Professional Documents
Culture Documents
Mem Project Planning and Control - Pre 833
Mem Project Planning and Control - Pre 833
AND CONTROL
Assignment
PGENG 8600402
i. Draw the network diagram and calculate the normal project duration.
ii. Using a step by step crashing algorithm reduce the project duration from normal
condition to fully crashed condition and tabulate the total cost and activities involved at
each stage of the project time reduction.
Solution
i.
A (4 days) E (5 days)
D (3 days)
B (6 days) G (6 days)
C (2 days) F (4 days)
The various paths are isolated and the duration indicated to confirm the total duration.
A – E : 4 + 5 = 9 days
A – D – G : 4 + 3 + 6 = 13 days
B – G : 6 + 6 = 12 days
C – F : 2 + 4 = 6 days
We need to establish the critical path duration as this indicates the normal project
duration.
The critical path is A – D – G and the duration is 13 days.
Hence the normal project duration is 13 days
We select activity G over A and D for crashing because it has the lowest cost slope and the
highest number of days it can be crashed.
Iteration 0
Path Duration
A–E 9
A–D–G 13
B–G 12
C–F 6
Iteration 1
Path Duration
A–E 9
A–D–G 12
B–G 11
C–F 6
Iteration 2
Path Duration
A–E 9
A–D–G 11
B–G 10
C–F 6
Iteration 3
Path Duration
A–E 9
A–D–G 10
B–G 9
C–F 6
Iteration 4
Path Duration
A–E 9
A–D–G 9
B–G 8
C–F 6
Now there are two critical paths. To finish the project earlier, we would need to shorten
both paths. Crashing A, A – D, E – A or E – D does this, since those two activities are on
both paths.
Now there is one critical path B – G. To finish the project earlier, we would need to
shorten this paths.
Iteration 5
Path Duration
A–E 7
A–D–G 7
B–G 8
C–F 6
Iteration 6
Path Duration
A–E 7
A–D–G 7
B–G 7
C–F 6
Iteration 7
Path Duration
A–E 6
A–D–G 6
B–G 6
C–F 6