FIG TREE GARDENS -ROOF LABOUR (STEEL WORKS)

Works Description Unit Qty Rate Amount

Fabrication & Erection of Trusses,&Purlins average Sum 1 38,750 38,750.00


A
4800mm high above ground level

Fabrication & Erection of Ms steel fascia boards on the Sum 1 14,500 14,500.00
B estate side ,& gutters /down pipes average 4800mm high
above ground level

C Apply primer coat before erection Kgs 631 8 5,048.00

D Fix into place roofing sheets SM 28 250 7,000.00

Sub- Total Labour 65,298.00