CHAPTER 1
GENERAL
1.1 INTRODUCTION
1.1.1 Scope
The Design Criteria give the requirements for the design and detailing of all
Civil Engineering Works for the Land Transport Authority.
1.1.2 Definitions
The term Engineer used in the Design Criteria refers to the Engineer
appointed by the Authority for the purposes of the Contract. Where the
Conditions of Contract require instead that a Superintending Officer be
appointed for the purposes of the Contract, the term Engineer in this
Specification shall refer to the Superintending Officer so appointed by the
Authority.
The use of the terms “rapid transit”, “stations” etc, shall be taken to apply to
all guided systems, whether MRT or LRT, whether steel on steel or rubber
tyres on guideways, unless specifically stated otherwise or agreed otherwise
with the Engineer.
All designs shall comply with relevant regulations, Building Control Act and
Fire Safety Act.
The design shall take into account any constraints or effects imposed by the
existing and planned works and services in the surrounding areas, and
works of other nearby developments.