
materials underneath the insulation from sunlight (UV radiation) degradation. Both mechanical protection
and weatherproofing will improve the waterproofing of the insulation system, but sealing of joints/openings is
also important to achieve acceptable waterproofing.
Guidance note:
An independent QA/QC system should be enforced to follow up and ensure that the expected waterproofing properties are
achieved.
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
Calcium silicate (type I) 65 650 Yes Water absorbent and drainage is not very effective.
Calcium silicate (type II) 650 980 Yes Water absorbent and drainage is not very effective.
Perlite 65 650 Yes Water absorbent and drainage is not very effective.
Mineral wool 20 650 Yes Water absorbent and drainage is not effective.
DNV GL AS
Insulation material type Temperature Water Comment
range °C absorbent
material
Fiber glass 65 480 Yes Water absorbent and drainage is not effective.
Hydrophobic 65 760 Yes Water absorbent and drainage is not very effective.
microporous blanket
Needled Eglass 65 650 Yes Water absorbent and drainage is not effective.
Cellular glass 270 480 No Closed cells - not water retaining. Water can be trapped if
wrong mounting and lack of drainage from cladding.
1) 2)
Silica aerogel (type I) 270 120 Yes Water absorbent and drainage is not very effective.
2)
Silica aerogel (type III) 65 675 Yes Water absorbent and drainage is not very effective.
1)
Polyisocyanurate (PUR/ 185 175 No Closed cells - not water retaining. Water can be trapped if
PIR foam) wrong mounting and lack of drainage from cladding.
Phenolic foam 155 150 No Closed cells - not water retaining. Water can be trapped if
wrong mounting and lack of drainage from cladding.
1) Some types of aerogel contain alkaline corrosion inhibitor that can represent a threat to TSA.
2) Aerogel is defined as water absorbent (ASTM C1728), but tests by the industry have proven that water retention is
less than 8% for some products.
---e-n-d---o-f---n-o-t-e---
C.5 Complexity
The water wetting PoF may be affected by the complexity of the insulated equipment or system. As an
option, complexity can be added to the water exposure evaluation. A potential way of implementing such
additional criteria may be to adjust the water exposure one PoF category higher for complex systems/pipes
and one category lower for less complex (straight) pipes.
To differentiate complexity categories, the number of elements such as change of direction and/or change
of dimension, supports and branch connections may be used. Complexity shall reflect the number of weak
points for water ingress through the cladding.
DNV GL AS
C.6 Workmanship
Insulated objects shall be sorted into three categories, ranging from low to high probability of a breach of
waterproofing, based on the workmanship of the insulation and cladding work and the follow-up regime for
QA/QC of insulation and cladding. The decision criteria are:
1) Work performed in accordance with specification and best industry practice.
2) Inspection and maintenance programme.
3) Time since installation of insulation solution.
Based on the different responses, the decision logic is given in Figure C2.
Figure C2 Decision logic for probability of breach of waterproofing as a function of maintenance
and workmanship
DNV GL AS
C.6.2 Inspection and maintenance routines
The inspection and maintenance routines can be sorted into three categories:
No inspection and maintenance programme:
no plans for inspection and maintenance during the next 8 years.
Weak inspection and maintenance programme:
— Damaged (leaking) waterproofing will not be detected within 4 years after the damage. An example of
an inspection program can be a general visual inspection every two years or close visual inspection of
cladding every 4 years. It is assumed that damaged waterproofing is repaired as it is revealed. Repair in
this context means removing of all wet/humid insulation and replacing it with new insulation and cladding
of the same or better quality as the previous one.
DNV GL AS
APPENDIX D PROBABILITY OF FAILURE ASSESSMENT DESIGN
BARRIER
The probability of loss of containment due to CUI will depend on the layout of the object and the wall
thickness of the pipe/vessel.
Statistics from the oil and gas industry indicate that a major part of the CUI leaks on piping are on small
bore pipes with a diameter of less than 4", and this is further backed-up by the knowledge that small-bore
piping will be more difficult to insulate and coat with the correct quality. Small-diameter piping also tends to
have a thinner wall thickness. A high PoFdesign is assigned to equipment with a nominal wall thickness of less
than 8 mm or piping with less than 4" outer diameter.
Based on this knowledge, small-bore and thin-walled piping should be given extra attention. This is reflected
as high or low in Table D-1.
DNV GL AS
Table D1 PoFdesign divided into high or low as a function of pipe schedule and diameter
NDT is often used to confirm the wall thickness. An NDT inspection can be used to further detail PoF for the
design barrier. The detailing of the design barrier based on the schedule and inspection results is given in
Figure D1.
DNV GL AS
Figure D1 Decision logic for design barrier
DNV GL AS
APPENDIX E PROBABILITY OF FAILURE GUIDANCE ON INPUT
DATA
This appendix summarizes what data to collect and the quality impact of these data on all four barriers
applicable for CUI.
Guidance and the data types to be collected for PoF assessment is found in Table E-1.
Operational °C
X X X
temp.
Temp. Δ °C
X X
fluctuation
Coating Confirmed
application good,
X
quality Unknown
or poor
Dew point °C
dependent
on X
geographic
location
DNV GL AS
Data type Data Material Coating Water Design Comment
format barrier barrier wetting barrier
barrier
Insulation Water
type retaining
or water
X
repellent/
good
drainage
DNV GL AS
APPENDIX F SUSCEPTIBLE AREAS FOR CORROSION UNDER
INSULATION
Table F1 List of hotspots and their relevance to the different CUI barriers
Field joints X X
Complex geometries X X X
Penetration to cladding/weatherproofing X X X
Branch connections X X X
DNV GL AS
For a more extensive list of hot-spots, see chapter 5 of API 583 /1/ or chapter 5 of EFC no. 55 /2/.
Guidance note:
It is recommended to remove or avoid insulation in hot-spot areas.
---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e---
DNV GL AS
CHANGES – HISTORIC
Changes – historic
There are currently no historical changes for this document.
DNV GL AS
About DNV GL
DNV GL is a global quality assurance and risk management company. Driven by our purpose of
safeguarding life, property and the environment, we enable our customers to advance the safety
and sustainability of their business. We provide classification, technical assurance, software and
independent expert advisory services to the maritime, oil & gas, power and renewables industries.
We also provide certification, supply chain and data management services to customers across a
wide range of industries. Operating in more than 100 countries, our experts are dedicated to helping
customers make the world safer, smarter and greener.