ACTION PLAN ON THE CONSTRUCTION OF COMFORT ROOM FOR MALE


GRADE II
2017-2018
ACTIVITIES/ PERSONS BUDGET EXPECTED
OBJECTIVE TARGET DATE
STRATEGIES INVOLVED AMOUNT SOURCE OUTPUT
1. Meet the parents and
Parents
collect/present ideas in First week of Meeting
Teachers January 2016
constructing comfort Conducted
Constructor
room for male
Parents
Third week of Agreement
2. Finalize the agreement Teachers January 2016
Increase the finalized
Constructor
awareness on February 2016
3. Preparation of Teacher Construction is
gender sensitivity
Construction Materials Constructor ongoing
4. Costruction of the March 2016 Comfort room
Laborer 6,000.00 Elementary 2017
Comfort room constructed
5. Prepare and submit Accomplishment
accomplishment report Teacher June 2016 report prepared
of the project and submitted

Prepared by:

RHODALYN N. REYES
Grade II-A Adviser
Noted:
AMALIA P. BARBERO, Ed. D
Principal III

Republic of the Philippines


Department of Education
Region 02
Schools Division of Cauayan City
Cauayan East District
MALIGAYA ELEMENTARY SCHOOL
Maligaya, Cauayan City

ACTION PLAN ON THE RENOVATION OF LAVATORY IN


GRADE II-A CLASS
2016-2017
ACTIVITIES/ PERSONS BUDGET EXPECTED
OBJECTIVE TARGET DATE
STRATEGIES INVOLVED AMOUNT SOURCE OUTPUT
1. Meet the parents and Parents
First week of Meeting
collect/present ideas in Teachers March 2017 Conducted
renovating of lavatory Constructor
Parents
Second week Agreement
2. Finalize the agreement Teachers March 2017 finalized
Constructor
RENOVATION First week of
3. Preparation of Teacher Renovation is
OF LAVATORY May 2017
Construction Materials Constructor ongoing
Second week of Elementary Day Lavatory
4. Renovation of lavatory Laborer May 2017 10,545.00
2017 renovated
5. Prepare and submit Accomplishment
accomplishment report Teacher June 2017 report prepared
of the project and submitted

Prepared by:

RHODALYN N. REYES
Grade II-A Adviser
Noted:
AMALIA P. BARBERO, Ed. D
Principal III

Republic of the Philippines


Department of Education
Region 02
Schools Division of Cauayan City
Cauayan East District
MALIGAYA ELEMENTARY SCHOOL
Maligaya, Cauayan City

ACTION PLAN ON THE REPAIR OF COMFORT ROOMS FOR MALE AND FEMALE
GRADE II-A CLASS
2017-2018
ACTIVITIES/ PERSONS BUDGET EXPECTED
OBJECTIVE TARGET DATE
STRATEGIES INVOLVED AMOUNT SOURCE OUTPUT
1. Meet the parents and
collect/present ideas in Parents
First week of Meeting
repairing of comfort Teachers March 2017 Conducted
rooms for male and Constructor
female
Parents
Second week Agreement
INCREASE THE 2. Finalize the agreement Teachers March 2017 finalized
AWARENESS Constructor
ON GENDER 3. Preparation of Teacher First week of Repair is
SENSITIVITY Construction Materials Constructor May 2017 ongoing
4. Repair of Comfort Second week of
May 2017 Elementary Day Repaired
Rooms For Male and Laborer 6,770.00
2017 Comfort Rooms
Female
5. Prepare and submit Accomplishment
accomplishment report Teacher June 2017 report prepared
of the project and submitted
Prepared by:

RHODALYN N. REYES
Grade II Adviser
Noted:

AMALIA P. BARBERO, Ed. D


Principal III
Republic of the Philippines
Department of Education
Region 02
Schools Division of Cauayan City
Cauayan East District
MALIGAYA ELEMENTARY SCHOOL
Maligaya, Cauayan City

ACTION PLAN ON THE CONSTRUCTION OF PLANT BOX


AT READING PARK
2017-2018
ACTIVITIES/ PERSONS BUDGET EXPECTED
OBJECTIVE TARGET DATE
STRATEGIES INVOLVED AMOUNT SOURCE OUTPUT
1. Meet the parents and
collect/present ideas in Parents
First week of Meeting
repairing of comfort Teachers August 2017 Conducted
rooms for male and Constructor
female
BEAUTIFICATI Parents
ON OF Second week Agreement
2. Finalize the agreement Teachers August 2017
READING finalized
Constructor
PARK First week of
3. Preparation of Teacher Repair is
Construction Materials Constructor September 2017 ongoing
4. Construction of Plant Second week of Homeroom Construction of
Laborer September 2017 4,300.00
Project
Box at Reading Park Plant Box
5. Prepare and submit Teacher Accomplishment
accomplishment report October 2017 report prepared
of the project and submitted

Prepared by:

RHODALYN N. REYES
Grade II Adviser
Noted:

AMALIA P. BARBERO, Ed. D


Principal III

Republic of the Philippines


Department of Education
Region 02
Schools Division of Cauayan City
Cauayan East District
MALIGAYA ELEMENTARY SCHOOL
Maligaya, Cauayan City

ACTION PLAN ON THE IMPROVEMENT OF LAVATORY IN


GRADE II-A CLASS
2018-2019
ACTIVITIES/ PERSONS BUDGET EXPECTED
OBJECTIVE TARGET DATE
STRATEGIES INVOLVED AMOUNT SOURCE OUTPUT
RENOVATION 1. Meet the parents and Parents/
First week of Meeting
OF LAVATORY collect/present ideas in Teachers/ March 2018 Conducted
renovating of lavatory Constructor
Parents/
Second week Agreement
2. Finalize the agreement Teachers/ March 2018 finalized
Constructor
3. Preparation of Teacher/ First week of Renovation is
Construction Materials Constructor April 2018 ongoing
4. Renovation of lavatory Laborer Second week of 9, 950 Elementary Day Lavatory
May 2018 2017 renovated
5. Prepare and submit Accomplishment
accomplishment report Teacher June 2018 report prepared
of the project and submitted